
COMMISSION AGENDA – Action Item No. 6h Page 2 of 5
Meeting Date: January 22, 2019
Template revised September 22, 2016; format updates October 19, 2016.
DETAILS
Docks 3 and 4 have moderate-to-major corrosion on a majority of their piling. This corrosion
within the water line/ splash zone has resulted in material loss ranging from 12 to 36 percent of
the steel pile that is needed for the structural integrity of the pile. Dock 5 is showing corrosion
only at the water line/splash zone with a material loss ranging from 3 to 4 percent. All piling
were coated when new, but all have corrosion deterioration within the water line / splash zone.
The material loss on Docks 3 and 4 piling will require preservation to prevent future corrosion.
All piling at Docks 3, 4, and 5 will be repaired by wrapping each pile within a protective outer
wrap barrier to isolate the steel from the elements causing the corrosion within the splash
zone, including the installation of a passive cathodic protection system by welding a sacrificial
anode to each pile. Cathodic protection is an electrochemical means of corrosion control, the
benefits of this system include minimum disruption to terminal operations and maintaining
economic vitality of the terminal as the wrap system is installed on the existing piles. The pile
wraps will be installed by divers who will clean and attach the wrap system in sections. This is
far less disruptive and more cost effective than the other options explored which would
generate a significant amount of construction demolition waste and emissions.
Scope of Work
Prevent future corrosion of the steel piling supporting Docks 3, 4, and 5 and provide corrosion
protection in the splash zone. The work includes:
1) Cleaning and preparing the existing 294 piling within the water line / splash zone.
2) Installing Outer Wraps on 294 piles at Docks 3, 4, and 5 within the splash zone with
additional wraps for various piling at the mud line.
3) Install and weld 294 cathodic protection anodes at Docks 3, 4, and 5 just below the wraps
and waterline.
Diversity in Contracting
Per the scope of work within the construction phase, WMBE firms within this field are limited.
0% is the goal for this work. With the support of project staff and the central procurement
office (CPO), the Diversity in Contracting Department is continuing to promote and outreach
this opportunity.
Schedule
Design was completed during the fourth quarter of 2018. Construction is anticipated to start in
the second quarter of 2019 with construction completed by Q4 2019/ Q1 2020. In-water work
will not be disrupted by the fish window making this decision the preferred design remedy as
this work can be installed at any time throughout the life of the project.
Commission design authorization