COMMISSION AGENDA – Corrected Action Item No. __8a__ Page 2 of 10
Meeting Date: June 26, 2018
Template revised September 22, 2016; format updates October 19, 2016.
The following are some issues identified by the project team that resulted in the irregular bid:
1. Removing, storing, and reinstalling the existing paraline ceiling was expensive and
complicated for the contractor. The new approach, which directs the contractor to
remove and dispose of the old ceiling and replace with new, improves constructability
and reduces risk for the contractor while greatly improving the aesthetics of the SSAT.
2. Performing spot regulated materials management (RMM) abatement instead of full
abatement required the contractor to use additional personnel to maintain the work
area in a safe working condition at all times. The full RMM abatement will speed up the
demolition and allow for easier maintenance in the future, saving the Port money in the
long term.
This project will improve the effectiveness and reliability of the HVAC system for the SSAT, a
terminal that has seen dramatic passenger growth. The scope of the work for the previous
authorization included replacement and upgrade of the existing air handler and HVAC system,
reinstallation of the existing ceiling and partial regulated materials (RMM) abatement.
The additional HVAC capacity will also accommodate the expansion of the Airport Dining and
Retail (ADR), providing needed customer amenities. Maintaining comfortable heating and
cooling is a basic necessity for a satisfying customer experience. While the Port is interested in
undertaking a major renovation of the SSAT within the next 10 to 15 years, the inadequacy of
the HVAC system today and its risk of failure make this investment necessary.
The proposed scope of work for this project includes replacement and upgrade of the existing
air handler and HVAC system (prior scope), replacement of the ceiling, lighting, sprinkler
system, and signage on the concourse, Satellite Transit System (STS), and mezzanine levels, and
above the escalators, replacement of the carpet on the concourse level, and full RMM
abatement in areas where work will be performed. The additional scope increases the budget
by $38,307,000, for a total estimated project cost of $52,232,000. Staff anticipates returning to
Commission in October 2018 to request this funding after the 90 percent design is complete
and request authorization to advertise the bid package for construction.
Equipment installed as part of this project may not be compatible for the future SSAT
renovation project and the financial analysis for this project is based on this premise. Given
what we know today about a likely SSAT renovation project schedule, the HVAC improvements
would have a life of at least 10 to 15 years; consequently, the capital costs will be amortized
over this period. This project is the first and most critical phase of the shorter-term SSAT
program to address the immediate needs of the facility. Staff anticipates returning to
Commission Q4, 2018 to brief Commission on additional project/s necessary to support the
SSAT facility.
The SSAT was constructed in 1971 and the core mechanical and electrical utilities of the original
concourse have remained largely unchanged since it was built. Demand on the mechanical
systems has approximately doubled since 1971, primarily from additional cooling load caused