COMMISSION AGENDA – Action Item No. __8b__ Page 4 of 9
Meeting Date: April 23, 2019
Template revised September 22, 2016; format updates October 19, 2016.
(4) Demolish and replace the entire C25 BHS from the underground tunnel to the Ramp
level at the South Satellite. This adds additional outbound lines in the existing
baggage tunnel, replaces two (2) makeup units, provides future availability for
manual encode and demolishes the existing claims in the Federal Inspection Services
(FIS) area;
(5) Construct the new North-End odd-size BHS (Zone 7);
(6) Demolish C22 odd size BHS;
(7) Construct C92 BHS final connections;
(8) Remove and decommission various existing BHS components;
(9) Demolish and install BHS make-up devices;
(10) Construct a new tenant storage area in the C1 building basement;
(11) Relocate the existing tenant storage area from the Central Terminal Expansion (CTE)
basement level to the new area in the C1 building;
(12) Relocate, modify and add new structural, architectural and utility systems;
(13) Construct a new maintenance conveyor shop;
(14) Relocate and demolish the existing maintenance conveyor shop;
(15) Construct, modify and demolish various construction elements, such as wall, ceiling,
flooring and finish work; and
(16) Perform various Regulated Material abatement.
Schedule: Phase One
Based on the most current contractor schedule, Phase 1 is approximately 3 months behind
schedule. Holding this schedule would place Phase 1 Substantial Completion in 2019 Quarter 4.
The contractor delay can be attributed to late conveyor submittals and lagging equipment
fabrication, along with further delay caused by a failed factory acceptance test, and water
damaged EDS machine replacement.
While the contractor schedule shows the project approximately 3 months behind schedule, the
Port project team feels that the project is six months behind schedule due to the contractor
delays. This does not include any delays resulting from the damaged EDS machines. These
delays are being assessed and are critical to the project schedule. Delays will be added to the
project schedule once they are determined.
While the current delay to the project is likely unrecoverable, the project team is working to
eliminate further delay. To address the performance and schedule concerns, the team has
implemented the following:
Three additional design review meetings were held to help the contractor understand
the project requirements.
Port staff was sent to Denver to meet with both the contractor and designer in order to
speed up critical submittal reviews.
Multiple letters have been issued documenting the delay caused by the contractor.
The project team now meets on-site with the contractor’s executives quarterly to
discuss ways to mitigate the schedule delays. Actions resulting from these meetings: