Item No. Date of Meeting Baggage Optimization First Quarter Briefing and Project Update 9c_supp June 12, 2018 AGENDA • Project Overview • 2018 Quarter 1 Update • Budget • Schedule • Challenges • Accomplishments • Progress • Sustainability Baggage Optimization Project 2 PROJECT OVERVIEW • Replaces six individual baggage screening systems with a centralized system that optimizes the operation and functionality of the checked baggage system Key elements: • 60 Million Annual Passengers (MAP) • Reliability • Redundancy • Security Complete Overhaul of Outbound System 3 2018 Q1 Update • Schedule - Contractor Falling Behind on Submittals and Fabrication • Phase 1: - Contractor Maintaining Two Work Shifts (Mon. through Thurs.) - Conveyor Installation has Begun (Critical Path) • Phase 2: - Developing Phase 2 Bid Documents - Creating Detailed Construction Sequencing Plan Phase 1 Schedule Concerns 4 FINANCIAL PROGRESS REPORT Millions Authorization Summary Capital Expense Total Current Budget $444.90 M $0.15 M $445.05 M $400 Current Authorization $136.16 M $0.15 M $136.31 M $350 Amount Remaining to be Authorized $308.74 M $0 M $308.74 M $450 $300 $250 Total Project (Capital + Expense) $200 Budget Spent to Date Forecast at Completion Variance Soft Cost $64.99 M $21.47 M $64.99 M $0 M $50 Construction $359.43 M $25.03 M $359.43 M $0 M $- Management Reserve $20.63 M $0 M $15.00 M <$5.63 M> $445.05 M $46.50 M $439.42 M <$5.63 M> $150 $100 Management Reserve Remaining Construction Spent Soft Cost Spent Construction Remaining Soft Cost Remaining Financial Breakdown - Project Tracking Within Authorized Budget 5 SCHEDULE Dependent upon Phase 1 On-Time Completion 6 SMALL BUSINESS/APPRENTICESHIP UTILIZATION SCS/SBE APPRENTICESHIP Overall (15%) SBE Const (15%) Women (10%) SCS Const (5.0%) 0.0% Minority (15%) 50.0% 100.0% 150.0% 200.0% 250.0% Goal Actual Tracking Close to or Exceeding Goals 0.0% 50.0% Goal 100.0% 150.0% Actual 7 CHALLENGES • Phase 1 Construction Schedule • Baggage Handling/Steel Market Conditions for Phase 2 Bid • Operational Impacts Through Construction • Phasing Impacts - Maintain Consistency Through Phases • Project Coordination - Have coordinated with 40+ projects so far Overcoming Challenges 8 ACCOMPLISHMENTS • Started conveyor installation. • Completion of Central Terminal (CT) Ramp demolition. • New CT Ramp Construction is approximately 80% complete. • Maintenance breakroom in Concourse B is 80% complete. • North Oversize baggage screening machine installed and in use. • Continued construction on utilities and infrastructure. Baggage Optimization Construction Progress 9 SUSTAINABILITY Energy Conservation Optimized system is projected to result in up to 30% energy savings Water Conservation No opportunity Waste Reduction Contractual requirement to recycle demolished material when possible Opportunity in Energy Conservation 10 New Conveyor Installed 11 EDS Machines and Conveyor Sections 12 CT Ramp Construction 13 North Oversize Baggage Screening Machine 14 Control Room Construction 15