
COMMISSION AGENDA – Action Item No. 6d Page 2 of 3
Meeting Date: November 13, 2018
Template revised September 22, 2016; format updates October 19, 2016.
error by DES in which working days rather than calendar days were counted. Upon recognizing
this error, the ESCO requested that DES make an adjustment of 116 days to correct this
administrative error. On August 16, 2018, DES notified the Port and requested that an
administrative change in the contract duration be approved. This Commission action corrects
the contract duration by adding 116 days for a total duration of 411 consecutive calendar days
from NTP which was issued by DES on March 5, 2018. The DES contract end date then becomes
April 20, 2019.
Scope of Work
This project will improve the efficiency of the Airport’s mechanical systems, replace equipment
that has exceeded its useful life and reduce energy usage. Energy savings will be achieved for
both electricity and natural gas, with a resulting reduction in carbon emissions.
The project work includes:
(1) Optimize chilled water production and distribution network
(2) Remove non-performing heat exchanger in the chilled water system
(3) Replace direct expansion refrigeration units with chilled water units and install duct
work in the main data center to improve cooling at the server racks
(4) Optimize chilled water pumping
(5) Monitor indoor air quality in the airport Main Terminal to improve efficiency and
reduce energy consumption
(6) Install air curtains at public doors on baggage and ticketing levels to reduce the
amount of conditioned air leaving the building
(7) Replace older constant volume terminal boxes with variable volume boxes
(8) Insulate condensate tanks
(9) Add electrical submetering.
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1 – Do not award the additional days.
Cost Implications:
Pros:
(1) None.
Cons:
(1) The contractor would be unable to complete the work within the contract time and
would therefore be unduly subjected to liquated damages due to this administrative
error. The Port and DES may be subject to litigation or be unable to close out the
contract with the ESCO.