Item Number: 9c_Report
Meeting Date: March 13, 2018
Capital Improvement Projects
Fourth Quarter Report 2017
ii - Port of Seattle 4Q 2017 Report
Port of Seattle
Capital Improvement Project Report
Fourth Quarter 2017
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2017, the Port plans to invest $651,600,000 to expand and upgrade the infrastructure that supports marine and
aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping companies,
airlines, rental car companies, concessionaires and public parking. About 2 percent of the Port's capital budget comes
from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in transportation
facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, budget transfers, and cost growth of construction if it exceeds 10% of contract. The
report may include graphics that report project costs compared to authorization, construction costs (including change
orders (CO)) compared to the construction contract, location maps, and photographs. The Port implements a number
of different types of projects and not all information may be relevant to a specific project; as such, the reports may vary
in detail and content. Project types may range from construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (substantial completion). This section also includes "Project Status" illustrating at a
glance if the project is on schedule, and within budget, and the date Construction authorization received.
•
•
•
•
•
•
•
Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
Budget addresses the total project budget and includes information on the overall budget status, recent
Commission authorizations, forecasted overruns or savings, and scope changes.
Change Orders provides information on current quarter's COs and total project COs including justification for CO's for
the reporting period and information on any CO over $200,000 or 10% of the contract value.
Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
Budget Transfers reports any transfers between authorized projects during the reporting period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports intend to meet the reporting requirements of Port of Seattle General Delegation of Authority and the
Commission motion on January 8, 2008' regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page on the Port of Seattle web site to ask a question, make a comment or
request a copy of the State Audit Reports Response and Action Plan.
Port of Seattle 4Q 2017 Report - 1
Charts from PowerPoint
Project Title
Page
Q4 CDD Projects by Status Chart................................................................6
Q4 CDD Projects by Dollar Value Chart......................................................7
Aviation
Overall Project
Status
CIP Number
Project Title
Page
Variance
Schedule
Budget
C101107 ................160th GT Lot ..........................................................8 ........... l............... ⌧
C102112 ................Hennelly Service Tunnel Renewal Rep .................9 ........... l
C102162................Air Cargo Road Safety Improvements.................. 10 .......... l
C800019 ...............Gate Utilities Improvement ................................... 11 .......... l............... ⌧
C800061 ...............Main Terminal South Low Voltage ........................ 12 .......... l............... ⌧ .................. ⌧
C800107 ...............C4 UPS System Improvements ............................ 13 .......... l
C800251 ...............Vertical Conveyance Modernization..................... 14 .......... l............... ⌧
C800335 ...............EGSE Electrical Charging Stations ...................... 15 .......... l............... ⌧
C800483 ...............Airfield Pavement Program .................................. 16 .......... l
C800538 ...............Utility ER Backup Standby.................................... 17 .......... l
C800549 ...............SSAT Interior Renovations ................................... 18 .......... l............... ⌧
C800556 ...............NorthSTAR North Satellite Lobbies ...................... 19 .......... l
C800583 ...............International Arrivals Facility ................................20 .......... l
C800585 ...............Wi-Fi Enhancement for Ramp and Terminal ........21 .......... l
C800605 ...............Security Exit Lane Breach Control Phase II .........22 .......... l............... ü
C800612 ...............Checked Baggage Recap/Optimzation ............. 23-24 ....... l............... ⌧
C800638 ...............Dining and Retail Infrastructure Modernization ....25 .......... l............... ⌧
C800642 ...............CCTV Camera Data Improvements ....................26 .......... l
C800655 ...............IWS Segregation Improvements ..........................27 .......... l
C800688 ...............Construction Logistics Expansion ........................28 .......... l............... ⌧
C800692 ...............2016 Fuel System Modifications...........................29 .......... l............... ⌧
C800695 ...............C3 Holdroom Expansion ......................................30 .......... l............... ü
C800697 ...............Concourse B, C and D Restroom Upgrades ........ 31 .......... l
C800699 ...............Electric Utility SCADA Utility.................................32 .......... l............... ü .................... ü
C800702 ...............2015-2016 C Concourse Roof Repl .....................33 .......... l............... ⌧
C800716 ...............Central Terminal Stairs .........................................34 .......... l............... ⌧
C800717................N. Terminal Utilities Upgrade ................................35 .......... l............... ⌧
C800722 ...............CTE HVAC ............................................................36 .......... l
C800724 ...............Concourse C New Power Center .........................37 .......... l............... ⌧
C800743 ...............South Sattelite Terminal Renovation ....................38 .......... l............... ü
C800760 ...............Auburn Mitigation Rd Removal .............................39 .......... l............... ⌧
2 - Port of Seattle 4Q 2017 Report
Aviation, cont.
Overall ProjectVariance
Status
CIP Number
Project Title
Page
Schedule
Budget
C800761 ...............Concourse B Ramp Level Holdroom....................40 .......... l............... ⌧ ................... ü
C800762 ...............Telecommunications Meet Me Room ................... 41 .......... l
C800769 ...............Concourse D Hardstand Terminal ........................42 .......... l
C800771 ...............D6 Gate Modifications ..........................................43 .......... l............... ⌧
C800781 ...............SSAT Narrow Body Configuration ........................44 .......... l
C800784 ...............Emergency Generator ..........................................45 ......... l............... ⌧ .................. ⌧
C800793 ...............PLB Renew and Replace Phase 2 .......................46 .......... l
C800798 ...............SSAT HVAC Infrastructure Upgrade .................... 47 .......... l
C800801 ...............Variable Frequency Drive .....................................48 .......... l
C800818 ...............SSAT Structural Improvements ............................49 .......... l............... ⌧
C800825 ...............Interim Baggage System Program .......................50 .......... l............... ⌧
C800826 ...............ARC Flash Hazard Mitigation ............................... 51 .......... l
C800833 ...............Holdroom Seating For Concourses B and C........52 .......... l............... ⌧
C800834 ...............Ground Based Augmentation System Upgrade ...53 .......... l............... ü
C800841 ...............Tenant Telecommunications DEMARC Upgrade .54 .......... l
C800842 ...............AOA Perimeter Fence Line Standards Comp
55 .......... l............... ü .................... ü
C800846 ...............ADR Kiosk Program Expansion 1 ........................56 .......... l
C800858 ...............Checkpoint 5 Wall Replacement ..........................57 .......... l............... ⌧
C800862 ...............Terminal Security Enhancements ........................58 .......... l
C800873 ...............Concourse B Gate Reconfiguration .....................59 .......... l
C800880 ...............Employee Security Screening ..............................60 .......... l............... ü
C800886 ...............Central Terminal Enhancements ..........................61 .......... l............... ü
C800898 ...............Airport Signage Phase 1 ......................................62 .......... l
C800913 ...............Concourse B IWS Upgrade .................................63 .......... l
C800914 ...............Taxiways ABLQ Improvements ............................64 .......... l
C800917 ...............ST Walkway and Bridge Improvements ...............65 .......... l
E104395-6 ............Lora Lake ..............................................................66 .......... l
U00225 .................Flight Corridor Safety Prog Ph 1 ..........................67 .......... l............... ⌧
U00239 .................NERA Program .....................................................68 .......... l
U00356 .................Flight Corridor Safety Program Phase 2 and 3 ....69 .......... l
U00370 .................Automated Passport Control Kiosk - Ph 3............70 .......... l............... ⌧
Other Aviation
Overall Project
Status
CIP Number
Project Title
Page
Variance
Schedule
Budget
C200007 ...............Highline School Noise Insulation .......................... 71 .......... l............... ⌧
C800154 ...............Tenant Reimbursement ........................................72 .......... l
Port of Seattle 4Q 2017 Report - 3
Maritime
Overall Project
Status
CIP Number
Project Title
Page
Variance
Schedule
Budget
C800355 ...............Shilshole Bay Marina Paving ................................73 .......... l
C800356 ...............Shilshole Tenant Service Buildings ..................... 74 .......... l............... ⌧
C800525 ...............FT Redevelopment Phase I ..................................75 .......... l
C800526 ...............FT Net Sheds 3, 4, 5 & 6 Roof Replacement .......76 .......... l............... ü
C800531 ...............FT Docks 3, 4, 5 & 6 Fixed Pier Impr ...................77 .......... l
C800675 ...............P91 South End Fender .........................................78 .......... l
C800829 ...............T-91 C173 Building Roof Overlay .........................79 .......... l
C800895 ...............T-18 Stormwater Outall Renewal & Repl ..............80 .......... l
C800910 ...............T-91 Standoff Barges............................................ 81 .......... l
C800993 ...............Salmon Bay Marina Uplands Improvements ........82 .......... l
E104324 ................Viaduct Construction Coordination ......................83 .......... l............... ⌧
U00218 .................P66 Alaskan Way Street Improvements...............84 .......... l
Economic Development
Overall Project
Status
CIP Number
Project Title
Page
Variance
Schedule
Budget
C800196 ...............T-102 Roof and HVAC ..........................................85 .......... l
C800813-105257 ..P66 Elevator 3 & 4 Control ...................................86 .......... l
C800813-105261 ..P66 Elevator 2 Control System ............................87 .......... l............... ü
C800888 ...............P69 Solar Panel System.......................................88 .......... l
C800889 ...............BHICC Interior Modernization ..............................89 .......... l
Joint Venture
Overall Project
Status
CIP Number
Project Title
Page
Variance
Schedule
C102858 et al ....... Street Vacations T-5/18/105.............................. 90-91 ....... l............... ⌧
C800546 ...............Argo Yard Truck Roadway ....................................92 .......... l
C800620-U00064 T-46 Permit Mitigation ..........................................93 .......... l............... ⌧
E102007 ................East Marginal Way Grade Separation ..................94 .......... l............... ü
U00289 .................T-5 Pile Removal ..................................................95 .......... l
4 - Port of Seattle 4Q 2017 Report
Budget
Corporate
Overall Project
Status
CIP Number
Project Title
Page
Variance
Schedule
Budget
C800162 ...............ID Badge Replacement ........................................95 .......... l............... ⌧
C800728 ...............Parking System Replacement ..............................96 .......... l............... ü
C800729 ...............Vessel Moorage System .......................................97 .......... l............... ⌧
C800747................Project Delivery System .......................................98 .......... l
C800748 ...............Remote Data Ctr Business Continuity..................99 .......... l............... ⌧
C800776 ...............POS Website Redevelopment .............................100 ......... l............... ü
C800782 ...............Airport Subway Info Displays .............................. 101 ......... l
C800788 ...............Airport Data Network Switch Upgrade ................102 ......... l............... ⌧
C800790 ...............Checkpoint Wait Time..........................................103 ......... l............... ü
C800800 ...............SEA Smartphone App .........................................104 ......... l............... ⌧
C800827 ...............STIA Communication Infrastructure ....................105 ......... l............... ⌧
C800835 ...............South Loop Train Displays ...................................106 ......... l............... ⌧
C800907 ...............Supplier Outreach and Procurement System ..... 107 ......... l
C800908 ...............Enterprise Network Firewal Upgrade .................108 ......... l
C800909 ...............PeopleSoft Financials Upgrade ..........................109 ......... l
C800929 ...............Rental Car Facility Fleet Tracking System ..........109 ......... l
Key Project Status
l Project within or ahead of target budget and schedule
l Either target schedule or budget are off
l Both target schedule & budget are off
Negative Variance Status
ü
New Variance
⌧ Previously Reported
Schedule Completion on the Project Reports refers to:
Beneficial Occupancy or Last Asset In-Use date
Port of Seattle 4Q 2017 Report - 5
6 - Port of Seattle 4Q 2017 Report
Port of Seattle 4Q 2017 Report - 7
FOURTH QUARTER REPORT, 2017
So. 160th GT Lot Expansion
Project: C101107
Budget: $4,326,533
Phase: Design
Start: 2/1/2013
Schedule Completion: 11/16/2018
Improve lot drainage and complete
site fencing and landscaping,
rehabilitate the Ground Transportation
(GT) Lot building, underground
existing overhead utility lines
Schedule
Project was rescoped at 100% design in 2015, resulting in project delivery
delay. Project had building rehabilitation scope restored by the Commission on
September 26, 2017. Anticipate advertising for construction bids in Q1 2018.
Budget
Port resolved a federal income tax issue with PSE. Commission authorized
additional $2,231,533 on September 26, 2017 for the rehabilitation of the GT
Lot building.
Change Order
Current Quarter
N/A
N/A
Project Total
N/A
N/A
Risks
Long lead times during construction may further delay the schedule.
Budget Transfers
AIRPORT
8 - Port of Seattle 4Q 2017 Report
From
To
5
Dollars in Millions
Lot improvements are complete. Final Puget Sound Energy (PSE) bill paid; the
federal income tax issue was resolved. The rehabilitation of the GT Lot
building, originally deleted, has been added back in and design is complete.
Amount
$0
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Number of COs
Amount of COs
Justification for COs: N/A
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 9/26/2017
4
4.3
3.6
3
1.4
2
1
0
Authorized Forecasted
Construction Costs
None at this time
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Service Tunnel Renewal/Replace
Project: C102112
Budget: $39,505,000
Phase: Construction
Start: 11/4/2012
Schedule Completion: 12/31/2019
Project will seismically retrofit and
structurally strengthen the airport
Service Tunnel located between the
Main Terminal and Airport Garage.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 7/25/2017
(Commission Construction Auth.)
Budget/Costs Incurred
Contractor has started work within the south portion of the Service Tunnel and
along the south portion of the Parking Garage courtesy van drive.
Schedule
The project is on schedule.
Budget
$50
Dollars in Millions
Significant Developments
39.5
39.5
$40
$30
$20
6.1
$10
$0
Budget was increased for a second time due to a bid irregularity (high bid).
Received requested increase of $6 million. High bid was driven by the
complexity of the work, need for tunnel to remain in operation during
construction, and construction market conditions.
Authorized Forecasted
Construction Costs
Current Quarter
Number of COs
0
Amount of COs
$0
Justification for COs: None this quarter.
Project Total
1
$0
Dollars in Millions
$30
Change Order
Costs
Incurred
24.0
$25
$20
$15
$10
$5
0.0
2.1
Change
Orders
Spent
$0
Initial
Risks
Certain International Arrivals Facility, Supervisory Control and Data
Acquisition System, and North Terminal Utilities Update project outcomes may
impact this project. Coordinating project with those efforts as well as Aviation
Operations, Business Development, and Maintenance to minimize impacts to
airport operations.
Photo
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 9
FOURTH QUARTER REPORT, 2017
Air Cargo Rd Safety Improvements
Project: C102162
Budget: 8,819,590
Phase: Design
Start: 10/2/2013
Schedule Completion: 9/11/2020
Improvements along Air Cargo Rd
and S 170th St to support Cell
Phone L and roadway operations,
and meet current safety standards.
(Commission Construction Auth.)
Budget/Costs Incurred
Schedule
Project restarted Q2 2017 and is currently on schedule. Plan to begin design in
Q1 2018.
Budget
Project is currently within budget. Overall project budget includes $ of
additional project contingency to address risks. Commission authorization
includes construction of critical pavement repair on Air Cargo Rd ( workw
Change Order
Current Quarter
0
$0
Project Total
0
$0
8.8
10
Dollars in Millions
Completed consultant selection for design services in November 2017. Began
contract negotiations with HNTB Corporation and plan to execute the service
agreement in January 2018. Completed an update to the survey base map to
support design.
8
6
3.6
4
2
0.1
0
Authorized Forecasted
$2
$1
•
•
Storm Drainage System portions of the storm drainage system have failed
and need to be replaced.
Unknown Utilities widening and sidewalk construction require the
relocation of a number of unknown utilities.
Traffic Growth completion of the traffic analysis identifies the need for
additional intersection improvements to accommodate growth.
0.1
0.0
0.0
Initial
Change
Orders
Spent
$0
Risks
•
Costs
Incurred
Construction Contract Costs
Dollars in Millions
Significant Developments
Number of COs
Amount of COs
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 7/11/2017
Photo
Budget Transfers
Amount
$0
AIRPORT
10 - Port of Seattle 4Q 2017 Report
From
To
Air Cargo Rd Pavement Repair
FOURTH QUARTER REPORT, 2017
Gate Utility improvements
Upgrade the Concourse B loading
Project Status:
bridges to the standard 4 z power.
Schedule: Delayed
This will reduce aircraft emissions and
Budget: On or Under
Status Reset: N/A
noises improve energy efficiency and
(Commission Construction Auth.)
save money for the airlines.
Significant Developments
Concourse B 4 z construction is complete. Motor Generators are installed
and system is in operation at all gates. This will be the final report.
Schedule
Substantial construction completion occurred October 31, 2017.
Budget
Budget/Costs Incurred
20
Dollars in Millions
Project: C800019
Budget: $15,737,508
Phase: Construction
Start: 6/28/2007
Schedule Completion: 10/31/2017
17.2
14.4
13.8
15
10
5
0
The project is within the existing approved budget.
Authorized Forecasted
Change Order
Construction Costs
Reflecting Concourse B 4
Project Total
11
Risks
3.5
Dollars in Millions
z only.
