COMMISSION
AGENDA MEMORANDUM
Item No.
6b
ACTION ITEM
Date of Meeting
November 27, 2018
DATE: October 22, 2018
TO: Stephen P. Metruck, Executive Director
FROM: Michael Ehl, Director, Aviation Operations
Wayne Grotheer, Director, Aviation Project Management Group
SUBJECT: 2020 Airfield Pavement Replacement Projects (CIP # C800483)
Amount of this request:
$ 1,250,000
Total estimated project cost:
$13,100,000
ACTION REQUESTED
Request Commission authorization for the Executive Director to authorize design and
preparation of construction documents for the replacement of distressed pavements and
related utilities for the 2020 Airfield Pavement portion of the 2016-2020 Airfield Pavement
Replacement Program at the Seattle-Tacoma International Airport in the amount of $1,250,000,
and approve the use of a Project Labor Agreement (PLA) for this contract.
EXECUTIVE SUMMARY
This project is part of an ongoing Pavement Management and Maintenance Program (PMMP)
as required by the Federal Aviation Administration (FAA), and a recognized best practice to
provide a safe and operable pavement system. The focus of this program is to replace
distressed and damaged pavement on the airfield. This project will take advantage of these
replacements by also replacing in-pavement utilities and covers when it makes sense, as well as
removing abandoned utilities within the general work area. The project includes emergent
distressed areas on the airfield.
Replacing damaged pavement on the airfield supports the long-term strategy of the Port’s
Century Agenda objective to “Meet the region’s air transportation needs at Seattle-Tacoma
International Airport for the next 25 years.” The PMMP maintains the integrity of airfield
pavements and enables efficient airport operations. Deferring damaged pavement replacement
could potentially increase risk to airfield operations, damage from ensuing Foreign Object
Debris (FOD), increase the likelihood of critical or emergency work, and drive costs higher in the
future. This project is included in the 2018 2022 capital budget and plan of finance. This work
COMMISSION AGENDA Action Item No. _6b_ Page 2 of 5
Meeting Date: November 27, 2018
Template revised September 22, 2016; format updates October 19, 2016.
is included in the airports 5-year Airport Capital Improvement Plan (ACIP) submitted to the FAA
for Federal Funding under the Airport Improvement Program (AIP).
JUSTIFICATION
The 2020 Airfield Pavement Program is a continuation of the programmatic approach of
replacing aged and distressed pavement as part of a multi-year program. Many sections of
airfield pavement have exceeded their 20-year service life and have become cracked and
damaged.
This project will interface with other projects and airline operations so that the scope and
schedule of this project will not be in conflict. Replacing distressed pavements on the airfield
ensures safe operations at Seattle-Tacoma International Airport.
One of the Century Agenda goals is to use the Port’s influence as an institution to promote
small business growth and workforce development. This project may include federal assisted
fund which would require the utilization of the Disadvantage Business Enterprise (DBE)
requirements. The Port will utilize its Diversity in Contracting program to support minority and
women business enterprise (M/WBE) in the event federal funding is not applied.
DETAILS
Scope of Work
(1) Replace aged and distressed concrete pavement:
a. at the south end of Taxiway B adjacent to Taxiway S
b. at Gate C17
c. along the Service Road at Cargo 3
d. emergent damaged individual concrete panels as identified
(2) Replace sections of damage and failing asphalt:
a. at the ARFF Station adjacent to the North Satellite Taxilane
b. Cargo 2 east GSE storage area
(3) Remove abandoned utilities, add or upgrade in-pavement utilities located within the
distressed pavements work area when it makes sense.
Schedule
Design start
2018 Quarter 4
Commission construction authorization
2020 Quarter 1
Construction start
2020 Quarter 2
In-use date
2020 Quarter 4
COMMISSION AGENDA Action Item No. _6b_ Page 3 of 5
Meeting Date: November 27, 2018
Template revised September 22, 2016; format updates October 19, 2016.
Cost Breakdown
This Request
Total Project
Design
$1,250,000
$1,250,000
Construction
0
$11,850,000
Total
$1,250,000
$13,100,000
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1 - Delay the project beyond 2020
Cost Implications: $13,700,000
The estimate is based on the assumption of delaying this project to 2021. If the project is
delayed beyond 2021, the cost estimate would be further increased to reflect annual
escalation.
Pros:
(1) No construction cost for 2020.
(2) No construction impacts to aircraft operations or airport operations at affected areas by
this project in 2020.
