
COMMISSION AGENDA – Briefing Item No. _9c___ Page 2 of 6
Meeting Date: February 26, 2019
Template revised September 22, 2016.
International Airport. The purpose of this project is to optimize the baggage system to achieve
the maximum outbound baggage capacity within the current airport footprint. The project
increases screening capacity for greater baggage volumes, increases flexibility to allow bags to
be checked in from any ticket counter and be conveyed to serve any gate, meets the
established minimum-connect-time goal, and increases energy efficiency. Additional benefits
include increased reliability, redundancy, and security. Meeting travelers’ baggage needs will
significantly contribute to increased customer service, and address growing passenger demands
of the region. The project is currently scoped to accommodate 60 million annual passengers
(MAP).
The project is being bid and constructed in three separate phases. Phase 1 is currently on
budget but has recently experienced schedule setbacks of an estimated three to six months.
The biggest risks to future phases of the project are Phase 1 schedule delays and baggage
handling market conditions affecting Phase 2 and 3 bids.
PROJECT UPDATE
Phase One
Notice to Proceed was issued to the Phase 1 prime contractor, PCL Construction Services Inc.,
on May 26, 2017. Construction is currently underway, including the following activities and
accomplishments:
(1) Conveyor Factory Acceptance Retest has been successfully completed.
(2) All conveyor equipment has been delivered to Seattle and stored at provided
warehouse location.
(3) Structural steel has been installed at the Central Terminal to create additional
building space on ramp level.
(4) Conveyor installation is scheduled to be complete in May.
(5) Construction on utilities and infrastructure continues.
(6) Network hardware equipment for baggage handling system has been purchased and
delivered.
Upcoming critical elements include conveyor installation, computer programming, and
completion of the new baggage system control room.
On-going stakeholder coordination continues to be essential, particularly with other projects,
Aviation Maintenance, and airport tenants.
The contractor has increased work shifts from five to six days per week. As of the latest
December pay application, 103,726 work hours have been reported and work completed is
estimated to be 73 percent.