Current Quarter
Number of COs
0
Amount of COs
$0
Justification for COs: Nothing this quarter
Costs
Incurred
3
2.5
2
1.5
1
0.5
None
3.2
3.0
0.3
0
Initial Change
Orders
Budget Transfers
Amount
From
To
Spent
MG Set installation photo
AIRPORT
Port of Seattle 4Q 2017 Report - 11
FOURTH QUARTER REPORT, 2017
Main Terminal Low Voltage
Renewal and replacement of low
voltage volts and belowb electrical
distribution equipment in the Main
Terminal.
(Commission Construction Auth.)
Significant Developments
Budget/Costs Incurred
Project was taken to 30% design and has been updated through Q2 and Q3
2017 with action to follow in Q1 2018.
Schedule
The scope of work, schedule and design budget will be revised in Q1 2018.
Budget
Current Quarter
0
$0
Project Total
0
$0
Risks
This area is a 27/365 operation. Sequencing of this work is critical and
electrical power has to be maintained without interruptions. Significant work
growth is possible due to lack of project definition.
Budget Transfers
AIRPORT
12 - Port of Seattle 4Q 2017 Report
100.3
100
80
60
40
20
8.1
Authorized Forecasted
Construction Costs
Change Order
Amount
$0
120
2.8
0
The forecast has been revised at the conclusion of the 30% design. An increase
in budget is expected to be required and will likely exceed the $20.7M budget.
Number of COs
Amount of Cos
Justification for COs: N/A
Project Status:
Schedule: Delayed
Budget: Forecast Overrun
Status Reset: N/A
Dollars in Millions
Project: C800061
Budget: 100,300,000
Phase: Design
Start: 6/28/2007
Schedule Completion: 7/2/2024
From
To
Not Applicable
Photo
Costs
Incurred
FOURTH QUARTER REPORT, 2017
C4 UPS System Improvement
Replace existing Uninterruptible Power Project Status:
Supply !<=>) System, including
Schedule: Within or Ahead
batteries, with a new system located in
Budget: On or Under
the Airport Combined Communications Status Reset: CA:CA&+:*
(Commission Construction Auth.)
and Command Center !?C)@
Significant Developments
Started project closec activities, created punchcist items, started asca
and prepared final change orders. This will be the final report.
Schedule
Substantial completion achieved on December 8 2017.
Budget
Budget/Costs Incurred
$5
Dollars in Millions
Project: C800107
Budget: $4,010,238
Phase: Closeout
Start: 4/14/2015
Schedule Completion: 12/8/2017
4.2
3.7
$4
2.9
$3
$2
$1
$0
Authorized Forecasted
A savings of $500,000 is being forecast on this project.
Change Order
Costs
Incurred
Construction Costs
$2
Dollars in Millions
Current Quarter
Project Total
Number of COs
18
27
Amount of COs
!"# %&')
"%* **+
Justification for COs: Higher level of care for Factory and Field Testing and
Static Transfer switch and UPS assembly, reconfiguration of K-. K/0 cabinet
permitting transfer of load from A to B sources.
1.6
1.5
$2
$1
$1
0.1
$0
Risks
Initial
Risk mitigated in Bid with detailed Construction Sequence Plan. Plan
developed with involvement of Electric Shop, Commissioning Agent, FF3 and
Construction Management and CC staff. Contractor has used this plan as
foundation for his schedule. 5/6 5/7-6/9 from existing SSS:; November
30, 2016 failure added to scope of the project.
Change
Orders
Spent
Photo
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 13
FOURTH QUARTER REPORT, 2017
Vertical Conveyance Modernization Program - Aeronautical
Project: C800251
Budget: $12,306,408
Phase: Construction
Start: 10/25/2011
Schedule Completion: 6/30/2017
Perform modernization on J existing
elevators and M escalators: SSAF, MTBIH
MTBEH MTBMH MTBNH MTBOH MTBGH SSB,
SSC. Install new elevators SSM and
SSN. Install cooling packages on 12
existing hydraulic elevators throughout
Main TerminalP
(Commission Construction Auth.)
Budget/Costs Incurred
Substantial completion was achieved in Q2 2017. Final negotiations and
closeout begins with expected completion in Q1 2018.
Schedule
Construction is complete as of Q2 2017.
Budget
20
Dollars in Millions
Significant Developments
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 11/11/2013
16.4
15
10.5
5
0
Authorized Forecasted
The project forecast is within the approved budget; expect savings.
Change Order
Contractor has exceeded contract time and has failed to complete work on time
in 2016.
Budget Transfers
14 - Port of Seattle 4Q 2017 Report
From
To
5
Dollars in Millions
Risks
AIRPORT
Costs
Incurred
Construction Costs
Current Quarter
Project Total
Number of COs
2
108
Amount of Cos
$511,121
BDEGHEIJ
Justification for COs: differing site conditions, sequencing of work, and
administrative changes.
Amount
$0
9.9
10
4.8
4.6
4
3
2
0.5
1
0
Initial
Change
Orders
Spent
FOURTH QUARTER REPORT, 2017
Electrical QRTUVW Support EXUYZ[\V] (EGSE) Electrical Charge Stations
Airportgopqr electrical charging
system for electrical ground support
equipment at the Concourses and the
North and South Satellitest
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Significant Developments
EGSE Phase 2 Project ^ Concourse A, Concourse B and South Satellite:
Received Concourse A _``d IFB design documents for review in December,
2017. Completed the 360 degree photo presentation and the Regulated
Materials Good Faith. Preparation of Divisions 00 and 01 and Engineeref Cost
estimate is complete.
Schedule
Phase 2g Start construction process in Q2 i`_jk Implementation of this project
will be coordinated with the Concourse C New Power Center Project to
standardize the design for the new power center in Concourse B. Schedule is
delayed to allow for better coordination with airline alignment and the IAF
project.
Budget/Costs Incurred
Dollars in Millions
Project: C800335
Budget: $30,700,000
Phase: Construction
Start: 10/26/2010
Schedule Completion: 1/29/2021
35
30
25
20
15
10
5
0
30.7
25.6
18.4
Authorized Forecasted
Costs
Incurred
Construction Costs
Not Applicable
Budget
Project forecast is within the approved budget. Request authorization for
construction funds and authority to advertise for construction when the design
and bid documents are complete for EGSE Charger Phase 2 Project.
Phase 1 completed for l_mni``n```k
Change Order
Current Quarter
Number of COs
0
Amount of Cos
$0
Justification for COs: None this quarter
Project Total
0
$0
Risks
Coordinate with other airfield projects and Airline Gate Realignment program.
Budget and schedule may affect project implementation and completion of the
EGSE Phase 2 Project.
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 15
FOURTH QUARTER REPORT, 2017
Airfield Pavement Program
Project: C800483
Budget: $10,300,000
Phase: Construction
Start: 5/5/2011
Schedule Completion: 6/30/2021
This is a multi}~ program to
replace distressed pavement and
joint seal on the airfield starting in
2016 through 2020.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 10/25/2016
(Commission Const Auth.)
Budget/Costs Incurred
Significant Developments
2017 Airfield Replacement Project was completed in Q3 2017.
Schedule
Dollars in Millions
2018 Airfield Replacement Project was combined with other projects into a
single construction contract to minimize impacts to airfield operations. The
contract was advertised in Qu 2017 and bid opening was in Q1 vxyz{
12
4
1.5
2
0.8
Change Order
Current Quarter
Number of COs
0
Amount of Cos
$0
Justification for COs: None at this time
Project Total
0
$0
0.5
0.4
0.4
0.4
0.3
0.2
0.1
0.0
0
Initial Change
Orders
2017 Photo
Risks
More pavements identified needing urgent replacement and added to the scope.
Risk of delay in project delivery due to the bid protest.
Budget Transfers
From
C800483
To
C800914
Costs
Incurred
2017 Construction Costs
Dollars in Millions
Project is within budget. Work project U003u| has been moved to CIP
Czxx|yu{
16 - Port of Seattle 4Q 2017 Report
6
Authorized Forecasted
Budget
AIRPORT
8
0
Projects will occur annually through 2020. 2017 project was completed. The
contract bid opening of vxyz project was in Q1 vxyz and the review of bids is
underway.
Amount
$22,000,000
10.3
10
Spent
FOURTH QUARTER REPORT, 2017
Alternate Utility Facility
Project: C800538
Budget: $37,200,000
Phase: Construction
Start: 8/4/2015
Schedule Completion: 3/31/2018
Build and house a new 30MW
electrical backup power generation
facility for the Airport.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset:
(Commission Construction Auth.)
Construction has commenced and is proceeding on schedule. All permits have
been issued and long lead items procured. Major equipment delivery is
underway in Q 2017. Construction is anticipated to complete in Q1
Schedule
Project is currently on schedule for completion in Q2
Dollars in Millions
Budget/Costs Incurred
Significant Developments
37.2
40
35
30
25
20
15
10
5
0
35.0
15.1
Budget
Authorized Forecasted
Project is within budget per the amount authorized by the Commission.
Construction Costs
Current Quarter
0
$0
Project Total
1
$0
Risks
Federal regulatory requirements may adversely impact schedule and budget.
$30
Dollars in Millions
Change Order
Number of COs
Amount of Cos
Justification for COs: N/A
Costs
Incurred
27.9
$25
$20
12.9
$15
$10
$5
0.0
$Initial
Change
Orders
Spent
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 17
FOURTH QUARTER REPORT, 2017
South Satellite Interior Renovations
Project: C800549
Budget: $6,256,000
Phase: Construction
Start: 11/4/2012
Schedule Completion: 6/30/2017
Modify the mezzanine and concourse
levels of the South Satellite to improve
the passenger experience.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 3/22/2016
(Commission Construction Auth.)
Significant Developments
Budget/Costs Incurred
Escalator panels are currently being installed.
Schedule
Remaining expense work to re escalator panels was delayed due to
production issue during the laminating manufacturing process. Anticipate
completion in Q1
Dollars in Millions
6.4
6.26
6.2
5.94
6
5.71
5.8
5.6
5.4
Budget
Authorized Forecasted
This project is on budget.
Current Quarter
Project Total
Number of COs
2
50
Amount of COs
($2,185)
$295,294
Justification for COs: Varying site conditions, design changes.
Risks
Risks have been mitigated during construction.
Dollars in Millions
Construction Costs
Change Order
4
3.5
3
2.5
2
1.5
1
0.5
0
AIRPORT
18 - Port of Seattle 4Q 2017 Report
From
To
Photo
3.4
3.1
0.3
Initial
Budget Transfers
Amount
$0
Costs
Incurred
Change
Orders
Spent
FOURTH QUARTER REPORT, 2017
Satellite Renovation and Lobbies
Project: C800556
Budget: $670,671,192
Phase: Construction
Start: 7/24/2012
Schedule Completion: Q3 2021
Renovation and expansion of the North
Satellite ÂÃÄÅÆÇ¸ including NSAT
Satellite Transit System ÂÄÆÄÇ stations
Ȧ©É¦©Ê¤È¸ ramp level, Concourse level,
and ne¡ rooftop airline lounge.
Significant Developments
Executed remaining Base Building subcontracts and conformed document set
issued. Phase 1 basement concrete is complete and started structural steel
erection. North Satellite escalator replacement started ¡¢£¤ NS4 removal.
Decision made for HP to procure and install Holdroom Case¡¥¦§ and install
Port purchased PLBs. Rain¡¨£©¦ harvest tanks are installed and buried.
Submitted LEED application to USª<<¬
Project Status:
Schedule: Ë¢£¤¢½ or Ahead
Budget: On or Under
Status Reset: ±Ì°·Ì®¯°¾
(Commission Construction Auth.)
Budget/Costs Incurred
TOTAL
670.6
Dollars in Millions
Schedule
Budget
Commission authorized overall budget of µ¶·±¸¹®°¸°º® Capital and
$12,300,000 Expense for a total of $670,621,192. Subse>>¼©½£ transfer of
$50,000 from C±¯¯¾±® STS Display Upgrade brings overall
budget/authorization to $670,671,192.
Change Order
Current Quarter
Project Total
°±®
Number of Cos
61
Amount of Cos
$665,106
$9,072,206
Justification for COs: E¿ÀÁ varying site conditionsÁ Contract scope changes
108.8
Authorized Forecasted
Costs
Incurred
Construction Costs
500
Dollars in Millions
Coordinate and monitor ®¯°± Taxi¡¨² ³¦¥´ect and NSAT Phase 1 opening.
Finalize direction for Phase 2 ground board operations and Concourse C
vertical core STS station upgrades. Finalize agreement for Port/AS cost sharing
items.
670.6
700.0
600.0
500.0
400.0
300.0
200.0
100.0
0.0
453.6
400
300
200
51.5
100
9.0
0
MACC
Change
Orders
Spent
Photo
Risks
Maintaining budget and schedule due to further changes, errors and omissions,
differing site conditions, customer service and unforeseen events during
construction. Challenge of construction phasing for maximum gate availability
during construction
Budget Transfers
Amount
From
To
$50,000
C±¯¯¾±®
C±¯¯··¶
$0
Transfer of $50,000 for STS Display Upgrade at Concourse C STS Station
AIRPORT
Port of Seattle 4Q 2017 Report - 19
FOURTH QUARTER REPORT, 2017
International Arrivals Facility (IAF)
Project: C800583
Budget: îïðñòóôôòôôô
Phase: Design
Start: 6/25/2013
Schedule Completion: 6/30/2020
Planning, design, and construction of a
neÍ Federal õÜâpection Services (Fõöá
facility including a pedestrian ÍÛ÷ÖÍÛø
connecting the South Satellite and seven
Concourse A gates to the neÍ õùúû
Project Status:
Schedule: üÑÒÓÑÜ or Ahead
Budget: On or Under
Status Reset: 12/èýþÏÿ8
(Commission Authorization to start
Design & Construction)
Corridor.
Schedule
The ØÕÔ×ect remains on schedule. The DB baseline schedule completion for
Dollars in Millions
Significant Developments
Budget/Costs Incurred
RevieÍ of ÎÏÐ design completed. The Design/Build team (DB), Clark/SOM, is
761.5
761.5
800
proceeding ÍÑÒÓ design and procurement. Ninety percent of the ÍÔÕÖ (by value)
700
has been bid out. Started ma×ÔÕ construction of the main building and Sterile
Phase 2 is 2nd Quarter 2020.
600
500
400
300
200
100
0
153.1
Authorized Forecasted
Budget
Costs
Incurred
Dollars in Millions
The DB is over the Target Budget. The DB and the Port are exploring
Construction Costs
opportunities to align the design to the overall budget goal. The ÙÚÛÕÛÜÒÝÝÞ
Maximum Price (Ùßàá timetable is ad×ÚâÒÑÜã to alloÍ both parties to agree that
700
573.0
600
the risks and opportunities presented are sufficiently identified and addressed.
500
$101M in additional Commission Authorization ÍÛâ obtained in August to
400
support DB design, Ùäâå and subæçÔÜÒÕÛçÒÔÕ aÍÛÕÞâ and Port management costs
300
until the Ùßà is negotiated.
Change Orders
Risks
Potential cost and schedule impacts from forecasted shortages of materials and
skilled labor in the current robust Seattle construction market remains a risk.
Programming and scope changes driven by dynamic operational environment
and emerging customer/stakeholder interests and reíÚÝâÒâ
Budget Transfers
$0
AIRPORT
20 - Port of Seattle 4Q 2017 Report
86.0
100
6.4
0
Current Quarter
Project Total
Number of COs
22
è
Amount of COs
$3,751,379
$ ÎåéêÎåèéÏ
Justification for COs: OÍÜÝÕ added scope on Ùë Lotì added DB fee on
previous design change orders
Amount
200
From
To
Initial
Change
Orders
Spent
FOURTH QUARTER REPORT, 2017
Enhancement
Project: C800585
Budget: $10,676,000
Phase: Construction
Start: 11/4/2012
Schedule Completion: 10/2/2018
Upgrade Wi system in the public
and ramp operational areas of the
Airport. Provide micromw w
cabinets on the ramp of each
concourse to extend communications
infrastructure.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset:
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Construction for Concourse C and the Main Terminal is complete. Construction
for Ramp Wi on Concourse A, B, C, D, and the South Satellite is nearing
completion. Bids for Phase II Wi in the Baggage Claim, BagB G
Marie Lindsey Hall, and Satellite Transit System Stations due in February.
Design for passenger loading bridges and South Satellite interior moving
f Bard from 3
12
Dollars in Millions
W
10
8
4.60
6
4
2
Authorized Forecasted
ect is on schedule.
ect is Bw
Costs
Incurred
Construction Costs
Budget
The p
10.68
0
Schedule
The p
10.68
budget.
3.00
2.75
Dollars in Millions
2.50
Change Order
2.00
Current Quarter
11
Number of COs
Amount of COs
$3
Justification for COs: Changed conditions.
Project Total
13
$3
1.37
1.50
1.00
0.50
0.03
0.00
Initial
Change
Orders
Spent
Risks
Unforeseen conditionsc p ect team has mitigated through a thorough revieB
of site conditions including opening up B and ceilings.
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 21
FOURTH QUARTER REPORT, 2017
Security EE L Breach Control Phase 2
Project: C800605
Budget: $11,100,000
Phase: Design
Start: 10/15/2015
Schedule Completion: 1/31/2020
Installation of automated security
breach control ee'()*#+& at exits to
ConcourseC, A, C and North and
South Satellite Transit System
exits.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 7/12/2016
(Commission Construction Auth.)
