COMMISSION AGENDA – Action Item No. __8b__ Page 3 of 8
Meeting Date: January 22, 2019
Template revised September 22, 2016; format updates October 19, 2016.
Assessment (EA) are complete. The SAMP SEPA EIS/NEPA EA is anticipated to be complete by
early 2020 and the current project schedule does not require construction authorization until
Q4 2020.
On April 24, 2018, the Commission authorized the Airport Utilities Master Plan; the Widen
Arrivals Roadway project includes several risks associated with the development of this plan.
The Airport Utilities Master Plan may result in decisions to build a utility corridor under the
Arrivals approach roadway or to upgrade the primary water, storm drainage, or power
distribution systems under the roadways. Due to the work associated with the Airport Utilities
Master Plan, the construction will occur in two phases, under two separate construction
contracts, to help mitigate these risks. Phase I will provide the improvements necessary to
support the Phase II temporary roadways (detours), and Phase II will provide the temporary
roadways and permanent roadway improvements to support Airport operations. Both the
Phase I and Phase II construction contracts will utilize project labor agreements.
The total estimated cost to complete the Widen Arrivals Roadway project as currently defined
is $50 million. Since the Airport Utilities Master Plan risks can be significant if they occur and
changes to the project are needed, they will be treated as scope revisions requiring additional
Commission authorization. Future requests for Commission authorizations, and corresponding
budget increases, are planned to coincide with the phased implementation of this project and
would include any scope revisions.
Scope of Work
The Widen Arrivals Roadway project is a roadway improvement project. These types of
projects generally include paving, sidewalks, barriers/curbs, pavement markings, illumination,
storm drainage, retaining walls, signage, sign structures, safety elements (e.g. attenuators), and
Intelligent Transportation Systems (ITS) improvements. Key components of the project include:
(1) The widening of the southbound lanes of the Northern Airport Expressway to provide
an additional two lanes into the curbsides and Main Garage
(2) The demolition of the existing closed bridge from Departures to the 4th Floor of the
Main Garage
(3) The demolition of the remaining Bridge 5 ramp and abutment, construction of a
retaining wall to support the Departures approach roadway, and the relocation of the
north rental car bus curb further to the north
(4) The completion of the seismic retrofit of the north portal of the Service Tunnel,
consistent with work underway in other portions of the tunnel
(5) The construction of a retaining wall along the airfield north of the Service Tunnel and
the relocation of power, water, and natural gas infrastructure systems to support the
future temporary roadways (detours)
(6) The relocation of a portion of Air Cargo Road along the new airfield retaining wall