COMMISSION AGENDA – Action Item No. ____ Page 2 of 5
Meeting Date: April 23, 2019
Template revised September 22, 2016; format updates October 19, 2016.
The parallel effort that is looking into whether the need for remediation of any of the assets
being renewed could be attributed to design (Error and Omission) or construction (Latent
Defect) is still ongoing. Additional information on the progress of this effort is provided in the
“Additional Background” section of the memo.
JUSTIFICATION
The project scope includes several major maintenance improvements for the facility that the
Port has the responsibility to complete under the terms of the RCF Lease Agreement. The
Operators have requested that the Port complete these improvements as expeditiously as
possible since many are essential to their operations. Completing the perimeter fence in a
timely manner is also essential to ensure the safe and secure operations of the facility. This
project supports the Port’s Century Agenda strategy of advancing this region as a leading
tourism destination and business gateway by meeting the region’s air transportation needs at
Sea-Tac Airport for the next 25 years.
DETAILS
The project will be completed in two phases. Phase one consisted of the early replacement of
critical portions of the fifth floor topping slab in support the Operators’ request for expeditious
action and was completed in October 2018 by Port Construction Services (PCS). Phase two
includes the remaining scope.
The project scope has been modified during the design phase. The scope decreased with the
reduction in area for the replacement of the fifth floor topping slab since testing proved it was
not as damaged as originally thought. The scope increased to include the replacement of
existing perimeter site fencing with a 10-foot no-climb fence to address site security concerns
and resealing the fifth floor employee and visitor parking areas to address weather proofing
and safety concerns at these locations.
Diversity in Contracting
Project staff worked with the Economic Development Division – Diversity in Contracting
Department and determined this contract will have an eight percent WMBE aspirational goal.
Scope of Work
The project will complete the major maintenance improvements described below.
(1) Replace and upgrade the fifth floor expansion joints in the bus operation area
(2) Replace and upgrade portions of the fifth floor topping slab in the bus operation area
due to excessive cracking and spalling
(3) Route and seal cracks in the deck and beams of both Helices
(4) Complete pavement rehabilitation on the existing S. 160
th
St. driveway
(5) Replace the weatherproofing membrane at carwash areas at the RCF located on the
second and fourth floors of the facility
(6) Replace existing perimeter fence with a 10-foot no-climb fence