Significant Developments
Budget/Costs Incurred
Design and procurement engineered building systems design build document
preparation underr !"
12.000
11.1
11.1
Dollars in Millions
10.000
8.000
Schedule
ProP#%& schedule delayed as design and procurement document development has
taken longer than anticipated.
6.000
3.1
4.000
2.000
0.000
Budget
Authorized Forecasted
ProP#%& is on budget.
Change Order
Number of COs
Amount of Cos
Current Quarter
0
$0
Project Total
0
$0
Risks
Need to ensure that existing conditions have not significantly changed.
Budget Transfers
Amount
$0
AIRPORT
22 - Port of Seattle 4Q 2017 Report
From
To
Construction Costs
None at this time
Photo
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Checked Baggage Recapitalization/Optimization
Significant Developments
Phase 1 MaM-. construction
The follol/01 activities are currently underl24 in the Central Terminal ramp
area:
• Concrete and curb demolition in the ramp area is nearing completion5
• Electrical and mechanical infrastructure relocations and installation is
ongoi015
• The nel building bump out slab and curb l266 have been completed5
• Micro piles installations at the ramp leading to the basement have been
completed5
• Pre7/09:2662:/-0 meetings for soil nail and shotcrete have been held l/:;
the contractor5
• Chilled l2:<. piping relocation in the basement has started and is
ongoi015
• Contractor has started mechanical and plumbing installation in B
Concourse ramp area for nel maintenance locker and break area5
• Steel erection for the north and south elevator pits has been completed5
• Conveyor header steel installation has started5 and
• Delivery of nel conveyor has been arriving -079ite.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
445.1
500
Dollars in Millions
TSA approached the Airport in 2012
l/:; plan to replace all federally ol0K<0:A In addition the >.-Mect
replaces the remainder of the outbound
baggage system.
400
300
200
136.3
100
33.8
0
Authorized Forecasted
Costs
Incurred
Construction Costs
60
Dollars in Millions
Project: C800612
Budget: $445,050,000
Phase: Construction
Start: 2/26/2013
Schedule Completion: 2/28/2025
52.0
50
40
30
20
10
8.3
0.4
0
ProM<=: coordination l/:; other Port and Tenant >.-Mects is ongoing.
Initial Change
Orders
Spent
Phase 2: Consultant and sub7=-09s6:20:9 have been -079ite investigating right
of l249 and reviel/01 existing conditions. They have also been l-.?/01 on
construction se@s<0=/01A
Schedule
Phase 1 is one month behind the original baseline schedule (approved in April
DFHIJ5 ;-lever, Substantial Completion is still anticipated in Q3 2019.
Phase 2 l/66 continue l-.?/01 on construction se@s<0=/01A
All phases are scheduled to be complete in Q1 2025. Consultant and sub
consultants have been on site investigating right of l249 and reviel/01 existing
conditions. They have also been l-.?/01 on construction se@s<0=/01A
Port of Seattle 4Q 2017 Report - 23
Budget
The NOQRect is currently authorized for $136 million of the $445 million Budget
for completion of Phase 1 and design of Phase 2.
Change Order
Current Quarter
2
$135,316
Project Total
Number of COs
S
Amount of Cos
$370,020
Justification for COs:
• Modify utilities T Unforeseen site conditions
• Accelerate phase 2 manual encode into phase 1 T Reduce risk to operations
Risks
•
•
•
Continuity may be lost betbUUV the different phases of the NOQRect.
EXYZN[UV\ manufacturers may differ betbUUV phases, reXYZOZV] Port
Maintenance creb^ to maintain and replace many models of eXYZN[UV\_
ShutdobV^ may impact airline operations if they last longer than
anticipated.
Budget Transfers
Amount
0
AIRPORT
24 - Port of Seattle 4Q 2017 Report
From
To
FOURTH QUARTER REPORT, 2017
Dining and Retail Infrastructure Modernization
Project: C800638
Budget: $14,889,000
Phase: Construction
Start: 10/28/2014
Schedule Completion: 6/30/2020
Pro|}~y is to provide infrastructure
modifications, re}xx of spaces,
and one neu Children Play Area in
support of the Airport Dining and
Retail concessions plan.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Design Package `a is dggh complete. Construction to support Lease ijknq `t
continues for scopes of ukjv that can be completed uxyzkny impacting existing
tenants.
Schedule
As the construction schedule depends on the leasing schedule, impacts to that
schedule have delayed construction from the plan. Construction ux{{ be able to
support the revised leasing schedule.
Budget
Currently on budget, but delays may impact budget due to escalation and
extended overhead.
Dollars in Millions
Budget/Costs Incurred
Significant Developments
16
14
12
10
8
6
4
2
0
14.89
14.89
4.90
Authorized Forecasted
Costs
Incurred
Construction Costs
Not applicable
Change Order
Number of COs
Amount of COs
Justification for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Risks
Construction is linked uxyz leasing, unforeseen site conditions
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 25
FOURTH QUARTER REPORT, 2017
CCTV Camera and System Enhancement
Project: C800642
Budget: $13,000,000
Phase: Construction
Start: 11/4/2012
Schedule Completion: 12/29/2018
Add cameras and improve the video
management system at the Airport.
Pro funded by a TSA Other
Transaction Agreement (OTA)
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 5/23/2017
(Commission Construction Auth.)
Significant Developments
Schedule
Pro is on schedule. Pro team evaluating means to ensure completion of
OTA grant funding may re additional
Dollars in Millions
Budget/Costs Incurred
Ramp cameras contract has been closed out. Construction of Terminal Building
camera installations under The video management system upgrade is
progressing and the cutover to the ne system is under
13.00
14
12
10
8
6
4
2
0
13.00
5.36
Authorized Forecasted
Budget
Costs
Incurred
The ect is budget.
Construction Costs
Change Order
Number of COs
Amount of COs
Justification for COs: Design changes.
Project Total
4
Risks
1
Dollars in Millions
Current Quarter
5
0.87
0.84
0.8
0.6
0.4
0.2
0.08
0
The ect team is revie¡ as¢£¤ information and site conditions in order
to understand variances.
Budget Transfers
Amount
$0
AIRPORT
26 - Port of Seattle 4Q 2017 Report
From
To
Initial
Change
Orders
Spent
FOURTH QUARTER REPORT, 2017
I¥¦ Segregation Improvements
Project: C800655
Budget: $1,142,000
Phase: Design
Start: 8/1/2016
Schedule Completion: 2/13/2019
Install Total Organic Carbon (TOC) Project Status:
analyzers into the exisiting Industrial Schedule: Within or Ahead
Waste§¨ª´¯ conveyance system serving Budget: On or Under
the Terminal Areas of the Airport.
Status Reset: n/a
(Commission Construction Auth.)
Design completed November 21, 2017. A§¨©ª©<<¬ Airport Building Department
building permit to be issued. Port Construction Services has scheduled cre§ to
§®¯° on the ±¯®²ect during the dry season.
Schedule
Design §¨ completed on schedule, ±¯®²ect is scheduled for completion in
Q3 2019.
Dollars in Millions
Budget/Costs Incurred
Significant Developments
1.2
1.1
1.1
1
0.8
0.6
0.4
0.20
0.2
0
Authorized Forecasted
Budget
Design: $407,000
Construction: $735,000
Costs
Incurred
Construction Costs
Not Applicable
Change Order
Current Quarter
Number of COs
0
Amount of Cos
$0
Justification for COs: None at this time
Project Total
0
$0
Risks
Risk to ±¯®²ect³ Weather.
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 27
FOURTH QUARTER REPORT, 2017
Construction µ¶·¸¹º¸>>¹ Expansion
Project: C800688
Budget: ÛÜÝÞßàÝáâá
Phase: Closeout
Start: 8/1/2014
Schedule Completion: 9/30/2017
The expansion and reconfiguration of
the existing construction logistics
facilities (including the contractor
parking lot and associated bus stops),
and the renovation of Port field offices.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 2/23/2016
(Commission Construction Auth.)
Budget/Costs Incurred
Construction is complete and completion memos have been issued for the
Contractor Parking Lot (CPL), Logistics Lots, Field Office Renovation, and
CPL Bus Stops. CPL has been closed out. Logistics Lots ¼½¾ closed out in Q4.
Field Office Renovation and CPL Bus Stops are in closeout. The replacement
field office (changed scope) ¼½¾ placed into use in December.
Schedule
12.0
Dollars in Millions
Significant Developments
10.0
8.6
10.0
6.0
4.0
2.0
0.0
The overall ¿ÀÁÂect ¼½¾ delayed ¼ÃÄÅ completion dates of Q1 2017 for CPL Bus
Stops (delays due to ¼Æ½ÄÅÆÀ and errors and omissions), and Q4 2017 for the
replacement field office (delay due to scope change and procurement).
Authorized Forecasted
Change Order
Dollars in Millions
6
ProÂÆÇÄ forecast is ¼ÃÄÅÃÈ the revised budget. Returned ÉÊËÌÍÎÏ in final closeout
savings for Logistics Lots in Q4. Anticipate additional final closeout savings
¼ÃÄÅ Field Office Renovation ($121,000 in Q4 ÍËÐÊÑ and CPL Bus Stops
($142,000 in Q2 ÍËÐÊÑÒ
4.9
4.4
5
4
3
2
1
0.1
0
Current Quarter
Number of COs
0
Amount of COs
$0
Justification for COs: None this ÓÔ½rter.
Project Total
69
$99,533
Initial
Change
Orders
Photo
Risks
None
Budget Transfers
From
To
Cost of Construction GroÕÖ×
CPL Bus Stops: Additional ¿ÀÁÂect contingency ¼½¾ included ¼ÃÄÅÃÈ the ¿ÀÁÂect
budget for ÔÈØÈÁ¼n substandard pavement section risk. T¼Á change orders
¼ÆÀÆ issued representing ÐÙÒÊÚ of the original contract value.
AIRPORT
28 - Port of Seattle 4Q 2017 Report
Costs
Incurred
Construction Costs
Budget
Amount
$0
8.1
8.0
Replacement Field Office
Spent
FOURTH QUARTER REPORT, 2017
Fuel System Modifications
Project: C800692
Budget: $14,480,000
Phase: Construction
Start: 3/31/2017
Schedule Completion: 7/31/2017
There is a 2016 çèéãect and a 2017
The addition of fuel pits
accommodates gate reconfiguration
and éooðte operations.
çèéãect.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 9/13/2016
(Commission Construction Auth.)
Significant Developments
Budget/Costs Incurred
Schedule
Waiting for the çèéãect closeout.
Budget
Proãäåæ is êëæìëí the authorized budget. 2017 Fuel System Modifications çèéãect
returned $2,200,000 in savings in the 1st îïðrter of 2017.
Dollars in Millions
Proãäåæ is complete. This is the final report.
14.5
16
14
12
10
8
6
4
2
0
10.5
9.3
Authorized Forecasted
Costs
Incurred
Change Orders for 2016 Fuel System Modifications
Project Total
17
$371,149.72
Change Orders for 2017 Fuel System Modifications
Current Quarter
Project Total
Number of COs
12
31
Amount of COs
$19,909.50
$129,272.74
Justification for COs: Provide Instrument Valvesñ revise pneumatic test
pressure reîïëèäòäíæóñ reconciliation of COñ reconciliation of Bid Itemñ
additional êéèô reîïëèäõ to mitigate the impact to schedule caused by an
unanticipated eîïëçòäíæ procurement timeñ and value Engineering Cost
Proposalö÷ Settlement.
2016 Fuel SÿS Modification
Construction Costs
3
Dollars in Millions
Current Quarter
Number of COs
0
Amount of COs
$0.00
Justification for COs: None this îïðrter.
2
1.5
1
Budget Transfers
Amount
$300,000
From
To
øù úûûüûý
øù úûûþýý
0.4
0.5
0
Initial Change
Orders
Spent
2017 Fuel SÿS Modification
Construction Costs
Dollars in Millions
None
2.6
2.5
5
Risks
2.8
4.2
4.1
4
3
2
1
0.1
0
Initial Change
Orders
Spent
AIRPORT
Port of Seattle 4Q 2017 Report - 29
FOURTH QUARTER REPORT, 2017
C3 H
Expansion
Project: C800695
Budget: $6,300,000
Phase: Design
Start: 4/4/2016
Schedule Completion: 8/31/2019
Provide a 1,500 sf building addition Project Status:
to increase the size of Gw C3
Schedule: Delayed
passenger holdroom. Provide 1,130
Budget: On or Under
sf renovation of existing holdroom.
Status Reset: 7/11/2017
(Commission Construction Auth.)
Significant Developments
Budget/Costs Incurred
Building permit revier process rw completed. Design team revisions have
been completed.
7.000
6.30
6.30
Dollars in Millions
6.000
5.000
Schedule
4.000
Due to designer continuity challenges, the completion of the p
fallen behind schedule.
ect design has
3.000
2.000
0.70
1.000
Budget
0.000
Authorized
On budget
Change Order
Number of COs
Amount of COs
Current Quarter
0
$0
Project Total
0
$0
From
To
Risks
None at this time
Budget Transfers
Amount
$0
AIRPORT
30 - Port of Seattle 4Q 2017 Report
Forecasted
Construction Costs
None at this time
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Concourse B, C, and D Restroom Upgrades
Project: C800697
Budget: $33,047,000
Phase: Design
Start: 7/12/2016
Schedule Completion: 1/19/2022
Renovate eight sets of public
Project Status:
restrooms on Concourses B, C, and
Schedule: Within or Ahead
Budget: On or Under
D. Increase the size of a portion of
Status Reset: 9/12/2017
the existing restrooms" build ne
restrooms" build space for displaced (Commission Construction Auth.)
existing tenant functions" and
enlarge the building to add one
additional ne set of restrooms.
Budget/Costs Incurred
Construction for the first phase is under Design for the remaining ect
is 3 complete. The initial phase of restroom design is 6 complete.
Schedule
ProP is on schedule.
Budget
33.0
$35.0
$30.0
$25.0
$20.0
$15.0
$10.0
$5.0
$0.0
Dollars in Millions
Significant Developments
7.6
1.1
ProP is budget.
Authorized Forecasted
Number of COs
Amount of COs
Current Quarter
0
$0
Project Total
0
$0
Risks
Air handling capacity limits on Concourse C may re !P additional to
ensure that there is enough air for additional restrooms.
Construction Costs
2
1.5
Dollars in Millions
Change Order
Costs
Incurred
1.5
1
0.5
0.0
0.1
Change
Orders
Spent
0
Initial
Budget Transfers
Amount
$0
From
To
Photo
AIRPORT
Port of Seattle 4Q 2017 Report - 31
FOURTH QUARTER REPORT, 2017
Electric Utility SCADA
Project: C800699
Budget: $9,600,000
Phase: Design
Start: 8/5/2015
Schedule Completion: 7/29/2019
Install a Supervisory Control and
Data Ace1.s.*.-4 (SCADA) system
for the Airportms 12.47 kV Medium
Voltage (MV) +-#er distribution
net#-,n&
Project Status:
Schedule: Delayed
Budget: Forecast Overrun
Status Reset: 8797:;<=
>Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
One hundred percent design revie# is under#$%&
9.6
Schedule
Pro'()* is behind schedule due to change in +,-'ect management and a period of
inactivity due to a shortage of resources.
Budget
Change Order
Current Quarter
Number of COs
0
Amount of Cos
$0
Justification for COs: None at this point.
Project Total
0
$0
Risks
Controls #.00 be added to an existing electrical system that includes several
manufacturersm ee1.+2(4*& Unplanned shutdo#4s may be mitigated through the
Construction See1(4).45 Plan.
Budget Transfers
AIRPORT
32 - Port of Seattle 4Q 2017 Report
8
6
4
1.6
1.5
2
0
The estimate at completion exceeds the original budget estimate. The budget
increase is primarily related to market conditions and complexities #.*/ the
Po#(, Centers control systems interface.
Amount
$0
Dollars in Millions
10
From
To
Authorized Forecasted
Construction Costs
Not Applicable
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Concourse B ? C Roof Replacement
Project: C800770 ,C800702
Budget: $13,183,000
Phase: Construction
Start: 3/1/2010
Schedule Completion: 6/25/2018
Overlay the existing roof system
Project Status:
(approximately T\Y@AA SF of roofing
Schedule: Delayed
system on Concourse B and T]YAAA SF
Budget: On or Under
on Concourse C)^ install a neC
Status Reset: 1/24/2017
(Commission Construction Auth.)
elastomeric roofing system^ ladders
and fall protection^ and replace and
refurbish the existing skylight
CDE_`CaCNbbMK
Concourse C complete. Roof overlay on Concourse B is about @AB complete.
Construction has been suspended to avoid continuing roof replacement into the
CDEFIJK Anticipate reLMFNJFDEO and completing construction in Q2 QARTK
Schedule
Contract has been suspended over the CDEFIJ months.
Dollars in Millions
Budget/Costs Incurred
Significant Developments
14
12
10
8
6
4
2
0
Budget
13.18
13.18
5.33
Authorized Forecasted
ProUIVF is CDFWDE budget.
