Item No. 8a_supp Meeting Date: October 23, 2018 Restroom Upgrades at Concourses B, C, and D CIP #C800697 1 PROJECT OVERVIEW • Phase 1: Enabling Work - Concourse B Leased Space Relocation Fully authorized Construction complete • Phase 2: Enabling Work - Airline office relocation and employee restroom renovation Requesting construction authorization • Phase 3: Prototype Restroom Requesting construction authorization • Phase 4: 3 Restrooms (one per concourse) • Phase 5: Remaining restrooms Requesting construction authorization for Phases 2 and 3 2 PHASE 2 - ENABLING WORK To expand restrooms on Concourses C and D the Port must relocate existing functions from Concourse to Ramp Level 3 PHASE 3 - PROTOTYPE RESTROOM Prototype Restroom Concourse D Before Prototype Restroom is located on Concourse D - it will be renovated and enlarged 4 PHASE 3 - PROTOTYPE RESTROOM After Rendering of proposed prototype restroom entrance 5 PHASE 3 - PROTOTYPE RESTROOM Existing Layout New Layout Prototype is guiding the development of the restroom standards 6 PROTOTYPE RESTROOM DESIGN Finishes convey cleanliness as well as a Pacific Northwest "Sense of Place" 7 PROJECT SCHEDULE • Construction start - Phase 2 - 1st Quarter 2019 - Phase 3 - 2nd Quarter 2019 • In-use dates - Phase 2 - 4th Quarter 2019 - Phase 3 - 4th Quarter 2019 Prototype restroom to open Q4 2019 8 THANK YOU 9