COMMISSION AGENDA – Action Item No. 6e Page 2 of 9
Meeting Date: March 26, 2019
Template revised September 22, 2016; format updates October 19, 2016.
southbound lanes of the Northern Airport Expressway (NAE) will likely impact access to the
Doug Fox Parking Lot in 2024 and as early as 2023. Construction phasing for SAMP projects will
be refined as projects move through more detailed planning and design. Given the inherent
uncertainty of construction phasing at this current level of planning and project definition, Port
staff believes that the best use of this property in the near-term is continued use as a parking
facility and that the best financial return to the Port is via an amendment to the current lease
with ATZ. This lease is expected to generate over $16 million in non-aeronautical revenue
during the proposed five-year term of this option period.
JUSTIFICATION
The Doug Fox Parking Lot has been used primarily for airport parking since its development well
over 30 years ago. Although it is an “off-airport” site, the property has the advantage of being
relatively close to the Airport with a convenient approach for customers from the Northern
Airport Expressway as well as convenient access to the Airport for the operator’s shuttle vans
bringing customers to and from the Airport (Attachment 1). The lot provides the Airport with a
facility that competes in the off-airport parking market where prices are lower, while the Airport’s
main parking garage commands higher rates based on the value of its proximity to the terminal.
On May 22, 2012, the Commission authorized proceeding with design for pavement renewal
and replacement, a new and improved lighting system, new signage to improve visibility of the
facility, demolition of the existing building, and construction of a new building on this property
referred to as the Doug Fox Parking Lot Services Upgrade Project. These improvements were in
addition to a new drainage system for the property that was authorized by the Commission on
February 14, 2012.
Following those Commission actions, Port staff initiated a public RFP process for an operator of
the improved facility in anticipation of the expiration of the then-current lease with ATZ in
September 2012. The RFP was advertised broadly in various local, national, and industry-
specific publications. However, ATZ was the lone respondent that met the minimum
qualifications. ATZ is a locally-owned and operated small business that has over 30 years of
experience managing parking operations in the local airport market. The Commission approved
a lease with ATZ on July 9, 2013, that included a five-year term as well as two five-year options.
In September 2014, ATZ submitted a claim for harm suffered from changes to the construction
schedule for the Doug Fox Parking Lot Service Upgrade Project. Later that fall, an audit
identified that ATZ had failed to complete the divestiture of its ownership in another parking
facility located within three miles of the airport within the timeframe granted to it by the Port,
as was required by the RFP issued in 2012. On June 9, 2015, the Commission approved the first
amendment to the lease with ATZ that incorporated revised terms negotiated between ATZ and
the Port to account for the negative impacts of the delayed construction of the Doug Fox
Parking Lot Services Upgrade Project and that reflected both parties roles in these delays as
well as the delayed divestiture by ATZ.
The first five years of this lease have produced significant revenues to the Port, exceeding the
minimum annual guarantee (MAG) each year as noted in the table below.