Construction Costs
Current Quarter
6
$55,245
Project Total
12
$XTYZ[@
Risks
Unforeseen site conditions and adverse CINFWIJK
5.7
5
3.9
4
3
2
1
0.1
0
Initial
Budget Transfers
Amount
$0
6
Dollars in Millions
Change Order
Number of COs
Amount of COs
Costs
Incurred
From
Change
Orders
Spent
To
AIRPORT
Port of Seattle 4Q 2017 Report - 33
FOURTH QUARTER REPORT, 2017
Central Terminal Stairs
Project: C800716
Budget: $2,910,000
Phase: Construction
Start: 2/15/2015
Schedule Completion: 6/30/2017
Build thf stairht}u near the central Project Status:
checkpoint to provide egress
Schedule: Delayed
Budget: On or Under
capacity from the mezzanine level
Status Reset: 9/13/2016
to the ticketing level on the xfx~
(Commission Construction Auth.)
secure side of the airport.
Beneficial Occupancy has been issued, lighting has been added under the stairs
and the cdfgect has been closed out. This hijj be the final report.
Schedule
Complete
Budget
Dollars in Millions
Budget/Costs Incurred
Significant Developments
3
2.9
2.8
2.7
2.6
2.5
2.4
2.3
2.9
2.9
2.5
Authorized Forecasted
Progklq htu completed hiqvix budget
Change Order
Construction Costs
2.0000
Risks
Dollars in Millions
Current Quarter
Project Total
Number of COs
05
16
Amount of COs
($76,062)
($49,237)
Justification for CO: Cost associated hiqv completing Work after Substantial
Completion.
Costs
Incurred
None at this time.
yz{|zzz
1.6
1.5
1.5000
1.0000
0.5000
0.0000
Initial
Change
Orders
(0.049)
Budget Transfers
Amount
$0
AIRPORT
34 - Port of Seattle 4Q 2017 Report
From
To
Photo
Spent
FOURTH QUARTER REPORT, 2017
North Terminal Utilities Upgrade Project
Project: C800717
Budget: $21,335,000
Phase: Construction
Start: 9/21/2010
Schedule Completion: 8/30/2019
Replace and extend the steam,
condensate and chilled
supply and return piping from the
Central Mechanical Plant to the end
of mechanical room four and to the
ends of the South and West Loops
(Commission Construction Auth.)
Budget/Costs Incurred
Schedule
Construction of the end early ect started Q4 2017. Ninety
percent design of the main ect is due Q4 2017. The schedule delayed to
accommodate a change in the contracting method of the utility tunnel.
Budget
Commission authorization to increase the ect budget is likely needed to
complete entire ect due to additional scope associated the D Concourse
Hardstand and Service Tunnel ects. Cost estimates are still in development.
Change Order
Current Quarter
0
$0
Project Total
0
$0
25
Dollars in Millions
The end early ect mechanical construction contract
a in Q2 2017. Commission authorized a contract duration extension for
the early construction contract in Q3 2017.
21.3
20
15
9.3
10
2.2
5
0
Authorized Forecasted
$2.0
$1.5
1.1
$1.0
$0.5
Risks
pipe through densely developed areas of the airport. Risks to be minimized
during design.
0.0
0.0
Change
Orders
Spent
$Initial
chedule and budget can be at risk due to the need to route large sections of
Costs
Incurred
Construction Costs
Dollars in Millions
Significant Developments
Number of COs
Amount of Cos
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
Photo
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 35
FOURTH QUARTER REPORT, 2017
Central Terminal Infrastructure Upgrade
Project: C800722
Budget: $16,834,000
Phase: Construction
Start: 5/8/2015
Schedule Completion: 4/30/2020
Install HVAC, elevators, stair
for mezzanine levels of the central
terminal. Reconfigure tenant spaces
on the Concourse level of the
central terminal in order to improve
customer service and experience.
Schedule
Project is now within schedule.
20
16.8
16.8
15
10
5
1.3
Budget
0
Project is now within budget.
Authorized Forecasted
Change Order
Current Quarter
Number of COs
0
Amount of Cos
$0
Justification for COs: None at this time
Project Total
0
$0
Risks
Risks to project: Delayed reopening of the south tenant spaces due to project
contractor construction delays, tenant design and contractor delays.
Budget Transfers
36 - Port of Seattle 4Q 2017 Report
Dollars in Millions
Pro bid opening November 14, 2017. Lo bid 8.77% below the
engineers estimate. Construction contract was awarded.
AIRPORT
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Amount
$6,190,000
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 6/27/2017
From
C800638
To
C800722
Construction Costs
Not Applicable
Photo
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Concourse C New Power Center
Add ne 3200A double ended unit
Project Status:
substation on Ramp level at column
Schedule: Delayed
line F/40 for a ne electrical room in
Budget: On or Under
Concourse C. Existing distribution
Status Reset: n/a
panels ¤°° be re¶·¯¸ from the ne
(Commission Construction Auth.)
¢er center, ne distribution panels
and branch circuit panels ¤°° be added.
Budget/Costs Incurred
Significant Developments
Ninety percent design is complete and revie is under Engineer cost
10.5
12
estimate for the ninety percent design revie is complete and ¡¢£ect probable
10
cost is ¤¥¦¤§ the approved budget.
Schedule
One hundred percent design bid documents are scheduled for completion Q1
¨©ª<< Construction completion scheduled for Q4 2019. Standardization of
ma£¢¡ electrical of e¬¤ ®¯§¥ caused design completion delays, but reduced
further risks/cost increases by ensuring that ne electrical e¬¤ ®¯§¥ ¤°° fit in
the existing space.
Budget
The budget forecast, based on ±©² design revie³ is ¤¥¦¤§ approved budget.
Dollars in Millions
Project: C800724
Budget: $10,500,000
Phase: Design
Start: 10/26/2014
Schedule Completion: 11/29/2019
8
6
4
2.0
2
0.8
0
Authorized Forecasted
Costs
Incurred
Construction Costs
Not Applicable
Change Order
Number of COs
Amount of Cos
Justification for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Risks
Airline ´¥¯ Realignment program and other ¡¢£ects may affect Concourse C
Ne Po¯¡ Center Pro£¯µ¥ Budget and/or schedule may be affected if site
conditions differ from record files.
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 37
FOURTH QUARTER REPORT, 2017
South Satellite (SSAT) Terminal Renovation
Programing, planning, design and
construction for renovation of the
SSAT
Project: C800743
Budget: TBD
Phase: Planning
Start: Q1 2017
Schedule Completion: TBD
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
Budget/Costs Incurred
Planning and programing efforts continue on a range of options including full
renovation and shorter¹º>>¼½ programs to address needs in the facility for the
next 10 ¾ 15 years.
Schedule
Q4 2017 Port¹¿ÀÁ>> goal to recommend a preferred design concept ¿Âà not met.
By the end of Q2 ÄÅÆÇÈ É¼ÊËect team ¿ÀÌÌ identify a full range of options for
consideration.
Budget
6
Dollars in Millions
Significant Developments
5
4.6
4
3
1.7
2
1
0
Authorized Forecasted
Costs
Incurred
Construction Costs
This ɼÊËect ¿Âà included in the ÄÅÆÇ ¾ 2022 capital budget and plan of finance None
¿ÀºÍ preliminary estimated total cost of $600 million. This estimate ¿ÀÌÌ be
refined as the scope and timing of the ɼÊËect is more clearly understood.
Photo
Peak Hour Operation
Change Order
Number of COs
Amount of COs
Current Quarter
0
$0
Project Total
0
$0
From
To
Risks
TBD
Budget Transfers
Amount
$0
Cost of Construction Growth
N/A
AIRPORT
38 - Port of Seattle 4Q 2017 Report
FOURTH QUARTER REPORT, 2017
Auburn Mitigation Road Removal
Project: C800760
Budget: $720,000
Phase: Construction
Start: 8/1/2017
Schedule Completion: 12/15/2017
Wetland mitigation site
enhancements, including installing
perimeter chainÞßÚÝà fence and
converting interior paths/roads to
forest.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 6/2ÔáÑÒÓâ
(Commission Construction Auth.)
Construction started on schedule in August 2017, and road removal has been
completed. Contract for fence construction is scheduled for Authorization on
March 13th.
Schedule
Fencing ÎÏÐ scheduled for October 2017, but delay in contract procurement has
pushed start date into April ÑÒÓÔÕ Construction is scheduled for completion by
July 31, ÑÒÓÔÕ
Budget
The ÖרÙect forecast is ÎÚÛÜÚÝ the approved budget and authorization
Dollars in Millions
Budget/Costs Incurred
Significant Developments
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
0.7
0.7
0.3
Authorized Forecasted
Costs
Incurred
Construction Costs
Not Applicable
Change Order
Number of COs
Amount of Cos
Current Quarter
0
$0
Project Total
0
$0
From
To
Risks
None at this time
Budget Transfers
Amount
$0
AIRPORT
Port of Seattle 4Q 2017 Report - 39
FOURTH QUARTER REPORT, 2017
Concourse B Ramp Level ãäåæçääè
Project: C800761
Budget: $5,548,000
Phase: Construction
Start: 4/12/2015
Schedule Completion: 2/28/2018
Construct a ramp level holdroom on Project Status:
Concourse B to serve airline
Schedule: Delayed
Budget: Forecast Overrun
passengers bussed to and from
Status Reset: 11/ìýéêëþ
remotely parked flights at
(Commission Construction Auth.)
hardstands.
Budget/Costs Incurred
Temporary occupancy received. Anticipate activating the site in Q1 éêëìí
Additional funds îïðð be reñòïóôõ in order to address several elements of the
öó÷øect. Additional budget authorization îïðð be reñòôùúôõ in Q1 éêëìí
Schedule
The öó÷øect remains behind schedule due to a number of factors including site
conditions and design changes.
5.9
6
Dollars in Millions
Significant Developments
5.8
5.5
5.6
5.4
5.1
5.2
5
4.8
Authorized Forecasted
Budget
The öó÷øect budget îïðð need to be increased in order to address changed site
conditions, changed design elements and additional scope reñòïóôûôüúùí
Construction Costs
Current Quarter
2
$64,743
Project Total
21
$262,673
Risks
Dollars in Millions
Change Order
Number of COs
Amount of COs
Justification for COs:
3.5
3
2.5
2
1.5
1
0.5
0
3.2
2.8
0.3
Initial
Additional budget îïðð be reñòïóôõ in order to complete the öó÷øect.
Budget Transfers
Amount
$0
AIRPORT
40 - Port of Seattle 4Q 2017 Report
From
To
Costs
Incurred
Change
Orders
Spent
FOURTH QUARTER REPORT, 2017
Telecommunications Meet Me Room
Airport Telecommunications ÿ"
Me Roomÿ is a gateg to the
internet and alloga qck, reliable,
and costc netgn
connections for all of the airport a
tenants
Project: C800762
Budget: $3,928,000
Phase: Design
Start: 11/20/2016
Schedule Completion: 2/4/2020
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 9/26/2017
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Selected A/E from IDIQ contract.
5.000
3.93
Dollars in Millions
3.93
Schedule
4.000
On schedule
3.000
2.000
Budget
On budget
0.000
Authorized
Change Order
Number of COs
Amount of COs
0.67
1.000
Current Quarter
0
$0
Project Total
0
$0
From
To
Forecasted
Costs
Incurred
Construction Costs
None at this time
Risks
None at this time
Budget Transfers
Amount
$0
AIRPORT
Port of Seattle 4Q 2017 Report - 41
FOURTH QUARTER REPORT, 2017
Terminal
Construct a 32,500 SF building
using the alternative public Ww
design/build method to support
passengers bused to and from
airline flights parked at remote
hardstands.
Project: C800769
Budget: $38,400,000
Phase: Construction
Start: 2/28/2016
Schedule Completion: 6/30/2018
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 9/27/2017
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Sloping WalkW construction to complete in February. Holdroom Hardstand
excavation complete and floor slab to complete in February.
Schedule
ProP is on schedule.
Budget
38.4
38.4
40.000
35.000
30.000
25.000
20.000
15.000
10.000
5.000
0.000
Dollars in Millions
Concourse D H
ProP is on budget.
7.4
Authorized Forecasted
Current Quarter
Number of COs
Amount of COs
8
$190,276
Project Total
17
$226,225.00
Construction Costs
30.000
24.28
25.000
Dollars in Millions
Change Order
Costs
Incurred
20.000
Risks
15.000
The pPect schedule is tight.
10.000
AIRPORT
42 - Port of Seattle 4Q 2017 Report
0.23
0.000
Budget Transfers
Amount
$0
4.91
5.000
Initial
From
To
Photo
Change
Orders
Spent
FOURTH QUARTER REPORT, 2017
D6 Gate Modifications
Project: C800771
Budget: $2,200,000
Phase: Construction
Start: 9/20/2015
Schedule Completion: 12/4/2017
Add case!#$ to holdroom, access
Project Status:
control to the exterior door and an
Schedule: Delayed
ADA sloped % $%& from holdroom Budget: On or Under
to the ramp level for passengers to
Status Reset: 9/12/2017
(Commission Construction Auth.)
gain access to buses to transport them
to remotely parked aircraft.
Budget/Costs Incurred
Significant Developments
Pro is complete. This be the final report.
Dollars in Millions
2.3
Schedule
Pro is complete.
Budget
Pro is on budget.
2.2
2.2
2.2
2.1
2.0
2
1.9
1.8
Authorized Forecasted
Change Order
Number of COs
Amount of COs
Current Quarter
0
$0
Project Total
0
$0
Costs
Incurred
Construction Costs
Not Applicable
Photos
Risks
None at this time.
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 43
FOURTH QUARTER REPORT, 2017
South Satellite Narrow Body Configuration
Project: C800781
Budget: $5,500,000
Phase: Construction
Start: 2/23/2016
Schedule Completion: 6/29/2018
Planning, design and construction
of three ne' narro' body positions
at the S. Satellite. Scope includes
ne'< 1 passenger loading bridge
(PLB), 1 fuel pit, a passenger ramp
at S10, portable ee=(,>0:)? and
pavement marking.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 2/23/2016
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Construction started. Design advancing '()* overall IAF program.
On schedule and blends '()* the IAFI+ design and construction schedule. Final
design completed in Q2 2017. Due to scheduling updates for the IAF ,-./ect,
completion of the Narro' Body Pro/01) '(22 be Q2 34567 G9)0 closures '(22 be
minimal (one or t'. days) due to the ne' design.
Dollars in Millions
Schedule
5.5
6
5.5
5
4
3
2
0.9
1
0
Authorized Forecasted
Costs
Incurred
Budget
Construction Costs
Not Applicable at this time
Pro/01) is currently '()*(: budget.
Change Order
Project Total
0
$0
Risks
•
•
•
Current gating needs limit the ability to take gates out of service.
All '.-; takes place outside, '09)*0- could impact construction schedule.
Change in the layout of the SSAT (specifically adding parking positions)
'(22 trigger an addendum to the SEPA and NEPA for the IAF Pro/01)7
Budget Transfers
Amount
$0
AIRPORT
44 - Port of Seattle 4Q 2017 Report
From
To
5
Dollars in Millions
Number of COs
Amount of Cos
Current Quarter
0
$0
4.6
4
3
2
0.8
1
0.0
0
Initial
Change
Orders
Spent
FOURTH QUARTER REPORT, 2017
EmergencE Generator Control Renewal and Replacement
Project: C800784
Budget: $2,640,000
Phase: Design
Start: 12/28/2015
Schedule Completion: 10/18/2019
Replace and reiNCO\Ct] generator
programmable logic controllers
(PLCs). Install load bank rRST controls
for ^R_X Safety` code reUVRCXD
generator load testing.
Project Status:
Schedule: Delayed
Budget: Forecast Overrun
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Design revier is @AB complete, progressing tortCD FAB design. EngineerJK
cost estimate is underrtLM
Schedule
Delayed due to NCOQect coordination rRST other NCOQects that are in design or
construction phases.
4
Dollars in Millions
Significant Developments
3.0
3
3
2
2
1
0.8
0.3
1
0
Budget
Authorized
Forecasted
Thirty percent design estimate indicates a budget increase may be reUVRCXDM
Change Orders
Current Quarter
Number of COs
0
Amount of Cos
$0
Justification for COs: None this UVtrter
Project Total
0
$0
Costs
Incurred
Construction Costs
Not applicable
Risks
During YAB design, additional iniKZONX rOC[ rtK identified that is expected to
impact NCOQect budget. Current budget forecast shorK an increase from $2.5M
to $2.9M. Completion of @AB cost estimate is underrtLM Consideration for
potential budget increase reUVXKS shall be evaluated during this revierM
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 45
FOURTH QUARTER REPORT, 2017
PLB Renew & Replace Phase 2
Project: C800793
Budget: $10,000,000
Phase: Design
Start: 12/17/2015
Schedule Completion: 12/12/2020
Replace nine passenger loading
bridges (PLBxyz
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 2/2{|}~
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Proposals for PLBs bdfd received from vendors in Q4 2017. Contract abhfjdjk
Dollars in Millions
12
Schedule
Proldmo is on schedule to complete in Q4 2020.
