
Delta Lounge - Tenant Reimbursement Agreement
September 2015- January 2018
SCHEDULE OF FINDINGS AND RECOMMENDATIONS
THE TENANT REIMBURSEMENT AGREEMENT WAS NOT WRITTEN TO GIVE PORT
STAFF BROAD OVERSIGHT AUTHORITY FOR DECISIONS MADE BY EXTERNAL
PARTIES.
The Agreement does not give Port management the authority or ability to be included in the selection
process of contractors. However, the Port remained financially responsible for the majority of costs from
these decisions. Delegating decisions to external parties, while still maintaining financial responsibility, is
not designed to facilitate accountability and sound stewardship of public funds. Below are examples that
reflect decisions made externally and the resulting financial impact to the Port.
1. Delta received three bids for design services and selected ECH as the architect, with a bid of
$317,245. ECH revised their bid to approximately $900,000; however, Port management questioned
their request which resulted in a revised lower estimate of approximately $623,000. Internal Audit
estimated that the Port incurred an additional $190,000 as a result of the cost overrun.
Although not required by the Agreement, Delta did not retain documentation of the two bids that were
not selected. Retaining this documentation would have allowed IA and Port Management to assess if
other bidders might have anticipated any later changes in their bids.
2. Delta did not follow sound practices and allowed PCL, the general contractor, to review bids, including
their own. PCL selected themselves as the successful bidder of “self-performed” work.
General Contractors may have information, such as budgeted costs and contingency funds that other
bidders don’t have, giving them an unfair advantage. General Contractors may also claim that they
can perform the work at a more reasonable cost than a subcontractor, because they have a more
comprehensive understanding of the project. Therefore, implementing strong internal controls is
critical to make sure the bidding process is equitable and the successful bidder is accountable for their
bid.
PCL’s conceptual estimate for self-performed concrete work was $203,473. However, the revised
estimate was $450,536. Internal Audit was not able to determine the additional cost derived from the
initial and final estimate.
3. The Agreement included a contingency fund of $912,000 to absorb budget overruns. Although the full
contingency fund was expended, the Port was not given an opportunity to assess if it aligned to the
original scope of the project or to determine the reasonableness of the charges until after the work
had been completed.
Recommendation:
Management should reexamine the Port’s Tenant Reimbursement Agreements to assure that the Port’s
interests are met. Additionally, Tenant Reimbursement Agreements should be written in a manner that
gives Port management broad authority when decisions are made that impact the Port financially.
1) RATING: HIGH