COMMISSION AGENDA – Action Item No. 6d Page 2 of 5
Meeting Date: January 22, 2019
Template revised September 22, 2016; format updates October 19, 2016.
the first phase is finalized, a second phase for fencing intrusion detection will be brought
forward for authorization. The authorization request for this initial phase includes no funding
for the planned second phase.
Aviation Security, Information & Communication Technology (ICT), Aviation Maintenance
(AVM), and Port Construction Services (PCS) will collaborate to complete this project. Total cost
for this initial phase is estimated to be $3,520,000. Ten-year license and maintenance fees are
estimated at $420,000. Recurring license and maintenance costs will be budgeted within the
Aviation Maintenance department operating budget. The cost of both phases was included in
the 2019-2023 capital budget and plan of finance in the amount of $10,000,000.
JUSTIFICATION
Enhancements to our perimeter security have been identified as critical in ensuring public
safety and improving operational efficiencies through automation. The new system will be part
of a layered protection strategy that incorporates people, processes, and technology to
decrease security risk and increase situational awareness. When integrated with existing
security systems, it will provide a comprehensive picture to security and safety personnel and
facilitate coordinated responses.
The authorization for the first phase will provide for selected areas of the airport perimeter:
(1) Continuous monitoring for selected coverage areas.
(2) Algorithm-based threat assessment with the ability to proactively distinguish between
normal operations and a potential threat.
(3) Robust alerting capabilities.
(4) Directional tracking of potential intrusions enabling rapid responses to mitigate issues.
DETAILS
Scope of Work for First Phase
(1) Procure and implement a radar or similar technology solution to enhance perimeter
security for selected coverage areas.
(2) Integrate with existing security systems to provide a comprehensive picture and
operational efficiencies.
Schedule for First Phase
PIDS Hardware, Software, and Vendor Services