Budget
Proldmo is bsousv budget
10.0
10
8
6
4
2.3
2
0.2
0
Authorized Forecasted
Change Order
Number of COs
Amount of COs
Current Quarter
0
$0
Project Total
0
$0
From
To
Risks
N/A
Budget Transfers
Amount
$0
AIRPORT
46 - Port of Seattle 4Q 2017 Report
Costs
Incurred
Construction Contract Cost
Not Applicable
FOURTH QUARTER REPORT, 2017
SSAT Infrastructure
Project: C800798
Budget: $13,925,000
Phase: Permitting
Start: 9/19/2016
Schedule Completion: 6/30/2020
Replace hot and cold deck fans,
coils and controls energy
efficient ne air handler, coils and
controls.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset:
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Schedule
Pro is on schedule
Budget
Budget increased in November to account for market conditions and
complexity of the
Change Order
Number of COs
Amount of COs
Current Quarter
0
$0
Project Total
0
$0
Dollars in Millions
Additional funds approved in Q4 2017. Advertised in Q4 2017.
14
12
10
8
6
4
2
0
12.3
12.3
0.6
Authorized Forecasted
Costs
Incurred
Construction Contract Costs
Not Applicable
Risks
Market conditions and material availability may impact ect costs.
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 47
FOURTH QUARTER REPORT, 2017
¡¢£¤¢¥¦§ Fre¨©§ª<<¬ Drive
Project: C800801
Budget: $6,834,000
Phase: Design
Start: 7/10/2017
Schedule Completion: 11/29/2019
¶eplace 47 of the oldest Variable
Fre·¸¹º>>¼ Drives (VFDs) installed
Project Status: Design
Schedule: Within or Ahead
at Seattle Tacoma International Budget: On or Under
Status Reset: 5/23/2017
Airport.
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Dollars in Millions
Fifteen percent bases of design submittal ®¯ received on November 17, 2017.
Schedule
Design submittal ®¯ on schedule.
Budget
Design Budget: $2,025,000
Construction Budget: °±²³´µ²´´´
Costs
Incurred
0.8
0.6
0.4
0.2
0.0
0.0
0.0
Initial
Change
Orders
Spent
0
Budget Transfers
48 - Port of Seattle 4Q 2017 Report
0.1
1
Dollars in Millions
Project Total
0
$0
None
AIRPORT
2.0
Construction Contract Costs
Current Quarter
0
$0
Risks
Amount
$0
6.8
Authorized Forecasted
Change Order
Number of COs
Amount of COs
8
7
6
5
4
3
2
1
0
From
To
VFD powering a 350 HP motor
FOURTH QUARTER REPORT, 2017
SSAT Structural Improvements
Project: C800818
Budget: Û4,150,000
Phase: Construction
Start: 12/28/2015
Schedule Completion: 10/6/2018
Improvements to the SSAT
building to address structural
deficiencies based upon design
dead and live loads. Work includes
asbestos abatement.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: ÁÜÁÜÒÓÔÝ
(Commission Construction Auth.)
Budget/Costs Incurred
Completed ready to bid documents in October and advertised for construction
bids in November. Received and opened three bids in December that ranged
from ½¾½¿ to À¾Á¿ belo the engineerÃÄ estimate of $1,796,000. Issued and
retracted notice of intent to aÂÅÆÇ ÂÈÉÊ apparent lo bidder PCL Construction
due to a contract compliance issue involving the resolution of small business
reËÌÈÆÍÎÍÏÉľ Submitted concourse level ÂÐÆÑ for permits (PCS scope).
5.0
Dollars in Millions
Significant Developments
4.2
3.0
2.0
0.5
1.0
0.0
Schedule
Authorized Forecasted
The completion of design has been delayed into Q4 2017 due to scope changes
and resource constraints. Contract compliance issue may delay contract
execution currently planned for January ÒÓÔÁ¾
Dollars in Millions
Overall ÕÆÐÖect budget has increased from $3,600,000 to $4,150,000 ÂÈÉÊ
$300,000 in additional ÕÆÐÖect contingency to address risks. Commission
authorized additional funds on August Á× 2017. Staff anticipates the return of
$300,000 of ÕÆÐÖect contingency given the good bid results.
Costs
Incurred
Construction Contract Costs
$2.00
Budget
1.7
$1.50
$1.00
$0.50
0.0
0.0
Change
Orders
Spent
$-
Change Order
Number of COs
Amount of Cos
4.2
4.0
Initial
Current Quarter
0
$0
Project Total
0
$0
Photo
Risks
•
PreØÙÐÏÄÉÆÌÚÉÈÐÏ Delay: Process to obtain airport badges and custom seals
for the Contractor and subcontractors delays the start of construction.
Budget Transfers
Amount
$0
From
To
Column to be Strengthened (Ramp Level)
AIRPORT
Port of Seattle 4Q 2017 Report - 49
FOURTH QUARTER REPORT, 2017
C60 Interim Baggage System Project
Implement four distinct scope elements
êõäò the ßîâective of increasing
reliability and capacity on the C60
baggage system through the interim
period before the Baggage Optimization
Proâáãäð
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Security Þßàá Tracking Enhancements Proâáãäå TSA reimbursed the Port for
reæçáèäáé change to operations in the C60 Search Room. C60 baggage system
has been operational since substantial completion êëè achieved in midìíãäßîáïð
Performance improvements resulting from the Reìãßàäïßñ element include
improved diagnostics, increased throughput, and gridlock prevention. TSA
Search Room Expansion Proâáãäå Internal Port resources completed remaining
puncòìñist items at contractoróè cost.
14.2
14.5
Dollars in Millions
Project: C800825
Budget: ûüýÿÿ$$þ$$$
Phase: Construction
Start: 12/13/2015
Schedule Completion:
10/10/2017
14
13.5
13.5
13
12.4
12.5
12
11.5
Authorized Forecasted
Schedule
Budget
udget is êõäòõà the authorized amount. Proâáãä Savings is being returned.
Construction Costs
6
Dollars in Millions
All four elements of this ôïßâect êáïá designed on a fast track schedule. The
reæçõïáé contractor completion date for the TSA Search Room Expansion êëè
delayed until Q1 2017. The completion date for the Reìãßàäïßñ element êëè
delayed due to complications during initial TSA testing and a TSA funded
change to C60 operations. The overall ôïßâect reached substantial completion in
Q4 2017. Proâáãä closeout process êõññ continue during Q1 ö÷øùð
Costs
Incurred
5.4
5.1
5
4
3
2
1
0.1
0
Initial Change
Orders
Change Order
Current Quarter
2
Project Total
Number of COs
Amount of COs
$102,136.34
Justification for COs: Varying site conditions, error/emissions by oêàáï and
designer, and regulatory reæçõïáúáàäèð
Risks
No risks anticipated at this time, contingency funds available if needed.
Budget Transfers
Amount
$0
AIRPORT
50 - Port of Seattle 4Q 2017 Report
From
To
Spent
FOURTH QUARTER REPORT, 2017
Arc Flash H Mitigation
Project: C800826
Budget: $7,533,000
Phase: Design
Start: 9/21/2016
Schedule Completion: 12/17/2019
Replace nine medium voltage fused
ss s medium voltage
circuit breakers at six p ser
centers.
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Design is progressing.
7.53
7.53
Dollars in Millions
8.000
7.000
6.000
5.000
4.000
3.000
2.000
1.000
0.000
Schedule
On schedule
Budget
On budget
0.12
Authorized
Change Order
Number of COs
Amount of COs
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 9/26/2017
Current Quarter
0
$0
Project Total
0
$0
From
To
Forecasted
Costs
Incurred
Construction Costs
None at this time
Risks
None at this time
Budget Transfers
Amount
$0
AIRPORT
Port of Seattle 4Q 2017 Report - 51
FOURTH QUARTER REPORT, 2017
Seating for Concourses B & C
Project: C800833
Budget: $9,300,000
Phase: Construction
Start: 9/25/2016
Schedule Completion: 8/10/2018
Replace existing passenger
holdroom seating in Concourses B
and C. Provide electrical
improvements to support required
wer for new seating.
Early w to install new seating and electrical wer at G C2 and C3 w
completed. Design w w completed for remainder of holdrooms in
Concourses B & C.
Schedule
Construction of early w at G C2 and C3 w completed in November,
ahead of schedule. Balance of ect is behind schedule due to additional
design review for seating layout that w required.
Budget
ProP expenditures are proceeding in accordance w budget.
Change Order
Current Quarter
0
$0
Project Total
0
$0
From
To
Risks
None
Budget Transfers
Amount
$0
AIRPORT
52 - Port of Seattle 4Q 2017 Report
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Number of COs
Amount of COs
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 4/11/2017
10
Dollars in Millions
9.3
9.3
8
6
4
2
0.2
0
Authorized Forecasted
Costs
Incurred
Construction Contract Costs
N ApplicaA
FOURTH QUARTER REPORT, 2017
Ground Based Augmentation System (GBAS) Upgrade
Project: C800834
Budget: $3,529,000.00
Phase: Design
Start: 1/5/2017
Schedule Completion: 12/31/2020
Upgrade Sea-Tac's Ground Based
Augmentation System (GBAS)
from a beta system to a fully
functioning navigational aid.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 9/12/2017
(Commission Const Auth.)
Budget/Costs Incurred
Significant Developments
Finalizing contract with Honeywell.
4.6
Dollars in Millions
5
Schedule
Contract negotiations taking longer than anticipated.
Budget
Project is within budget.
3.5
4
3
2
1
0.1
0
Authorized Forecasted
Change Order
Current Quarter
0
$0
Project Total
0
$0
Risks
None at this time.
Budget Transfers
Amount
$0
Construction Contract Costs
1
Dollars in Millions
Number of COs
Amount of COs
From
To
Costs
Incurred
0.8
0.6
0.4
0.2
0.0
0.0
0.0
Initial
Change
Orders
Spent
0
AIRPORT
Port of Seattle 4Q 2017 Report - 53
FOURTH QUARTER REPORT, 2017
Tenant Telecommunications DEMARC Upgrade
Project: C800841
Budget: $2,815,000
Phase: Design
Start: 2/27/2017
Schedule Completion: 4/28/2021
Scope:
Standardize tenant network demark
packages for many existing legacy
installations and vacant properties
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 9/26/2017
(Commission Construction Auth.)
Significant Developments
Budget/Costs Incurred
Designer is working on 15% design.
3.000
2.82
Dollars in Millions
2.500
Schedule
2.000
On schedule
1.500
1.000
Budget
0.72
0.500
On budget
0.01
0.000
Authorized
Forecasted
Change Order
Number of COs
Amount of COs
Current Quarter
0
$0
Project Total
From
To
0
$0
Risks
None at this time
Budget Transfers
Amount
$0
AIRPORT
54 - Port of Seattle 4Q 2017 Report
Construction Costs
None at this time
Costs
Incurred
FOURTH QUARTER REPORT, 2017
AOA Perimeter Fence Line Standards
Compliance
Project: C800842
Budget: $5,680,000
Phase: Design
Start: 1/29/2017
Schedule Completion: 5/31/2019
This project will replace the old 7!
foot AOA fence line with the new
standard height of 1 !"##% plus one
foot barbed wire at the top.
Project Status:
Schedule: Delayed
Budget: Forecast Overrun
Status Reset: 6/13/2017
(Commission Construction Auth.)
Significant Developments
Budget/Costs Incurred
5.7
6
Dollars in Millions
AOA Perimeter Fence Line Standards Compliance project will replace
approximately 9800 feet of AOA perimeter fence with 1 !"##% fence plus one
foot barbed wire on the top. About 7000 feet of the fence will be replaced with
anti!a'()* fence for areas identified by Airport Security. In addition, gate E!
105, next to the Airport Rescue and Firefighting Facility, will be replaced with
a more secure and faster gate operator to shorten response time by the Fire
Department. Sixty percent design was completed in QQ 2017 with 90% design
due in Q1 2018. The onsite construction is estimated to start in Q4 2018.
5.7
5
4
3
2
1
0.2
0
Authorized Forecasted
Costs
Incurred
Schedule
The onsite construction is estimated to start in Q4 2018. The schedule is
delayed as more time is needed for design to include the additional scope items.
Construction Contract Costs
Budget
Project cost estimate will be updated to include the added scope items to
replace additional perimeter access gates.
Change Order
Number of COs
Amount of COs
Current Quarter
0
$0
Project Total
0
$0
Dollars in Millions
1
0.8
0.6
0.4
0.2
0.0
0.0
0.0
Initial
Change
Orders
Spent
0
Photo
Risks
Coordination with the both the Transportation Security Agency and Federal
Aviation Administration for approvals of the fence design standards.
Budget increase and project schedule delay due to the added scope to replace
additional perimeter access gates.
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 55
FOURTH QUARTER REPORT, 2017
ADR K+,-. Program E/023-+,3
Project: C800846
Budget: $1,240,000
Phase: Design
Start: 9/26/2017
Schedule Completion: 12/31/2020
Install utilities to support (8) new
ADR 45678 locations. (6)
Intermediate 456787 and (2)
Introductory 4567879
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Dollars in Millions
Design work started for the kiosks.
Schedule
Project on schedule.
Budget
Project is within budget.
1.4
1.2
1
0.8
0.6
0.4
0.2
0
1.24
1.24
0.08
Authorized Forecasted
Change Order
Number of COs
Amount of COs
Current Quarter
0
$0
Project Total
0
$0
Risks
Unforeseen site conditions. Changes in site use priorities.
Budget Transfers
Amount
$0
AIRPORT
56 - Port of Seattle 4Q 2017 Report
From
To
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Checkpoint 5 W:;l Replacement
Replace the wall at Checkpoint 5
with a new door system to improve
the efficiency and customer service
as well as the aesthetic appearance
of the checkpoint entry.
Project: C800858
Budget: $1,200,000
Phase: Construction
Start: 8/7/2016
Schedule Completion: 3/31/2018
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Remaining scope to provide emergency egress doors and signage approved by
the Building Department. Construction underway in January 2018.
Schedule
The emergency egress doors required additional review. The project is now
anticipated to be complete in Q1 2018.
Budget
Dollars in Millions
Budget/Costs Incurred
Significant Developments
1.4
1.2
1
0.8
0.6
0.4
0.2
0
1.2
0.8
0.6
Authorized Forecasted
Within budget.
Change Order
Number of COs
Amount of COs
Current Quarter
0
$0.00
Project Total
0
$0.00
Costs
Incurred
Construction Costs
Not Applicable
Photos
Risks
Security checkpoint operations can impact project construction activities.
Budget Transfers
Amount
$0
From
<=>
To
<=>
AIRPORT
Port of Seattle 4Q 2017 Report - 57
FOURTH QUARTER REPORT, 2017
Terminal Security Enhancements (TSE)
Project: C800862
Budget: $12,941,000
Phase: Design
Start: 10/8/2017
Schedule Completion: 6/30/2019
The project includes shatter proofing
the windows XYZ[\] I^ and security and
accessibility improvements XYZ[\] __^
for the Main Terminal and Sky bridge
entrances.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 10/`bc2017
(Commission Construction Auth.Phase I)
Ninety percent design plans for Phase I were submitted for review. Completed
project definition for Phase II and received approval to incorporate accessibility
improvements into project.
Schedule
Project on schedule. Upcoming Phase II milestone for Commission
Authorization to begin design in Q1 2018.
Dollars in Millions
Budget/Costs Incurred
Significant Developments
12.9
$14
$12
$10
$8
$6
$4
$2
$0
6.3
0.1
Authorized Forecasted
Budget
Project is within budget. The budget for Phase II was increased to address
addition of accessibility improvements.
Construction Contract Costs
Current Quarter
0
$0
Project Total
0
$0
Risks
Dollars in Millions
$15
Change Order
Number of COs
Amount of COs
Costs
Incurred
$10
$5
0.0
0.0
0.0
Initial
Change
Orders
Spent
$0
Phase I: RMM in Glazing of Windows
Phase II: Design of security and access improvement adversely impact curbside
operation along the Departures drive.
Phase I ?@BCDFI PJLIM II SMORT@UV
Budget Transfers
Amount
$0
Cost of Construction Growth
N/A
AIRPORT
58 - Port of Seattle 4Q 2017 Report
Photo
From
To
FOURTH QUARTER REPORT, 2017
Concourse B Gate Reconfiguration
Project: C800873
Budget: $9,900,000
Phase: Closeout
Start: 1/16/2017
Schedule Completion: 5/26/2017
Tenant reimbursement project by
Delta Air hijkl to add two new
gates and reconfigure four others at
Concourse B.
(Commission Construction Auth.)
Budget/Costs Incurred
The project is complete and is in closeout. Record drawings and Ode manuals
have been received and approved.
Schedule
Scope of work is complete and the project is currently in closeout.
Budget
Reimbursement request fg has been received and is currently under review.
Delta is reviewing a cost issue with a project supplier.
Change Order
Current Quarter
0
$0
Project Total
0
$0
From
To
12
Dollars in Millions
Significant Developments
Number of COs
Amount of COs
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: N/A
9.9
9.5
10
7.2
8
6
4
2
0
Authorized Forecasted
Costs
Incurred
Construction Contract Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
Amount
$0
AIRPORT
Port of Seattle 4Q 2017 Report - 59
FOURTH QUARTER REPORT, 2017
mnoqrtuu Securitt Screening
Project: C800880
Budget: $2,950,000
Phase: Construction
Start: 7/3/2016
Schedule Completion: 7/31/2018
Add security screening checkpoints
for employees entering the secure
areas of the airport.