Cons:
(1) Continued use of the pavement could result in increased FOD, creating additional
safety hazards for aircraft ingestion.
(2) This project would likely lose the opportunity to be combined with other construction
projects if it’s delayed beyond 2020. This would result in contracting inefficiencies and
more impact to airfield operations.
This is not the recommended alternative.
Alternative 2 Only replace the individual damaged concrete panels on taxiways, runways and
apron.
Cost Implications: $2,000,000
Pros:
(1) Reduced total construction cost for 2020.
(2) The replacement of damaged concrete panels help with ensuring safe aircraft
operations
Cons:
(1) Continued use of the aged and distressed asphalt pavement would result in increased
FOD and potentially increase risk to airfield operations.
(2) Deferring asphalt replacement would likely drive costs higher in the future.
This is not the recommended alternative.
COMMISSION AGENDA Action Item No. _6b_ Page 4 of 5
Meeting Date: November 27, 2018
Template revised September 22, 2016; format updates October 19, 2016.
Alternative 3 Replace distressed pavements and supporting projects on the airfield during the
2020 construction season.
Cost Implications: $13,100,000
Pros:
(1) Programmatic replacement of distressed pavements provide stable structural
support to aircraft and airport operations.
(2) This project could be combined with other construction projects during the 2020
construction season to increase efficiencies and minimize impacts to airport
operations.
(3) Support the Port’s Century Agenda.
Cons:
(1) Earlier capital spending than the other alternatives.
This is the recommended alternative.
FINANCIAL IMPLICATIONS of 2020 Airfield Pavement Replacement Projects C800483
Cost Estimate/Authorization Summary
Capital
Expense
Total
COST ESTIMATE
Original estimate
$32,300,000
$0
$32,500,000
Budget Transfers to Taxiways
($22,000,000)
$0
($22,000,000)
Budget Transfers from 2020-2024
Pavement Replacement Program CIP
$15,200,000
$0
$15,200,000
Revised Current Budget
$25,500,000
$0
$25,500,000
AUTHORIZATION
Previous authorizations
$2,875,000
$0
$2,875,000
Current request for authorization
$1,250,000
$0
$1,250,000
Total authorizations, including this request
$4,125,000
$0
$4,125,000
Remaining amount to be authorized
$21,375,000
$0
$21,375,000
Annual Budget Status and Source of Funds
The Airfield Pavement Program (C800483) is included in the 2018-2022 capital budget and plan
of finance with a budget of $31,026,000. The budget of $22 million was moved to the 2018
Taxiway Improvement project C800914. The budget transfer of $15.2M was moved from
C800930 Airfield Pavement Replacement 2021-2024 to accommodate the 2020 airfield
pavement improvements estimated to be $13,100,000. The funding sources for this project will
be the Airport Development Fund (ADF), future revenue bonds and Airport Improvement
Program (AIP) grant.
COMMISSION AGENDA Action Item No. _6b_ Page 5 of 5
Meeting Date: November 27, 2018
Template revised September 22, 2016; format updates October 19, 2016.
Financial Analysis and Summary
Project cost for analysis
$25,500,000
Business Unit (BU)
Airfield Movement Area
Effect on business performance
(NOI after depreciation)
NOI after depreciation will increase
IRR/NPV (if relevant)
N/A
CPE Impact
$.07 in 2021
Future Revenues and Expenses (Total cost of ownership)
Annual Operating and Maintenance costs are not anticipated to change appreciably. The
estimated life expectancy for this project is 20 years for concrete pavement. Replacing
pavement will result in maintenance cost avoidance.
ATTACHMENTS TO THIS REQUEST
(1) Presentation slides
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
October 9, 2018 The Commission authorized design funds for construction documents for
replacement of distressed pavement and related utilities in the 2019 portion of the
2016-2020 Airfield Pavement Program.
November 14, 2017 The Commission authorized advertisement and execution of a single
construction contract which included the 2018 Airfield Pavement Replacement as part
of the 2018 Taxiway Improvement Projects and approved non-use of PLA.
May 9, 2017 The Commission authorized design funds for construction documents for
replacement of distressed pavement and joint sealant replacement in the 2018 portion
of the 2016-2020 Airfield Pavement Program, and approved use of PLA.
October 25, 2016 The Commission authorized advertisement and execution of contract
for retrofits of 400 Hz In-ground power units and reconstruction of existing pavement at
Cargo 2.
February 24, 2015 The Commission authorized design funds for construction documents,
for replacement of distressed pavement and joint seal in the 2016 portion of the 2016-
2020 Pavement Program.