Item No. 9b supp Meeting Date: June 12, 2018 Main Terminal Low Voltage System Upgrade C800061 1 Main Terminal Low Voltage System Upgrade • What is the Main Terminal? • What is Low Voltage? • What is being Upgraded? Concourse B Concourse A Concourse C Concourse D MTLV System Upgrade 2 High Voltage Distribution System 3 Low Voltage Distribution System Power Centers 4 STIA Main Terminal The Main Terminal and Work Area 5 Passenger Experience Video Passenger Experience 6 Justification for Project • Genuine risk to airport/airline operations - Aged equipment, risk of failure/fire (water damage), extended outages to repair - Loss of power to ticket counters and kiosks, baggage claim, communications, airline offices, elevators/escalators, HVAC. • Existing system has limited capacity - Negates new equipment/circuits or increased loads • Unsafe working conditions - risk of injury or death • Inability to meter/monitor power usage Risks of Delay 7 Typical Main Terminal Electrical Room 28" FROM PANEL TO RAILING MECHANICAL VALVES IN WORKING SPACE DANGER! ASBESTOS! Safety issues in typical old Main Terminal electrical space. 8 Typical Main Terminal Electrical Room Safety issues in typical old Main Terminal electrical space with worker. 9 Another Electrical Room 6" CLEARANCE 23" CLEARANCE 18" CLEARANCE Working space does not comply with National Electrical Code. 10 Typical Power Panels in Main Terminal • Manufacturer no longer in business. • All breakers in use. • Replacement circuit breakers not available. • Unsafe condition. Obsolete electrical panels. 11 Recent Power Outage in the News • Aging equipment was scheduled for replacement. • "Equipment failed before we could get to it." Failure of Aging Electrical Equipment Results in Power Outage 12 Project Work Electrical Rooms Electrical Panels Conduit Runs 13 Overview Budget • Est. Final Construction Costs: $70,546,000 • Est. Design Costs: $29,754,000 • Est. Program Total: $100,300,000 Estimated Program Total: $100,300,000 14 Scope Item Costs Scope Item 2014 Estimate 2018 Estimate Normal Power $20 Million $61 Million Emergency Power $0 $5 Million Central Power Center $0 $14 Million Branch Metering $0 $7 Million Regulated Materials Abatement $0 $13 Million Scope item cost by line item. 15 Overview Schedule • • • • • • Commission Authorization for Design: Q3 2018 Design Team and GCCM Begin: Q1 2019 Design Complete: Q4 2021 Commission Authorization for Construction: Q3 2021 Construction Start: Q4 2021 Construction Complete: Q1 2025 Construction Complete 2024 16 Questions? 17