(Commission Construction Auth.)
Both the south and central screening rooms are operational. Received additional
authorization in fourth quarter to design and construct a new Baggage Service
Office for Alaska Airlines to provide space to then construct the North
Employee Security Screening room. Both are currently in design.
Schedule
Project has fallen behind schedule due to design developments uncovered
during design.
Budget
Change Order
Current Quarter
$0
$0
Project Total
$0
$0
From
To
Risks
None identified at this time.
Budget Transfers
AIRPORT
60 - Port of Seattle 4Q 2017 Report
3.5
3
2.5
2
1.5
1
0.5
0
3.0
3.0
0.8
Authorized Forecasted
Construction Costs
Not Applicable
Project is within the authorized CIP budget.
Amount
$0
Dollars in Millions
Budget/Costs Incurred
Significant Developments
Number of COs
Amount of COs
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 11/28/2017
Photos
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Central Terminal Enhancements
Project: C800886
Budget: $4,800,000
Phase: Construction
Start: 8/8/2017
Schedule Completion: 7/31/2021
Provide new passenger charging
Project Status:
station counters, furniture, music
Schedule: Delayed
Budget: On or Under
performance area, waste receptacles
Status Reset: 8/8/2017
and electrical floor outlets in the
(Commission Construction Auth.)
Central Terminal
Budget/Costs Incurred
Significant Developments
The 30% design phase was completed.
4.8
4.8
Schedule
In order to align with other project work in the Central Terminal and provide
good customer service, this project schedule has been delayed. Construction
and furniture installation will be completed in phases that are coordinated with
the timing of the other construction in the Central Terminal and the phased
opening of tenant restaurant spaces.
Dollars in Millions
5
4
3
2
1
0.1
0
Authorized Forecasted
Costs
Incurred
Budget
Project expenditures are proceeding in accordance with budget.
Construction Contract Costs
Not Applicable
Change Order
Number of COs
Amount of COs
Current Quarter
0
$0
Project Total
0
$0
From
To
Risks
None at this time
Budget Transfers
Amount
$0
AIRPORT
Port of Seattle 4Q 2017 Report - 61
FOURTH QUARTER REPORT, 2017
Airport Signage Phase 1
Project: C800898
Budget: $8,000,000
Phase: Design
Start: 4/4/2016
Schedule Completion: 3/30/2020
Provide shortvxyz{ improvements
to airport signage and wayfinding
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Design work was started for early work to install dynamic signage in ticketing
lobby. Initial recommendations from the wayfinding study forthcoming.
10.000
Dollars in Millions
Significant Developments
8.00
8.000
Schedule
6.000
On schedule
4.000
0.65
2.000
Budget
0.02
0.000
On budget
Authorized
Forecasted
Change Order
Number of COs
Amount of COs
Current Quarter
0
$0
Project Total
0
$0
From
To
Risks
None at this time
Budget Transfers
Amount
$0
AIRPORT
62 - Port of Seattle 4Q 2017 Report
Construction Costs
None at this time
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Concourse B I|} ~
Project: C800913
Budget: $1,750,000
Phase: Design
Start: 10/6/2013
Schedule Completion: 12/31/2018
Install an I flush gutter to
interce ential contaminated
runoff from aircraft rations on
gates B- through B-9.
Project Status:
Schedule: or Ahead
Budget: On or Under
Status Reset: 10/ ¡
(Commission Construction Auth.)
Budget/Costs Incurred
The work project was moved from this CIP to CIP C This is the final
re for this CIP.
Schedule
Transferred to C
Budget
Project Total
0
0
Coordination Delta for gate closures on Concourse B continue
through construction.
Budget Transfers
1
0.5
0.04
From
C800913
Costs
Incurred
Construction Contract Costs
1
Dollars in Millions
Current Quarter
0
0
Risks
Amount
1.5
Authorized Forecasted
Change Order
Amount of COs
1.75
0
Transferred to C
of COs
1.75
2
Dollars in Millions
Significant Developments
0.8
0.6
0.4
0.2
0.0
0.0
0.0
Initial
Change
Orders
Spent
0
To
C800914
AIRPORT
Port of Seattle 4Q 2017 Report - 63
FOURTH QUARTER REPORT, 2017
Taxiways A/B/L/Q Improvements
Project: C800914
Budget: $47,500,000.00
Phase: Design
Start: 10/11/2016
Schedule Completion: 12/31/2018
Ta¼¥¬¤½¾¿ A/B Reconfiguration of Project Status:
transition and S£ÀÁ routes,
Schedule: Ä¥®¥¦ or Ahead
Ta¼¥¬¤½ à Relocation and Ta¼¥¬¤½
Budget: On or Under
Q partial hot spot mitigation.
Status Reset: 11/©ÅÆ2017
(Commission Const Auth.)
Budget/Costs Incurred
Project is in the final design phase. Coordinating with FAA on review
comments and modifications to standards for construction documents. Review
of Engineers Design Report, Construction Safety Phasing Plan and final
quantities for construction estimates.
Schedule
Project is on Schedule ¢ Commission authorization - November 14, 2017;
Advertisement ¢ December 11, 2017. £¤¥¦ construction in spring and fall of
47.5
50
Dollars in Millions
Significant Developments
47.5
40
30
20
10
1.8
0
Authorized Forecasted
§¨©ª<<
Construction Contract Costs
Budget
Budget is currently under revie¬ ¬¥® final scope and construction quantities.
Amount of COs
Current Quarter
0
µ0
Project Total
0
µ0
1
Dollars in Millions
Change Order
¯°±²³´ of COs
Costs
Incurred
0.8
0.6
0.4
0.2
0.0
0.0
0.0
Initial
Change
Orders
Spent
0
Risks
Significant coordination bet¬³³¦ ¶´·¸ects and ¬¥® other programs,
coordination ¬¥® FAA, Operations and Airlines regarding required ´°¦¬ay
closure and maintaining schedule regarding FAA grant funding.
Budget Transfers
Amount
µ22,000,000
µ©¹º>>¨¹¨¨¨
AIRPORT
64 - Port of Seattle 4Q 2017 Report
From
C800483
C800913
To
C800914
C800914
Photo
FOURTH QUARTER REPORT, 2017
Sound Transit ÇÈÉkÊÈË & Bridge Improvements
Project: C800917
Budget: $3,500,000
Phase: Construction
Start: 11/11/2016
Schedule Completion: 8/31/2017
Interim improvements to the
walkway between the Airport light
rail station and the Main Terminal
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 11/22/2016
(Commission Construction Auth.)
Phase I improvements (painting, wind screens, directional signage, lighting
alignment, floor coating and graphics) are complete. Courtesy cart service
continues. Under Phase II planning effort evaluating long-term improvements
(moving walkways, full enclosure), identified potential building code and
structural concerns. These efforts are being postponed at this time. This is the
final report.
Schedule
Dollars in Millions
Budget/Costs Incurred
Significant Developments
3.5
4
3.5
3
2.5
2
1.5
1
0.5
0
1.4
Authorized Forecasted
In Phase I substantial completion reached during Q3 2017. Phase II was also
completed during Q4 2017.
1.2
Costs
Incurred
Construction Contract Costs
Not applicable
Budget
Interim improvements were completed within authorized budget.
Photo
Change Order
Number of COs
Amount of COs
Current Quarter
N/A
N/A
Project Total
N/A
N/A
From
To
Risks
None
Budget Transfers
Amount
$0
Completed northern wind screen,
signage, graphics and lighting
AIRPORT
Port of Seattle 4Q 2017 Report - 65
FOURTH QUARTER REPORT, 2017
Lora Lake Apt MTCA Remediation
Project: 104395, 104396
Budget: $24,300,000
Phase: Construction
Start: 9/26/2010
Schedule Completion: 12/31/2018
Remediation of contaminated soils
at Lora Lake Apartments site; and
Capping and filling of the Lora
Lake establishing wetland area
adjoining Miller Creek.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 9/13/2016
(Commission Construction Auth.)
Budget/Costs Incurred
Apartment site is complete. Lake site has been winterized and work will
resume June/July of 2018.
Schedule
Phase One is on track and has been completed. Phase two will resume summer
of 2018.
30
Dollars in Millions
Significant Developments
24.3
21.4
25
20
15
10.8
10
5
0
Budget
Authorized Forecasted
Project is within budget.
Construction Costs
Current Quarter
Project Total
Number of COs
1
6
Amount of COs
$60,000
$135,000
Justification for COs: State Route 518 Slope Side Repair.
Risks
Monitoring of lake fill settlement and water flow over winter months.
10
Dollars in Millions
Change Order
AIRPORT
66 - Port of Seattle 4Q 2017 Report
From
To
8.9
6.8
8
6
4
2
0.1
0
Initial Change
Orders
Budget Transfers
Amount
$0
Costs
Incurred
Photo
Spent
FOURTH QUARTER REPORT, 2017
Flight Corridor Safety Program Ì Phase 1 Port PropertÍ
Project: ö÷÷øøù
Budget: $5,806,000
Phase: Construction
Start: 5/31/2015
Schedule Completion: 12/31/2017
Removal of obstructions to
navigable airspace on Port of
Seattle property at Seattle-Tacoma
International Airport, including
eÎðÐÓßÒúÐ replanting and
revegetating on-site.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 11/Õåû2017
(Commission Construction Auth.)
All obstructions on Port property have been removed. Received Commission
Authorization on November 14, 2017 to increase the project budget in support
of a new major works construction contract to complete invasive species
removal and revegetation of sites P4 and P5 on Port property where trees have
previously been removed.
Schedule
Dollars in Millions
Budget/Costs Incurred
Significant Developments
7
6
5
4
3
2
1
0
5.8
5.8
3.0
Budget
Additional éçæêÖÖæÖÖÖ budget ÞÚß approved to complete the Phase 1 ÞàÜáâ
Dollars in Millions
Authorized Forecasted
Phase 1 construction was initially delayed due to the Contractor's bid eÎÏÐÐÑÒÓÔ
ÕÖ× of the Engineer's estimateØ this required additional Commission action and
delayed Phase 1 construction. The Commission also requested more public
engagement. Phase 1 construction began on ÙÚÓÛÚÜÝ 17, 2017 and is on-going. Construction Costs
Subsequent to the initial delay, additional funding authorization ÞÚß required to
2
1.7
complete the invasive species removal and revegetation ÞàÜáâ This ÞàÜá ÞÒãã
1.5
occur in a neÞ maäàÜ ÞàÜáß contract in Quarter åæ çÖÕèâ
Costs
Incurred
1.9
0.9
1
0.5
0
Change Order
ëÛìíÐÜ of COs
Initial
Current Quarter
å
Project Total
12
Amount of COs
éêîîæîÕêâåï
éèïêæåïïâçÕ
ÙÛßðÒñÒÏÚðÒàÓ for COs: 1) Removal of unidentified containers and construction
debrisØ 2) P-å Redesign Deduction and AdditionsØ îò óÚðÐÜÒÓÔ Additional Costs
and Reconciliation of COôïØ åò P-õ Redesign Additions.
Change
Orders
Spent
Photo
Risks
Added scope and an additional contract for vegetation management and
replanting could result in additional costs and/or schedule delays.
Budget Transfers
Amount
é0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 67
FOURTH QUARTER REPORT, 2017
North East Redevelopment Area Program
This is an FAA funded p ect w Project Status:
participation from the City of
Schedule: W or Ahead
Budget: On or Under
Burien but led by Port. The p ect
is to redevelop the Area north of the Status Reset: 10/ 12þ 1
(Commission Construction Auth.)
airport in the City of Burien.
Significant Developments
City of Burien received Transportation Research Board grant to fund
construction of the proposed improvements of Project Segment F. Design
consultant agreement was amended to accommodate designs for all project
segments. Eight design packages are being developed for the remaining Project
segments.
Schedule
Project is currently on schedule.
Budget/Costs Incurred
$6
Dollars in Millions
Project: U00239
Budget: $5,000,000
Phase: Design
Start: 8/16/2015
Schedule Completion: 8/14/2018
5.0
5.0
$5
$4
$3
1.2
$2
$1
$Authorized Forecasted
Budget
Project is within budget. The project is funded by $3.8 million dollar FAA
Grant and üýþÿÿ participation from the City of Burien and ü$ýÿÿby the Port.
Construction Costs
N Design Only
Change Order
Photo
N of COs
Amount of COs
Current Quarter
N
N
Project Total
N
N
Risks
M design resources of the consultant so that all deliverables are complete
prior to end of grant period August 2þ
Budget Transfers
Amount
ü0
AIRPORT
68 - Port of Seattle 4Q 2017 Report
From
To
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Flight Corridor Safety Program Phase 2
and Phase 3
Project: U00356
Budget: $2,605,000
Phase: Design
Start: 1/8/2017
Schedule Completion: 12/31/2019
Multi-year program to manage
obstructions consisting of trees and
other vegetation off Port property
around Seattle Tacoma
International Airport, and
replanting lower-height vegetation.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 2/28/2017
(Commission Design Auth.)
Budget/Costs Incurred
Significant Developments
Schedule
Overall project has been delayed due to Commission request for more public
engagement during Phase 1, which in turn delayed Phase 2.
Budget
8
7
6
5
4
3
2
1
0
7.2
2.6
0.4
Authorized Forecasted
Project is currently within budget.
Change Order
Number of Cos/
Amount of COs
Dollars in Millions
Early planning, design and environmental work on-going.
Current Quarter
0
$0
Project Total
0
$0
Costs
Incurred
Construction Contract Costs
Not Applicable
Risks
Entering into agreements with other agencies and/or property owners may cause
project delays.
Budget Transfers
Amount
$0
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 69
FOURTH QUARTER REPORT, 2017
Automated Passport Control (APC) K Phase 3
Project: U
Budget: $1,400,000
Phase: Construction
Start: 2/7/2017
Schedule Completion: 2/28/2018
Install 12 additional APC
and 8 Document V !"#%
Officer podiums.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: &'(
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Schedule
Project delays were due to the need for additional layout reviews and contractor
staffing issues.
Budget
Change Order
Current Quarter
0
$0
Project Total
0
$0
Risks
No remaining significant risks.
Budget Transfers
Amount
$0
AIRPORT
70 - Port of Seattle 4Q 2017 Report
1.6
1.4
1.2
1
0.8
0.6
0.4
0.2
0
1.4
0.9
0.7
Authorized Forecasted
Project is on budget.
Number of COs
Amount of COs
Dollars in Millions
Additional required signs have delayed overall completion to Q1 2018.
From
To
Costs
Incurred
Construction Contract Costs
Not Applicable
FOURTH QUARTER REPORT, 2017
H)*+,)-. Schools /0)3. Insulation
Project: C200007
Budget: ^_`_abcba```
Phase: Construction
Start: 3/23/1999
Schedule Completion: 11/30/2021
Highline School Insulation Agreement
C;9 intended to provide funding for
sound insulation for 1d schools that
are impacted by aircraft noise from
Sea-Tac Airport
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: J\]
(Commission Construction Auth.)
Budget/Costs Incurred
Port funds authorized for availability when the FAA, the State of Washington,
and the Highline School District (HSD) provide matching funds. Currently
working with the FAA and State 4 Federal L5679:;<=>9 to provide a mechanism
for release of federal Airport Improvement Program (AIP) grant funding for
this ?>=@ect. The Highline School District passed a bond for the construction of
Des A=7B59 Elementary School and Highline High School. Construction at Des
A=7B59 Elementary C7:: commence in Q2 DEFGI Construction at Highline High
Scho0l is scheduled to commence in 2019. J=795 testing at these schools C;9
completed by the Port in February 2017.
Schedule
If the FAA is provided a means of funding through federal legislation, then
funding for Des A=7B59 Elementary School C=O:P be required in the third
quarter of DEFGQ and Highline High School in the first quarter of 2019.
120
Dollars in Millions
Significant Developments
102.1
101.8
100
80
63.4
60
40
20
0
Authorized Forecasted
Costs
Incurred
Construction Costs
J=< Applicable
Budget
The ?>=@ect forecast is C7 of COs
Amount of Cos
YO9<7Z7[;<7=B for COs: J\]
Current Quarter
0
XE
Project Total
0
XE
Risks
The current risr is the availability of FAA AIP funding.
Budget Transfers
Amount
XE
From
To
AIRPORT
Port of Seattle 4Q 2017 Report - 71
FOURTH QUARTER REPORT, 2017
Tenant Reimbursement
Alloh| for the Port to reimburse
tenants for costs that are normally a
landlord responsibility, such as
upgrading currently unleasable space
to a leasable condition, or correcting
code deficiencies hix a tenant
encounters them on a tenant
construction onect.
Project: C800154
Budget: $4,709,577
Phase: Construction
Start: 8/14/2007
Schedule Completion: TBD
Schedule
3
2.8
2.5
2
1
Authorized Forecasted
Budget
Additional Authorization hjll be sought as additional Tenant Reimbursement
mnoq is approved.
