AGENDA MEMORANDUM
Item No.
7b
BRIEFING ITEM
Date of Meeting
February 26, 2019
DATE: February 15, 2019
TO: Stephen P. Metruck, Executive Director
FROM: Dave Soike, Chief Operations Officer
Eileen Francisco, Senior Manager AV Capital Program
SUBJECT: International Arrival Facility Progress Briefing
EXECUTIVE SUMMARY
This briefing is in response to the Commission motion of September 2018 requesting periodic
briefings regarding the construction status of the International Arrivals Facility (IAF).
This briefing will cover the cost and schedule status of the IAF program, in addition to a briefing
from Clark Construction on construction progress and an update from the Commission’s lead
Expert Review Panelist who will provide observations from its continuing assessment of the
program.
IAF’s scope includes a new 450,000 square foot arrivals building that can process 2,600
passengers during the busiest hour of the day, a connecting international corridor and a 760’
pedestrian walkway. It creates 20 international gates and includes seven bag claim devices and
forty CBP office processing podiums. IAF is under construction with structural steel and
concrete slabs complete for the main building and curtain wall construction well
underway. Structural steel has started for the center span of the pedestrian walkway offsite at
Air Cargo 2 and two of the four vertical circulation pods” for the international corridor are
finished. Management reserves have not yet been expended. The project is currently on track
to complete within its authorized GMP on May 30, 2020.”
ATTACHMENTS TO THIS BRIEFING
(1) Presentation slides
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
September 25, 2018 - Authorized a Guaranteed Maximum Price (GMP)
September 11, 2018 The Commission received a comprehensive briefing regarding the
program and Guaranteed Maximum Price negotiated with the design-builder.
March 27, 2018 The Commission was briefed on IAF progress.
November 14, 2017 The Commission was briefed on 3
rd
quarter 2017 progress.
August 15, 2017 The Commission authorized the balance of IAF funding in a joint request
with the NSAT project.
COMMISSION AGENDA Briefing Item No. __7b__ Page 2 of 3
Meeting Date: February 26, 2019
Template revised September 22, 2016.
March 28, 2017 - The Commission authorized additional IAF funding.
October 11, 2016 The Commission authorized IAF to add balance of Phase 2 for
accelerated execution.
September 27, 2016 The Commission was briefed on IAF reconsidering phasing and project
update.
September 13, 2016 The Commission authorized IAF FAA reimbursement agreement.
July 12, 2016 The Commission authorized IAF to add Phase 2 scope to meet continuing rapid
growth.
June 28, 2016 The Commission was briefed on two additional international aircraft gates at
IAF to meet continuing rapid growth briefing.
May 17, 2016 The Commission was briefed on Plan of Finance update.
April 26, 2016 The Commission was briefed on IAF 1Q2016 update.
February 9, 2016 - The Commission was briefed on IAF 4Q2015 update.
December 8, 2015 IAF Guaranteed Maximum Price (GMP) Development Period
authorization (presented in combination with NSAT authorization request).
November 10, 2015 The Commission was briefed on IAF update.
August 11, 2015 The Commission lead a special meeting, roundtable with airline
representatives.
July 28, 2015 The Commission lead an IAF forum.
July 14, 2015 The Commission lead an IAF forum.
June 23, 2015 The Commission authorized execution of the IAF Design-Build Contract.
May 26, 2015 The Commission approved IAF preliminary funding plan motion.
April 28, 2015 The Commission authorized a service agreement for Commissioning
Services.
April 28, 2015 The Commission authorized execution of a lease agreement with SEATAC
VENTURES 2010 LLC for IAF program management office space near Sea-Tac International
Airport.
February 24, 2015 The Commission authorized a service agreement for IAF consultant
program leader.
January 27, 2015 The Commission was briefed on IAF funding plan.
January 27, 2015 The Commission approved IAF request for proposals advertisement.
January 13, 2015 The Commission was briefed on IAF update.
December 2, 2014 The Commission was briefed on IAF scope and budget update.
October 28, 2014 The Commission was briefed on IAF 3Q2014 update.
August 19, 2014 The Commission was briefed on IAF 2Q2014 update.
August 5, 2014 The Commission authorized IAF request for qualifications advertisement.
July 22, 2014 The Commission was briefed on IAF progress.
June 10, 2014 The Commission was briefed on IAF 1Q2014 update.
May 6, 2014 The Commission was briefed on IAF project delivery.
April 22, 2014 The Commission was briefed on capital program.
March 11, 2014 The Commission authorized IAF master planning.
February 25, 2014 The Commission was briefed on IAF program.
COMMISSION AGENDA Briefing Item No. __7b__ Page 3 of 3
Meeting Date: February 26, 2019
Template revised September 22, 2016.
November 19, 2013 The Commission authorized IAF construction management, testing and
inspection; surveying and locating and safety service agreements.
July 23, 2013 The Commission authorized IAF project and program support; and price
factor design-build methodology.
July 9, 2013 The Commission was briefed on IAF.
July 9, 2013 The Commission was briefed on alternative public works contracting.
April 9, 2013 The Commission was briefed on IAF.
June 26, 2012 The Commission was briefed on airport terminal development challenges at
Seattle-Tacoma International Airport.
June 14, 2011 The Commission was briefed on international air service growth and future
facility.
February 2, 2010 The Commission was briefed on South Satellite passenger growth and
facility considerations, Delta’s proposed airline lounge and other possible future aviation
projects.