Late Night Noise Limitation Program
2
Draft language
3
Working Group: circulate draft language
4
Open discussions with FAA/Alaska/Delta on language
5
Update Working Group
12
Update StART
16
Define SEL Noise Thresholds
17
Conversations with FAA
18
Formal conversations with all airlines (station managers, AAAC, individual carriers)
19
Finalize language
20
Update Highline Forum
24
Update Commission
25
Develop new Fly Quiet materials
26
Implement program
27
Runway Use Agreement
28
Begin drafting runway use agreement
29
Working Group: circulate draft agreement
30
Open discussions with FAA/Alaska/Delta on language
31
Update Working Group
38
Update StART
42
Finalize language
43
Formal conversations with FAA
44
Update Highline Forum
48
Possible Environmental Review
49
Update Commission
50
Implement
51
Glide Slope Analysis
52
Begin definition of steps toward 34R glide slope implementation for conventional approach
53
Present the 34R glide slope level of effort, schedule and cost (conventional approach) to Working Group
54
Define steps toward 34R glide slope implementation for RNAV approaches only (all runway ends) and
conventional approaches for ends other than 34R (FAA assistance required)
55
Present the 34R glide slope implementation for RNAV approaches only (all runway ends) and conventional
approaches for ends other than 34R to Working Group
56
Update StART
60
Update Working Group
67
Determine path forward
68
Update Highline Forum
72
Update Commission
73
Airfield Noise/Reverse Thrust Study
74
Working Group: Present on reverse thrust, discuss opportunities to change the night time (and possibly
daytime) discouragement language
75
Working Group: Presentations on other sources of airfield noise including (but not limited to) taxi, and APU;
consultant presentation on identifying opportunities for ground noise reduction
76
Update StART
Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19
DRAFT/ROLLING NEAR TERM AVIATION NOISE ACTION AGENDA
StART AVIATION NOISE WORKING GROUP
2018/2019 Work Plan Draft
As of December 12, 2018
Page 1
Project: StART Aviation Noise W
Date: Thu 12/13/18
= Work Task/Activity Duration
= Not Yet Scheduled or Reoccurring Meeting