Change Order
Current Quarter
0
yz
Project Total
0
yz
From
To
Risks
snx identified at this time
Budget Transfers
72 - Port of Seattle 4Q 2017 Report
4
0
Schedules vary to meet the tenant's needs.
AIRPORT
4.7
5
Dollars in Millions
During Q4, tenant reimbursements were completed for code upgrades
completed by Delta Air Lines when they built out their offices on the ramp
level of Concourse B and the south Mezzanine in the Main Terminal, as well as
a sprinkler system upgrade completed in the hangar building efg hijki is a Port
asset due to end of lease reversion.
Amount
yz
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
stuvxo of COs
Amount of Cos
{t|}j~jk}jn for COs: s
Project Status:
Schedule: mj}ij or Ahead
Budget: On or Under
Status Reset: s
Construction Costs
sn} Applicable
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Shilshole Bay Marina Paving
Project: C800355
Budget: $2,000,000
Phase: Design
Start: 1/1/2016
Schedule Completion: 12/31/2018
Repave areas of Shilshole Bay
Project Status:
Marina not rehabilitated in the 2004 Schedule: Within or Ahead
Budget: On or Under
major capital redevelopment. Full
Status Reset: N/A
depth replacement in some failed
(Sponsor Design Auth.)
areas and extensive pavement
grinding and overlay.
Budget/Costs Incurred
Ninety percent design complete. Permits submitted with Seattle Department of
Construction Inspections (SDCI)
Schedule
to be performed under a single construction contract SB Tenant
Service Buildings (C800356). Target paving schedule is Q3 2018.
2.5
Dollars in Millions
Significant Developments
2.00
1.87
2
1.5
1
0.5
0.17
0
Budget
Authorized Forecasted
Costs
Incurred
Project is within the approved budget.
Construction Costs
Number of COs
Amount of Cos
Justification for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Risks
Work tied with Restroom schedule. Phasing and coordination will be critical
on active marina parking areas.
1
Dollars in Millions
Change Order
0.8
0.6
0.4
0.2
0.0
0.0
0.0
Initial
Change
Orders
Spent
0
Budget Transfers
Amount
$0
From
To
MARITIME
Port of Seattle 4Q 2017 Report - 73
FOURTH QUARTER REPORT, 2017
Shilshole Tenant Service Buildings
Project: C800356
Budget: $10,100,000
Phase: Design
Start: 1/6/2015
Schedule Completion: 12/31/2018
Replacement/rehabilitation of five
restrooms and laundry facilities at
Shilshole Bay ® by ¢ 2017
for ¡¯¬¨¯®.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 11/¯°¥2017
(Commission Construction Auth.)
Budget/Costs Incurred
Ninety percent design complete. Permits submitted with Seattle Department of
Construction Inspections (SDCI).
Schedule
The overall schedule tightened due to additional design effort to evaluate
and perform preliminary design on the second floor option. Current target is to
have the ne facilities to be online by mid-2019.
12
Dollars in Millions
Significant Developments
10.10
9.52
10
8
6
4
1.20
2
0
Authorized Forecasted
Budget
Pro is the approved budget.
Construction Costs
¤ at this time
Change Order
of COs
Amount of Cos
¢£¤ for COs: ¥¦
Current Quarter
0
¡0
Project Total
0
¡0
Risks
Schedule and phasing the ¤ § in an active site continue to be the primary
ris§¨ Construction costs in Seattle continue to be increasing and volatile
may lead to higher than e©ª<< bids.
Budget Transfers
Amount
¡¬
MARITIM
74 - Port of Seattle 4Q 2017 Report
From
To
Photo
Costs
Incurred
FOURTH QUARTER REPORT, 2017
FT Redevelopment Phase I
Project: C800525
Budget: $4,300,000
Phase: Design
Start: 12/1/2009
Schedule Completion: 12/31/2019
Demolition of net sheds Á Â Ã and
the C-12 BanÄ BuildingÅ
construction of 2 light industrial
buildings, refurbishment of Ship
Supply Building, and associated
site infrastructure improvements.
(Commission Construction Auth.)
Budget/Costs Incurred
Project SEPA Issued. Ninety percent design for buildings demolition
completed and construction (demolition) funding authorized. Master planning
and 15% design for new buildings completed.
Schedule
Project currently on schedule for demolition of bank and Net Sheds 7 and 8 in
2018 and start of construction of Gateway Building at Fishermen's Terminal in
2019.
Budget
5
Dollars in Millions
Significant Developments
3.99
4
3.00
3
2
0.65
1
0
Authorized Forecasted
Costs
Incurred
Construction Contract Costs
Pro±²³´ currently µ¶´·¶¸ authorized budget.
Current Quarter
0
¾0
Project Total
0
¾0
Risks
Dollars in Millions
1
Change Order
¹º>>¼²½ of COs
Amount of Cos
Project Status:
Schedule: ƶ´·¶¸ or Ahead
Budget: On or Under
Status Reset: ¹ÇÈ
0.8
0.6
0.4
0.2
0.0
0.0
0.0
Initial
Change
Orders
Spent
0
¹¿¸² at this time.
Budget Transfers
Amount
¾0
From
To
Cost of Construction Growth
¹¿¸² at this time
MARITIMÀ
Port of Seattle 4Q 2017 Report - 75
FOURTH QUARTER REPORT, 2017
FT Net Sheds 3,4,5, & 6 Roof Replacement
Project: C800526
Budget: $3,259,000
Phase: Construction
Start: 11/16/2014
Schedule Completion: 11/30/2017
Replace the existing roofing system
on all four Net sheds with new
security ladders, gutters, and fall
protection system. Install 44
crystalline solar panels at NS 5.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: 12/13/2016
(Commission Construction Auth.)
Budget/Costs Incurred
Construction is in progress for Net Sheds 3, 4 and 5. Structural frames are in
place for the solar panels and are currently active. Inclement weather and
material delays have hampered the final installation. Net Shed 6 is the last to be
completed.
Schedule
This project is a little behind schedule due to weather delays.
3.25
3.5
3
2.5
2
1.5
1
0.5
0
3.00
Dollars in Millions
Significant Developments
1.91
Authorized Forecasted
Budget
No budget issues anticipated.
Costs
Incurred
Construction Contract Costs
Change Order
2
Project Total
2
$10,000
Risks
1.6
Dollars in Millions
Current Quarter
Number of COs
0
Amount of Cos
$0
Justification for COs: None this quarter
1.4
1.5
1
0.5
0.0
0
Initial
None
Budget Transfers
Amount
$0
MARITIMÉ
76 - Port of Seattle 4Q 2017 Report
From
To
Photo
Change
Orders
Spent
FOURTH QUARTER REPORT, 2017
FT Docks 3, 4, and 5 Fixed Pier Improvements
Project: C800531
Budget: $6,400,000
Phase: Design
Start: 10/10/2017
Schedule Completion: 4/15/2019
Project Status:
îèïð the eÌØßÑØâã structural piling
Schedule: îØÑêØâ or Ahead
רÑê Fiber Reinforced Polymer
Budget: On or Under
ÏïÐÕÍÑß on DocÕß ÒñË and determine
need for replacement in ÕØâÎ of the
Status Reset: ËòóËòôÔóÓ
(Commission Construction Auth.)
eÌØßÑØâã timber fender system.
Install cathodic corrosion protection
for steel piles under DocÕ Ëé
Commission approved Design authorization on October 10, 2017. Design is
currently underway.
Schedule
The project is on schedule.
Budget
Projects U00440 (Dock ÊË FiÌÍÎ Pier), ProÏÍÐÑ U00ÒÓÔ (DocÕ ÊÖ FiÌÍÎ Pier)
רÙÙ be combined into one ProÏÍÐÑ number U00ÒÚÛ under ÜÝÞÐÕß Òà Ö and Ë
FiÌÍÎ Pier Improvementsá utilizing the eÌØßÑØâã ProÏÍÐÑ äåæçÍè U00ÒÚÛé The
combining process רÑê finance רÙÙ taÕÍ place shortly.
6.40
7
6
5
4
3
2
1
0
6.40
0.05
Authorized Forecasted
Costs
Incurred
Construction Contract Costs
Current Quarter
0
ë0
Project Total
0
ë0
Risks
Dollars in Millions
1
Change Order
äåæçÍè of COs
Amount of COs
Dollars in Millions
Budget/Costs Incurred
Significant Developments
0.8
0.6
0.4
0.2
0.0
0.0
0.0
Initial
Change
Orders
Spent
0
Permit conditions, Facility Operations, Stray voltage and Sole Source.
Budget Transfers
Amount
ëËÔì
ëÒÚËì
Photo
From
U00440
U00440
To
U00379
U00379
Cost of Construction Growth
äÞâÍ
MARITIMí
Port of Seattle 4Q 2017 Report - 77
FOURTH QUARTER REPORT, 2017
T-91 Fender Upgrades
Project: C800675
Budget: $4,100,000
Phase: Design
Start: 1/31/2016
Schedule Completion: 3/31/2018
Upgrade/replace existing timber
fender system at the South end of
Pier 91
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 8/8/2017
(Commission Construction Auth.)
Significant Developments
Budget/Costs Incurred
Favorable bids received, contract awarded to American Construction Co.
In-water work such as pile driving must be accomplished by February 15, 2018
to comply with permit fish window. Construction scheduled to start in Q1 2018,
completion by March 31, 2018.
Dollars in Millions
Schedule
5
4.10
4
2.40
3
2
1
0.21
0
Budget
Authorized Forecasted
Project is forecast under authorization.
Construction Costs
Change Order
Number of COs
Amount of Cos
Justification for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Risks
Procurement and construction schedule still tight. Long lead items such as pipe
piles tighten overall construction project and may be aggravated by material
demands of recovery efforts in other parts of the country.
Budget Transfers
Amount
$0
MARITIMõ
78 - Port of Seattle 4Q 2017 Report
Costs
Incurred
From
To
Not applicable at this time
Photo
FOURTH QUARTER REPORT, 2017
T-91 C173 Building Roof Overlay
Project: C800829
Budget: $1,561,000
Phase: Construction
Start: 9/13/2016
Scheduled Completion: 12/29/2017
Overlay the ee ÿJ standing seam
Single Ply
metal roof w J a N
PP Roof Membrane, including
Fall
dwnspouts w J a N
Protection system.
Project Status:
Schedule:
J or Ahead
Budget: On or Under
Status Reset: 1/2ö1û÷ú
(Commission Construction Auth.)
Budget/Costs Incurred
The PVC Membrane Overlay, Gutters and Fall Protection are all complete.
Substantial completion issued October 27, 2017. This will be the final report.
Schedule
Project is on schedule.
Budget
2
Dollars in Millions
Significant Developments
1.56
1.56
1.5
1.16
1
0.5
0
Project is within budget.
Authorized Forecasted
Current Quarter
Project Total
Number of COs
5
5
Amount of COs
$ö÷øùúû
üö÷øùúû
ýþÿJ J for COs: Lø materials and equipment to coat and paint the
entire length of the interior of the roof purlin at the wÿJ roof overhang
including inclement wJ delays.
Risks
Construction Contract Costs
1
Dollars in Millions
Change Order
Costs
Incurred
0.77
0.76
0.8
0.6
0.4
0.2
0.04
0
Initial
N
Budget Transfers
Amount
ü0
From
To
Change
Orders
Spent
Photo
MARITIMM
Port of Seattle 4Q 2017 Report - 79
FOURTH QUARTER REPORT, 2017
T-18 Stormwater Outfall Renewal &
Replacement
Project: C800895
Budget: $4,000,000
Phase: Design
Start: 9/26/2016
Schedule Completion: 12/31/2020
Remove and replace the 13 outfall
pipes and tides gate from the last
downstream manhole to the outlet
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 4/25/2017
(Commission Design Auth.)
Budget/B InI
The geotechnical investigation for the project has been completed and design
work for the first phase of construction is nearing completion. Permit
applications are under review by the tribes and agencies. Construction funding
request authorized in February.
Schedule
Construction is scheduled to begin on five of the 13 outfalls in the spring of
2018.
5
Dollars in Millions
Significant Developments
4.00
4.00
4
3
2
1
0.29
0
Authorized Forecasted
Costs
Incurred
Budget
BCIC BCI B
Project is within authorization
Number of COs
Amount of COs
Current Quarter
0
$0
Project Total
0
$0
Risks
Dollars in Millions
1
Change Order
0.8
0.6
0.4
0.2
0.0
0.0
0.0
Initial
Change
Orders
Spent
0
Delay in receiving in-water permits could delay any anticipated field work
Budget Transfers
Amount
$0
Cost of Construction G
N/A
MARITIM
80 - Port of Seattle 4Q 2017 Report
P
From
To
FOURTH QUARTER REPORT, 2017
T-91 Standoff Barges
Project: C800910
Budget: $1,100,000
Phase: Construction
Start: 3/17/2017
Schedule Completion: 4/15/2018
Procure five additional cruise
standoff barges to replace the
existing unifloats and complement
the existing fleet of ten purchased
in 2 !2"!# currently in use
Terminal 91
(Commission Construction Auth.)
Budget/Costs Incurred
Procurement complete and awarded to PCL. Northwest Steel Fabrication
currently assembling barges.
Schedule
Project is on schedule. Barges to be delivered Q2 2018 to be deployed for 2018
Cruise season (One season earlier than originally planned in the capital budget)
1.10
1.2
Dollars in Millions
Significant Developments
Project Status:
Schedule: W$%&$' or Ahead
Budget: On or Under
Status Reset: 9/12/2017
1.10
1
0.8
0.6
0.4
0.2
0.03
0
Budget
Authorized Forecasted
Costs
Incurred
Five barges procured under current authorization. Possibility of sufficient
budget to procure one additional barge within one year (allowed under current
contract).
Not Applicable at this time
Change Order
Photo
Number of COs
Amount of COs
Current Quarter
0
$0
Construction Contract Costs
Project Total
0
$0
Risks
Tight fabrication may mean barges are delivered after first cruise call. Existing
barge fleet can accommodate this, not disruption of cruise anticipated.
Budget Transfers
Amount
$0
From
To
MARITIM
Port of Seattle 4Q 2017 Report - 81
FOURTH QUARTER REPORT, 2017
Salmon Bay Marina Uplands Improvements
Project: C800993- U00471
Budget: $2,000,000
Phase: Planning
Start: 12/6/2017
Schedule Completion: 12/31/2020
uplands flef industrial
building and associated site
improvements.
59>
Project Status:
Schedule: ./03/4 or Ahead
Budget: On or Under
Status Reset: 12/?@()*A
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Planning and design to start in 2018 once Miller Hull team is under contract.
Dollars in Millions
Schedule
Planning and design: ()*+,()*Construction: 2019-2020
Budget
of COs
Amount of COs
56789:
1
0.5
0.2
Authorized Forecasted
Current Quarter
0
;0
Project Total
0
;0
Risks
at this time
Budget Transfers
Amount
;0
MARITIM=
82 - Port of Seattle 4Q 2017 Report
Costs
Incurred
Construction Contract Costs
1
0.8
0.6
0.4
0.2
0.0
0.0
0.0
Initial
Change
Orders
Spent
0
From
To
Photo
Cost of Construction Growth
5<49
2.0
1.5
budget.
Change Order
5<49
2.0
2
0
Dollars in Millions
./03/4
2.5
FOURTH QUARTER REPORT, 2017
Viaduct Construction Coordination
Project: E104324, E104535-38
Budget: $2,900,000
Phase: Implementation
Start: 1/1/2009
Schedule Completion: 12/31/2018
Participate in the design E
construction of the bored tunnel, FH
E S. portals, Holgate to KOQR St,
Central STUVXYXZQU surface streets,
E related pXZ[ects to ensure
adequate connection to port
facilities.
(Commission Construction Auth.)
Budget/Costs Incurred
Tunnel construction continued, including lid over Bertha disassembly pit. TTI
leasehold restoration completed and area returned to tenant. Month-to-month
lease continued for remaining areas, including North Pier and South Jackson
Street entry. Construction of Pier 62/63 began; Seattle City Light continued
Phase 2 of the Central Waterfront Transmission Line Relocation Project; and
construction of Colman Dock continued.
Schedule
Dollars in Millions
Significant Developments
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: F\]
3.5
3
2.5
2
1.5
1
0.5
0
2.90
1.75
1.38
Authorized Forecasted
Tunnel roadway construction is scheduled through Summer 2018. Central
Waterfront construction is expected to begin in 2019 following Viaduct
demolition. Colman Dock construction to continue through 2023. Central
Waterfront construction is expected to begin in 2019 following Viaduct
demolition.
Costs
Incurred
Construction Costs
Not Applicable
Photos
Girders over north SR99 tunnel
01.04.18
Budget
Costs were within anticipated 2017 spending.
Change Order
Number of COs
Amount of Cos
Justification for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Risks
NB SR99 off-ramp to Dexter Ave
11.15.17
Project delays due to unforeseen construction issues.
Budget Transfers
Amount
$0
From
To
MARITIMD
Port of Seattle 4Q 2017 Report - 83
FOURTH QUARTER REPORT, 2017
P66 Alaskan ^_` Street Improvements
Project: bccghi
Budget: $1,282,000
Phase: Construction
Start: 4/1/2015
Schedule Completion: 4/30/2018
Widen a segment of Alaskan Way
in the vicinity of the Bell Street
Cruise Terminal to improve traffic
flow and safety during cruise days.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 8/23/2016
(Commission Construction Auth.)
