
Pier 66 -
Norwegian Tenant Improvement Partnership
August 2015 - October 2017
6
SCHEDULE OF FINDINGS AND RECOMMENDATIONS
PORT MANAGEMENT SHOULD STRENGTHEN ITS MONITORING AND APPROVAL OF
CHANGE ORDERS
Changes orders (CO’s) are a change from the original scope, drawings, plans, or specifications of a
project. They may be caused by a change in local building code, unforeseen field conditions, design
changes or as a way to account for allowances, refunds or alternates. CO’s represent the largest financial
risk in a construction project because the changes may not be necessary and/or costs may be inflated.
Therefore, approval of both the scope and costs is critical to accuracy of payment requests.
This project included 14 CO’s, six of which modified the scope at a total cost of $2.2 million.
Port Management actively reviewed, identified, and corrected monthly pay applications prior to making
payment. Management was also engaged and frequently communicated with NCHL regarding the status
and milestones of the project.
However, an opportunity exists for Port management to develop a process to review and approve CO’s
for reasonableness and accuracy. We tested two CO’s that represented the largest financial change and
identified the following exceptions:
• Eight approved subcontractor CO requests did not include quotes and/or a breakdown of costs to
substantiate or support the cost of the CO at a total cost of $98,000.
• NCLH did not re-estimate the costs to determine whether the CO costs were reasonable prior to
submitting the CO request to Port Management.
Recommendations:
• Develop a process to review and approve CO’s. This process should include a review of
documentation to substantiate the request. As a best practice, the Port should require the project
manager, in this case NCLH, to provide a re-estimate of the costs to assess reasonableness.
Management Response/Action Plan:
Port management appreciates Internal Audit’s review, findings, and recommendations on monitoring and
approval of change orders.
Port’s tenant Norwegian Cruise Line Holdings (NCLH) retained Bermello Ajamil & Partners as their
consultant (Consultant) to design and manage the tenant improvement project at the Bell Street Cruise
Terminal. The Consultant worked closely with NCLH’s general contractor on implementing the
construction under a Guaranteed Maximum Price contract. A series of change orders were executed with
the general contractor as more investigative and design work progressed. Some change orders were
executed to address field conditions, scope refinement, as well as implementation of additional design
requirements imposed by US Customs and Border Protection late in the design process. Port
management relied on NCLH through their Consultant team to exercise professional judgment on
1) RATING: MEDIUM