
COMMISSION AGENDA – Briefing Item No. _9b___ Page 2 of 7
Meeting Date: June 12, 2018
Template revised September 22, 2016; format updates October 19, 2016.
electrical system is the low-voltage system (operating voltage distribution levels of 120 to 600
volts). This infrastructure is critical to airport operations.
Large portions of the existing low-voltage electrical distribution system have reached the end of
their useful operating life, raising concerns over their continued reliability. The useful operating
life of electrical equipment primarily depends on age, with 30 years being a reasonable lifespan.
Some of the equipment included in this project is well over 40 years old. Equipment
maintainability and availability of spare parts are increasing concerns with aging equipment.
Much of the existing equipment is not compliant with the current National Electrical Code
(NEC). There are areas in the low-voltage electrical system where the available fault current
exceeds the current ratings for the existing equipment, thus creating operating and working
condition safety issues. Other safety-related NEC issues exist for these older installations
including dedicated equipment space, working clearances, illumination, identification, and the
need for Underwriters Laboratory (UL) listing of all equipment. The MTLV project will correct all
the issues in this area and bring the installation up to current standards and compliance with
current codes. Having adequate and reliable capacity in the low voltage distribution system is
also critical in supporting deployment of new technologies that can maximize facility
throughput.
The project team explored multiple project delivery methods, strategies, and impact
mitigations. Delivery methods investigated included design-bid-build, design-build, progressive
design-build, and the selected GC/CM. Impact mitigation investigated included tenant
relocation, both in and outside of airport facilities, structured zone wide outages, and use of
Port construction crews to complete the work. The current plan of action helps minimize, as
much as feasible, the risks to operational impacts in construction.
Since authorization in 2014, the project team has completed both 15% and 30% design which
included a full physical inventory and condition assessment of all electrical equipment in the
main terminal. The condition assessment has driven the necessary renewals and project
scoping. The need for these major work elements is detailed below.
Normal Power Work
The 2014 action for renewal and replacement approached the Main Terminal Power
Distribution System with a phased concept. The team assumed that only the worst power
distribution panels, roughly 10% or 30 panels, were in need of immediate replacement. The
comprehensive year-long condition assessment of this system in 2016 established this to be
incorrect. The assessment found that nearly all the panels were in poor and failing condition
due to age and there were many more electrical panels than previously assumed. The project
now includes the replacement of nearly 300 of the 600 electrical panels; all of these panels are
of similar age and condition and are at a similar risk of failure.