Item No. __6f_supp Meeting Date: January 22, 2019 Parking Garage Elevator Modernization Commission Meeting January 22, 2019 1 Parking Garage Elevator Modernization PG C PG D PG B PG A PG E Project Overview 1/15/2019 2 Parking Garage Elevator Modernization Phase 1: Elevator Vestibules and Lobbies • Design Complete: Q1 2019 • Construction Complete: Q1 2020 • Phase 1 Scope - - Weatherize the PGB and PGC Elevator Towers Refresh lobbies on all floors (PGB through PGE) Elevator Vestibules and Lobbies Summary 3 Parking Garage Elevator Modernization Phase 2: Elevator Mechanical and Electrical Systems • • • • • Renew all 27 Elevator Cabs in parking garage (PGA - PGE) Comprehensive renovation on all five elevators at PGB Comprehensive renovation on all five elevators at PGC Replace electrical drive systems on all five elevators at PGD Replace four of the five electrical drive systems at PGE Project Overview 4 Parking Garage Elevator Modernization • • • • • Begin Design Design Complete Commission Approval (Construction) Bid Construction Contract Construction Complete Phase 2 Project Schedule Q2 2019 Q2 2020 Q2 2020 Q3 2020 Q3 2023