Item No. 9c_supp Meeting Date: February 26, 2019 Baggage Optimization Fourth Quarter Briefing and Project Update AGENDA • • • • • • • • Project Overview 2018 Quarter 4 Update Budget Schedule Challenges Accomplishments Progress Sustainability Baggage Optimization Project 2 PROJECT OVERVIEW • Replaces six individual baggage screening systems with a centralized system that optimizes the operation and functionality of the checked baggage system Key elements: • 60 Million Annual Passengers (MAP) • Reliability • Redundancy • Security Complete Overhaul of Outbound System 3 2018 Q4 Update • Schedule - Contractor Fell Behind on Submittals and Fabrication • Phase 1: - Contractor Maintaining Two Work Shifts (Mon. through Sat.) - Conveyor Installation is ongoing (Critical Path) • Phase 2: - 100% Design Documents completed - Permit set has been submitted to Building Department - Developing Phase 2 Bid Documents & estimate Phase 1 Schedule Concerns 4 FINANCIAL PROGRESS REPORT Millions Authorization Summary Capital Expense Total Current Budget $444.90 M $0.15 M $445.05 M $400 Current Authorization $136.16 M $0.15 M $136.31 M $350 Amount Remaining to be Authorized $308.74 M $0 M $308.74 M $450 $300 $250 Total Project (Capital + Expense) $200 $150 Budget Spent to Date Forecast at Completion Variance $100 Soft Cost $64.99 M $23.20 M $64.99 M $0 M $50 Construction $359.43 M $41.41 M $359.43 M $0 M Management Reserve $20.63 M $0 M $20.63 M $0 M $445.05 M $64.62 M $445.05 M $0 M $Management Reserve Remaining Construction Spent Soft Cost Spent Financial Breakdown Construction Remaining Soft Cost Remaining 5 FUNDING CONTRIBUTION (Port Contribution to Date $33.7M) Port $351M 79% TSA $94M 21% TSA OTA/LOI Reimbursement (TSA Contribution to Date $30.9M) Total Project Budget Total TSA Contribution Total Port Contribution Amount Spent to Date TSA Reimbursement to Date $445,050,000 $94,043,296 $351,006,704 $64,621,035 $30,899,397 6 SCHEDULE Contractor Delay Extends Overall Completion Date 7 SMALL BUSINESS/APPRENTICESHIP UTILIZATION SCS/SBE APPRENTICESHIP Overall (15%) SBE Const (15%) Women (10%) Minority (15%) SCS Const (5.0%) 0.0% 50.0% 100.0% Goal 150.0% 200.0% Actual Tracking Close to or Exceeding Goals - status as of January 2019 0.0% 50.0% 100.0% 150.0% 200.0% Goal Actual 8 CHALLENGES • Phase 1 Construction Schedule • Baggage Handling/Steel Market Conditions for Phase 2 Bid • Operational Impacts Through Construction • IAF Coordination - Must be operational prior to Phase 2 SSAT construction • Project Coordination - Have coordinated with 60+ projects so far Overcoming Challenges 9 COST INCREASES SINCE 2013 ESTIMATE • 15% Increase (Adjusted for Inflation) in Domestic Baggage Projects (Estimate from Baggage Designer) • Material Cost of Structural Steel and Metals Increased 25% in 2018, as a Reaction to the Tariffs • Construction Market Escalation Averaged 5% per year since 2013 (Approximately 25% Over 5 Year Period) Cost / Market Conditions 10 ACCOMPLISHMENTS • All conveyor equipment delivered and stored at warehouse. • Phase 2 permit set has been submitted to Building Department. • Structural steel on Central Terminal bump out has been completed. • Purchased and received baggage handling network equipment. • Conveyor Factory Acceptance Retest conducted and successful. • Continued construction on conveyors, utilities and infrastructure. Baggage Optimization Construction Progress 11 SUSTAINABILITY Energy Conservation Optimized system is projected to result in up to 30% energy savings Water Conservation No opportunity Working Environment Improved ergonomics Waste Reduction Contractual requirement to recycle demolished material when possible Opportunity in Energy Conservation 12 T106 Warehouse Space 13 New Conveyor Sections 14 Structural steel on Central Terminal Bump Out 15 Factory Acceptance Testing Facility- Detroit, MI 16