COMMISSION AGENDA – Action Item No. ____ Page 2 of 5
Meeting Date: April 23, 2019
Template revised September 22, 2016; format updates October 19, 2016.
This project was not included in the 2019-2023 capital budget and plan of finance. A budget
was transferred from the Aeronautical Allowance C800753 and the funding source is the Airport
Development Fund.
JUSTIFICATION
This project is critical to the expansion and renovation of North Satellite. The NorthSTAR
program is in line with the Century Agenda goals of 1) Advancing this region as a leading
tourism destination and business gateway by encouraging cost-effective expansion of domestic
and international passenger and cargo service and 2) Be the greenest and most energy efficient
port in North America.
The construction project at the North Satellite will close existing gates which will need to be
relocated. It is expected that Alaska will operate multiple ground boarded flights each day at
this hardstand. Additionally, this facility is available to all airline employees who have flights
operating at the hardstand.
DETAILS
This facility and the ground boarding operations at Cargo 5 are an interim solution until the
Sustainable Airport Master Plan (SAMP) is implemented (approx. 10 years). The facilities are
required as part of the NSAT construction impact mitigation plan in the near term (summer
2019 through NSAT completion in late summer/early Fall 2021).
A pre-fabricated trailer will be set on the edge of pavement at Cargo 5. It will be connected to
site utilities to provide a break room and toilet(s) for operating employees only. It is not
intended for passenger use. No additional parking or further expansion is intended.
Scope of Work
The scope of work includes the following key elements:
• pre-fabricated modular structure (trailer) to accommodate 15 to 20 ground crew members
with weather shelter, break room, and lavatory
• facility designed to address Port concerns re: security, accessibility, durability, location
(minimum ramp footprint), and common use by airlines operating at Cargo 5
• development of a temporary solution (e.g., tent and portable toilet cabinets – short term fix
until trailer can be set and connected, included in budget as contingency) will likely be
required concurrent with execution of this scope to meet NSAT’s construction impact
mitigation plan requirements
Diversity in Contracting
Work will be executed using Small Works contracts through PCS.