Item No.: 9c_Attach Meeting Date: May 22, 2018 Capital Improvement Projects First Quarter Report 2018 101 Capital Improvement Projects Overall Status of Projects  101 Total Projects in report (87 CDD, 14 ICT)  46 Projects are within or ahead of target schedule and budget  45 Projects have either target schedule or budget off with 11 new Reportable Variances for this Quarter.  6 Projects have both target schedule and budget off with 2 new Reportable Variance for this Quarter.  4 Projects are Substantially Complete Capital projects managed by CDD and ICT 2 CDD Projects by Status, by Quarter Off Schedule and Budget Off Schedule or Budget 100% 90% 80% 2 3 28 (Schedule) 70% 5 29 (Schedule) 33 (Schedule) 60% 6 37 (Schedule) 50% On Schedule and Budget 40% 30% 46 52 1Q17 Report Series3 46 40 3Q17 Report 4Q17 Report 1Q18 Report 3 2 5 6 Series2 29 33 35 37 Series1 46 52 46 40 20% 10% 0% Two new red and 11 new amber 3 CDD Projects by Dollar Value Off schedule and budget - OLD Variance - Emergency Gen - $2.6M - AOA Perimeter Fence Line - $6.9M - Electrical Utility SCADA - $9.6M - MT So Low Voltage - $100M Off schedule and budget - NEW Variance $1.072B $762.6M - IWS Segregation Improvements - $1.1M - International Arrivals Facility - $761.5M Budget of $25M or more, OLD Schedule Variance - GSE Electrical Charge Stations - $30.7M - Checked Bag Recap Optimization - $445M $119M Budget of $25M or more, NEW Schedule Variance $111M - Concourse D Hardstand Terminal - $38.4 $649M Other Projects with Budget of $50M or more - NS NSAT Renovation NSTS Lobbies - $670M Total Budget = $2.72B Two major projects off target 4 Aviation Project Summary  Two new projects with a budget and schedule variance o o  International Arrivals Facility - Multiple causes IWS Segregation Improvements - Change in construction delivery method required additional design and delaying construction Eight new projects with schedule variances o o o o o o o o Automated Screening Lanes Check Point Conversions - Supply/integration issues and request from Airlines/TSA to avoid busy summer season CDD/CPO Move to SeaTac Office Complex - Move delayed pending lease improvements by the landlord Concourse D Hardstand Terminal - Delayed two months due to unforeseen site conditions Flight Corridor Safety Program Phase 2 & 3 - Additional assessment & planning SSAT HVAC Infrastructure Upgrade - Irregular bid resulting in a re-evaluation of the project scope SSAT Narrow Body Configuration - Coordination with the International Arrivals Facility Wi-Fi Enhancements Project - Design of the final phase the Passenger Loading Bridge project has pushed out the final completion date of the Wi-Fi project Delta Inflight Services - Tenant Reimbursement Agreement pending documentation from Delta 10 new schedule variances out of a total of 65 Aviation projects 5 Aviation Projects Substantial Completion Ramp Wi-Fi 6 Aviation Projects Q1 Savings Project RW16C-34C Design and Reconstruction ST Walkway & Bridge Improvement Interim Baggage System Program All Other (5 projects) Total Savings (000's) $2,200 $2,100 $750 $410 $5,460 $5.5M in savings returned in Q1 7 Maritime/Economic Development Project Summary  Three projects with new schedule variance: o Shilshole Bay Marina Paving-due to consideration of a second floor alternative for the SBM Tenant Services Building project which resulted in a delay of this concurrent paving work. o FT Redevelopment Phase I - On hold pending resolution of proposed Gateway Building tenant lease agreement. o Argo Yard Truck Roadway- Ongoing UPRR construction delay on Element III (Argo freight yard automated gate systems). 3 new variance out of 24 projects 8 Maritime Substantial Completion FT Net Sheds 3, 4, 5 and 6 Roof Replacement 9 Resolution 3726 - Priority Hire • • • • • Designee, Advisory Committee, Regional Public Owners Group Establish goals for hiring from Economically Distressed Areas, no less than 20% Through contracts and PLAs require Contractor and Labor dispatch support Jobs Coordinator; regional Priority Hire efforts Benchmarks, metrics, Long Range Plan, annual report Priority Hire 10 Priority Hire Implementation Progress • • • • • • Team: Capital Development, Labor Relations, EDD, ICT, Public Affairs and Commission Office Contract language ready; PLA language in development Coordinator hiring underway; Participating in Regional Owners Group; ILA working LCP Tracker under evaluation Measurement in CDS; 2017: KC - 17%, expanded - 23% 2018 LRP goals to set objectives and develp program Hiring implementation 11 ICT Commission-Authorized Projects by Status, by Quarter 100% 90% Off Schedule or Budget 80% 46% 40% 70% 63% 57% 60% 50% 40% On Schedule and Budget 30% 54% 60% 20% 38% 43% 10% 0% 2Q17 Report 3Q17 Report 4Q17 Report 1Q18 Report Target: 70% green, 30% amber, 0% red 12 Information & Communication Technology Project Summary  No new variances 0 new variances out of a total of 14 ICT Projects . 13 Information & Communication Technology Substantial Completion Port of Seattle Website South Loop Train Station Wait Time Displays 2 projects reached substantial completion 14