COMMISSION AGENDA – Action Item No. 6e Page 5 of 5
Meeting Date: October 9, 2018
Template revised September 22, 2016; format updates October 19, 2016.
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
Main Lease #000307:
1) October 8, 2013, Commission approved Amendment No. 23 of the existing Main Lease
with the Transportation Security Administration represented by the General Services
Administration (TSA/GSA) to extend the term of the lease for five (5) additional years
from 11/1/2013 to 10/31/2018 and decrease the leased premises by 403 square feet.
2) October 5, 2010, Commission approved Amendment to extend the lease for an additional
three (3) years and increase the rental rate
3) May 12, 2009, Commission approved Amendment 18 to extend the lease for an
additional three (3) years and increase the rental rate, covering hold over period that
expired on October 31, 2010
4) September 11, 2007, the Port Commission authorized the construction of tenant
improvements with the General Services Administration (GSA) and the Transportation
Security Administration (TSA) for office space on the Mezzanine Level of the Main
Terminal.
C1 Building Lease #000995:
1) February 24, 2015, Commission approved Amendment No. 1 to construct administrative
office space and tenant improvements, to prepare contract documents; perform
construction services; execute and award outside professional services agreement;
advertise and award major and small works contracts; pre-purchase material and
equipment; provide contract administration and execution on behalf of GSA and TSA for
the construction of tenant improvement requiring an authorization of $1,312,000 of
Tenant Reimbursement CIP funds.
2) January 15, 2008, the Port Commission executed a 10 (ten) year Lease Agreement
(Lease) with the United States General Services Administration (GSA), on behalf of the
Transportation Security Administration (TSA) for the construction of tenant
improvements in the C1 Building.
3) August 14, 2007, the Port Commission authorized a $6,000,000 Tenant Reimbursement
CIP (CIP C800154). As part of that authorization, Port staff is required to bring any
project requesting funds in excess of $200,000 before the Commission for specific
authorization.
4) October 24, 2006, the Port Commission authorized an additional $488,000 to the C1
Project for a total of $1,288,000 for the TSA tenant improvements. This amount is
expected to be fully reimbursed back to the C1 Project by the GSA/TSA, as a part of the
10 year lease agreement with the Port.
5) January 31, 2006, the Port Commission authorized the C1 Project to spend $800,000, as
part of a $25,300,000 request for the C1 Building Interim and Final Baggage Screening
Systems project to design and build tenant improvements in the C1 Building on behalf of
the TSA.