Motion 2018-12 – Executive Review Panel Recommendations Page 2 of 3
TEXT OF THE MOTION
Section 1. Review Panel Recommendations.
The Port of Seattle Commission adopts, and directs the Executive Director to implement, the
recommendations of the International Arrivals Facility Executive Review Panel as follows:
(1) Assign Chief Operating Officer Dave Soike as Port Executive to lead the IAF program.
(2) Clarify decision-making and augment project staff as necessary to reflect the size and
complexity of the individual projects within the IAF program.
(3) Develop a workplan and accountability mechanism to ensure recommendations are
followed and projects are managed effectively.
(4) Continue to strengthen the relationship and communication between the port and the
design-builder.
(5) Increase stakeholder engagement with partner agencies, the aviation community, and
airlines and tenants.
(6) Increase visibility of the project for the benefit of the port and external audiences,
including a “dashboard” reporting mechanism for the commission every two weeks to
include key performance indicators, quarterly commission briefings, and improved
status reports for the port’s web page.
(7) Conduct careful and independent review of all potential project-delivery methods for
future projects.
Section 2. Oversight and Reporting.
To fulfill its oversight role, the commission directs port staff to perform the following reporting
activities:
(1) Develop a project “dashboard” communications platform available to the commission
and the public that identifies the real-time status toward achieving key construction
milestones and schedule, project spending and cash flow, worker utilization, invoice
payment, women- and minority-owned business enterprise participation, program
activation and commissioning, and other measures as appropriate, within 30 days of
this motion’s adoption.
(2) Prepare a program workplan that will identify critical-path milestones and schedule,
project leadership, partnering sessions, and engagement with the Dispute Resolution
Board. The workplan shall be made available to the Aviation Committee within 30
days of this motion’s adoption.
(3) Report to the port commission within seven days of proposed scope changes or project
occurrences that will materially affect either project schedule or cost.
(4) Schedule monthly project updates to the Commission’s Aviation Committee.
(5) Provide a public briefing to the commission from port project staff and the contractor
on a quarterly basis.