COMMISSION AGENDA – Action Item No. __6e__ Page 2 of 5
Meeting Date: February 26, 2019
Template revised September 22, 2016; format updates October 19, 2016.
expansion of domestic and international passengers and cargo service. This provides STIA with
much needed leasable space to meet the needs of our growing airline partners. It also supports
the Aviation Division’s financial performance by increasing occupancy of leasable space without
constructing new facilities.
Diversity in Contracting
For the immediate construction of Phase 1, staff anticipates a significant proportion of small
works contract work to be completed by small businesses which include woman and minority
businesses. For Phase 2, Women and Minority Business Enterprise (WMBE) aspirational goals
will be established by the Diversity in Contracting Department.
DETAILS
This project will be completed in two phases. The first phase will address an immediate need to
construct two office spaces for two new entrant airlines on the mezzanine level of the main
terminal. These spaces will be designed and constructed by this request. Additional space on
the Ticketing and Second Floor levels will be designed with a request for construction of these
spaces to follow in a future Commission request.
The work includes sub-dividing spaces where required, modifying heating, ventilation and air
conditioning (HVAC), electrical, communications and lighting systems, completing interior
finishes including ceilings and flooring, and installing Port standard telecommunications
demarcation packages.
The first space will be constructed in an expedited manner to provide two offices by Q2 2019,
which is needed to support recently announced service by two new Airlines. The remaining
spaces are needed to be able to respond to anticipated growth and will follow a more
traditional timeline.
Scope of Work
The project scope of work includes the following:
(1) Sub-dividing the existing vacant areas where required to provide manageably sized
offices meeting airline needs and Port standards
(2) Modifying heating, ventilation, and air conditioning (HVAC), electrical,
communications and lighting systems
(3) Constructing basic interior finishes including finished walls, ceilings, and flooring
(4) Installing a Port standard telecommunications demarcation package for new tenants
(5) Prepare related amenities as necessary or required by code
Office furnishings, equipment, and any discretionary tenant improvements will be provided by
the tenant and are not included in this project scope.