Budget/Costs Incurred
Schedule
Despite challenging field conditions and additional requirements imposed by
the railroad, staff expects the work would be completed and roadway ready for
use before the start of the 2018 cruise season.
Budget
Projecting that additional funding would be needed to complete the project.
Additional authorization request is planned for Q1 2018.
2
Dollars in Millions
Construction began in October after the completion of the 2017 cruise season
and the overall work is approximately 1/3 complete. Roadway paving is
progressing. Encountered poor soil condition which required additional
excavation and backfill materials. Burlington Northern Sante Fe imposed more
stringent flagging requirements than originally agreed and this resulted in
complete work resequencing and construction delays/additional costs.
Additional construction funding is anticipated and staff will be requesting
additional authorization in Q1 2018.
1.7
1.3
1.5
0.9
1
0.5
0
Authorized Forecasted
Costs
Incurred
Construction Contract Costs
1
Dollars in Millions
Significant Developments
0.8
0.8
0.6
0.4
0.4
0.2
0.0
0
Initial
Change Order
Number of COs
Amount of Cos
Current Quarter
0
$0
Project Total
0
$0
Risks
Differing site conditions, extra monitoring/protection of aged utility
infrastructure and mature trees, working adjacent to active railroad
tracks/roadways and changing railroad requirements have contributed to
construction delays and additional project costs. Construction is closely
monitored, and necessary adjustments are being made to minimize schedule and
cost impacts.
Budget Transfers
Amount
$0
MARITIMa
84 - Port of Seattle 4Q 2017 Report
From
To
Photo
Change
Orders
Spent
FOURTH QUARTER REPORT, 2017
T-102 jkll Roofs and jmnl oqrst Replacement
Project: C800196
Budget: uvxyzzxzzz
Phase: Construction
Start: 9/1/2014
Scheduled Completion: 10/31/2016
Replace Corporate Center building
roofs, final group (3rd phase) of
rooftop HVAC units, and all
rooftop gas piping. Assets are at the
end of their service lives.
Significant Developments
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Dollars in Millions
Construction completed on all buildings.
Schedule
Project closeout begun.
Budget
Project currently within authorized budget.
7
6
5
4
3
2
1
0
6.2
6.2
4.7
Authorized Forecasted
Change Order
Project Total
5
$36,700
Risks
No risks at this time.
Budget Transfers
Amount
$0
From
Construction Costs
Dollars in Millions
Current Quarter
Number of COs
0
Amount of COs
0
Justification for COs: None this quarter.
To
Costs
Incurred
3.5
3
2.5
2
1.5
1
0.5
0
3.32
1.66
0.00
Initial Change
Orders
Spent
ECON. DEVELOPMENT
Port of Seattle 4Q 2017 Report - 85
FOURTH QUARTER REPORT, 2017
P66 Elevator {| and {} Control
Project: C800813
Budget: $1,067,000
Phase: Construction
Start: 5/24/2016
Schedule Completion: 4/30/2018
Control Systems upgrade for
Elevator 3 and 4 at Pier 66.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
The prime contractor mobilized and began work on a different elevator on the
same contract. Anticipate full production on these elevators after the first of the
year.
1.10
1.20
0.85
1.00
Dollars in Millions
Significant Developments
0.80
0.60
Schedule
0.40
The external elevator at street level will not be back in service when cruise
season begins. Project is on schedule.
0.19
0.20
0.00
Authorized Forecasted
Budget
On budget
Construction Contract Costs
Change Order
0.6
Current Quarter
0
$0
Project Total
0
$0
Risks
Dollars in Millions
Number of COs
Amount of COs
Costs
Incurred
0.53
0.5
0.4
0.3
0.2
0.1
0.00
0.05
Change
Orders
Spent
0
None
Initial
Budget Transfers
Amount
$0
Cost of Construction ~
None
ECON. DEVELOPMENT
86 - Port of Seattle 4Q 2017 Report
From
To
FOURTH QUARTER REPORT, 2017
P66 Elevator Control S
Upgrades to the elevator controls
systems.
Project: C800813 105261
Budget: $728,000
Phase: Construction
Start: 5/24/2016
Schedule Completion: 1/2/2018
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
The majority of the modernization work is complete.
Schedule
Anticipate a short delay due to preparing for L&I inspection. The main issue is
a hoistway pressurization requirement which surfaced late in the construction.
Work is being phased with two elevators on Project 105257, which is on the
same MC contract.
0.80
0.70
0.60
0.50
0.40
0.30
0.20
0.10
0.00
0.7
0.6
Dollars in Millions
Significant Developments
0.4
Authorized Forecasted
Budget
Under budget.
Construction Contract Costs
Current Quarter
5
$77,075.00
Project Total
5
$77,075.00
Risks
Calculated available fault current for the location is higher than the rating of
new elevator gear. This elevator will pass all inspections. The design consultant
has proposed a solution, and POS Engineering is helping evaluate solution
and/or propose other solutions. The potential cost of the fault current is a risk
to the project.
Dollars in Millions
Change Order
Number of COs
Amount of COs
Costs
Incurred
0.40
0.35
0.30
0.25
0.20
0.15
0.10
0.05
0.00
0.3
0.3
0.1
Initial
Change
Orders
Spent
Budget Transfers
Amount
$0
From
To
Cost of Construction
A significant change order was approved. Contractor will now complete the
electrical scope originally slated for completion by Marine Maintenance crews.
ECON. DEVELOPMENT
Port of Seattle 4Q 2017 Report - 87
FOURTH QUARTER REPORT, 2017
P69 Solar Panel System
Project: C800888
Budget: $515,000
Phase: Construction
Start: 12/12/2017
Schedule Completion: 12/31/2018
Design and build a roof-mounted
kWh/yr photovoltaic (PV)
solar system at Pier 69 on the
sloped, metal-clad portion of the
roof.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 12/12/2017
(Commission Construction Auth.)
Budget/Costs Incurred
Preparing documents to advertise for a Building Engineering Systems contract,
and to execute an agreement with the WA Department Commerce to accept the
grant.
Schedule
On schedule
0.6
Dollars in Millions
Significant Developments
0.52
0.52
0.5
0.4
0.3
0.2
0.1
0.01
0
Budget
Authorized Forecasted
On budget
Construction Contract Costs
Current Quarter
0
$0
Project Total
0
$0
Risks
None
1
Dollars in Millions
Change Order
Number of COs
Amount of COs
Costs
Incurred
0.8
0.6
0.4
0.2
0.0
0.0
0.0
Initial
Change
Orders
Spent
0
Budget Transfers
Amount
$0
Cost of Construction Growth
None
ECON. DEVELOPMENT
88 - Port of Seattle 4Q 2017 Report
From
To
Photo
FOURTH QUARTER REPORT, 2017
P66 Interior and Exterior Modernization
Project: C800820, C800889
Budget: $2,500,000
Phase: Planning
Start: 10/11/2016
Schedule Completion: 6/30/2019
Modernize the interior and
exterior/façade of the P66 facility to
better support the needs of our
customers for the foreseeable future.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 10/11/2016
(Commission Design Auth.)
Budget/Costs Incurred
Held Executive briefing in August and reviewed design concepts and
conceptual costs. However, during the subsequent 2018 capital budget
development/project prioritization, senior leadership decided the exterior
modernization portion of the project would be delayed by 5 years. With this
new development, the project architect team has been directed to focus only on
interior modernization related scope. Interior concepts refinement continues.
3
Dollars in Millions
Significant Developments
2.5
2.5
2.5
2
1.5
1
0.3
0.5
0
Authorized Forecasted
Schedule
Budget
Budget is based on preliminary conceptual plans and will need to be validated
through additional planning/design efforts. Commission approved $2.5M for
the design development phase of both the Interior Modernization and Exterior
Modernization Projects but with Exterior Modernization project no longer in
the design scope, the cost of the design phase is expected to be reduced
accordingly. Staff expects to renegotiate design development fees in Q1 2018.
Construction Contract Costs
1
Dollars in Millions
Detailed schedule would be developed in Q1 2018 once desired conceptual
design components are better defined. Current schedule anticipates submitting
building permit package late 2018 and start construction Q4 2019 to minimize
impacts to conference center operations.
Costs
Incurred
0.8
0.6
0.4
0.2
0.0
0.0
0.0
Initial
Change
Orders
Spent
0
Change Order
Number of COs
Amount of Cos
Current Quarter
0
$0
Project Total
0
$0
Risks
Design is still in the conceptual level. LMN Architect services will help define,
refine scope, schedule and budget. Associated risks would continue to be
identified during design development.
Budget Transfers
Amount
$0
From
To
ECON. DEVELOPMENT
Port of Seattle 4Q 2017 Report - 89
FOURTH QUARTER REPORT, 2017
Street Vacations T-5 and T-18
Street ¡ related real estate
negotiations and agreements ¢
Terminal 5£ and Terminal 1¤
Significant Developments
Scope of project in ¨©ª finali<<¡¬ property agreements with asset owners in
Port-owned land at T-5 and T-1¤ Includes reports on how the Port met
Seattle Department Of Transportation (SDOT) imposed project conditions to
appro© street ¡ petition ®¯°°± for T-5£ ¯°°¤ for T-1¤²
T-1¤ Work ³ ´µ¨©©¶·
•
•
•
•
•
•
•
•
•
passed ordinance to execute key easement agreements (SPU
Master Easement£ SPU-BP easement)£
SPU-Port Master Easement signed and recorded by SPU
SPU executed SPU-Port Asset Transfer Agreement
SPU recorded BP-SPU Easement (Port as ºrd Party)
³©¡¹>>¸¼¡½ signed and returned easement with the Port for
telecommunications facility on Harbor Island (the Hut). ³¾¼ in selection
process for contractor to complete the modifications to the hut.
³¸ µ>> ded legal description of the right of way that will be ©¶ on
Harbor Island.
SDOT drafted ordinance to © streets. Plans to present to ³¸
³ ¹¡¨ in late February or early March.
³ ¡¡¹¡¬ to negotiate with Olympic Pipeline ³ ´µ¡¸ for their
easement re¿¹>>©´©¡ª (which are not part of the ³¸Àª re¿¹>>©´©¡ª for
street ¡ appro¨²
³ ´µ¨©©¶ first round of real property appraisal of OP¼ easement area.
³¸ ³ ¹¡¨
T-5 Street Á ¡ work includes:
•
Shifted efforts to T-5£ mostly working on the detailed work plans and
information gathering needed for effort. The ¼ ¡¬Â©¨¨ à ³>>©©½ O©>>¨ Ã
¼¡© will be the difficult issue to resol©
Schedule
is scheduling to © streets on Harbor Island in late Q1 Äů¤ or early
Q2 Äů¤£ depending on the legislati© calendar at ³¸ ³ ¹¡¨
³¸
Port and Olympic Pipeline in final re©Ã of easement for pipeline inside
Terminal 1¤ boundary
T-5 Street ¡ is planned for completion at end of year Äů¤
90 - Port of Seattle 4Q 2017 Report
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: ¥¦§
(Commission Construction Auth.)
Budget/Costs Incurred
Dollars in Millions
Project: C102858, C102875
Budget: $5,300,000
Phase: Implementation
Start: 6/1/2010
Schedule Completion: 2018
5.3
5.3
5.3
5.2
5.2
5.1
5.1
5.0
5.0
4.9
5.3
5.1
Authorized Forecasted
Construction Costs
¥ Applicable
Photos
Costs
Incurred
Budget
OÎÏÐÑÒÒ budget between T-1Ó and T-5 projects is good. ÔÕÖÖÒÏ to no major
expenditures is expected in the foreseeable future. Expense items that will cut
into the budget are within the T-5 side of the project and should not
significantly impact the ×ÎÏrall budget.
Change Order
Current Quarter
of
0
ØÙÚÛÏÐ
ÜÝÞ
Amount of ÜÝÞ
ß0
æÙÞÖÕçÕèÑÖÕ×é for ÜÝÞê Ø×éÏ this ëÙÑrter
Project Total
2
ßàáâãäáåãã
Risks
Ø×éÏ
Budget Transfers
Amount
From
To
ßá
ÆÇÈÉÊ
VËÉÊÌÍË
Port of Seattle 4Q 2017 Report - 91
FOURTH QUARTER REPORT, 2017
Argo ìíîï Truck Roadðíñ
Project: C800546, E
E
Budget:
Phase: Construction
Start: 3/11/2012
Schedule Completion: 4/15/2019
New Port of Seattle owned truck
roadway between East Marginal
Way and øùúùûüýù Aòóõþó South
right-of-way.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 222
(Commission Construction Auth.)
Budget/Costs Incurred
Union Pacific (UPRR) track crossing improòóôóõö÷ (POS sharing costs) on
East Marginal Way and øùúùûüýù Aòóõþó still to be completed; awaiting
finaliÿüöfùõ of construction agreements (currently in progress) between PortP
UPRRP and øföC of Seattle; and scheduling of UPRR crew. UPRR Element III
Argo Yard Automated Güöó System improòóôóõö÷ (POS to administer FMSIB
funding) construction under rebid by UPRR and SDøS permit still in reòfór
10
7.75
Dollars in Millions
Significant Developments
7.75
8
6.10
6
4
2
0
Schedule
Authorized Forecasted
UPRR railroad crossing improòóôóõö÷ anticipated to be completed in 2
UPRR Element III Argo freight yard Automated Güöó System improòóôóõö÷
now anticipated to be completed in 2019.
Construction Costs
Project is currently within the budget authoriÿóý by øùôôf÷÷fùõ on April 22P
2
Change Order
Number of ø÷
Amount of ø÷
Jþ÷öffüöfùõ for ø÷ N/A
Current Quarter
0
$0
Project Total
3
$P4
Risks
No significant known risks at this time.
Budget Transfers
Amount
$
VV
V
92 - Port of Seattle 4Q 2017 Report
From
To
Dollars in Millions
6
Budget
Costs
Incurred
5.05
4.50
5
4
3
2
1
0.41
0
Initial Change
Orders
Spent
FOURTH QUARTER REPORT, 2017
T-46 Permit Mitigation
Project: C800620:;<<<=>
Budget: $1,250,000
Phase: Design
Start: 3/26/2013
Schedule Completion: 12/20/2019
rwater public access
pedestrian pier to comply with
permit re"*@ in operation of
T-T.!
*? v
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
No change from prev reporting. to wait for Trustee approva !
AuthoriAa for construction funds will be re"# in % 2018.
Schedule
Project is delayed due to Port/Trustee NRD negotiation of the Sites &'(&)
Restoration project. Schedule to commence construction on October 2018.
1.40
1.20
1.00
0.80
0.60
0.40
0.20
0.00
1.25
1.25
Dollars in Millions
Significant Developments
0.11
Authorized Forecasted
Budget
** +
Costs
Incurred
within budget
Construction Contract Costs
Not Applicable
Change Order
Number of ,
Amount of
Current Quarter
0
-0
Project Total
0
-0
Risks
Potential risk of T-T. container operation due to permit condition out of
compliance.
Budget Transfers
Amount
-0
/0156
From
To
V756897
Port of Seattle 4Q 2017 Report - 93
FOURTH QUARTER REPORT, 2017
East Marginal WBD FHBIK Separation
Project: }~
Budget: ~~
Phase: Closeout
Start: 5/1/2006
Schedule Completion: 12/8/2017
FAST Corridor funded project;
FHWA^ State^ City with Port
commitment of jbb^gd^dmi Scope
is to construct grade separation in
cX`XYXRM of T5 and T18 to minimihL
truck traffic/rail conflicts.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: gbbbdeg
(Commission Construction Auth.)
Internal POS coordination and final preparation of documents for properties
and easements to be concLMLN to City of Seattle in conjunction with project
Memo of Agreement. Proposed OQR Boundary Adjustment for POS properties
has now been approcLN by Seattle DCI and recorded with UXYZ County. Upon
recXL[ and approc\] of properties/easements documents by SDOT^ Seattle City
OXZ_R and Seattle Public Utilities^ concLM\Y`L to be formally approcLN by City
Council and Port Commission.
Dollars in Millions
Budget/Costs Incurred
Significant Developments
56.4
56.2
56.0
55.8
55.6
55.4
55.2
55.0
56.25
56.25
55.30
Authorized Forecasted
Schedule
Now anticipate final acceptance by Seattle Department of Transportation
(SDOT) in 2018.
Construction Costs
Project is on track within the April bb^ bdeg Commission authorih\RXQYi
Change Order
Current Quarter
Number of COs
0
Amount of COs
j0
nopRXqX`\RXQY for COs: None this so\rter.
Project Total
97
je^kbb^klm
Risks
No risks at this time.
Budget Transfers
Amount
0
tuwxy
Vzxy{|z
94 - Port of Seattle 4Q 2017 Report
From
To
Dollars in Millions
25
Budget
22.0
22.0
20
15
10
5
2.0
0
Initial Change
Orders
Spent
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Terminal 5 Pile Removal
Project: U00289
Budget: $6,800,000.00
Phase: Construction
Start: 5/19/2016
Schedule Completion: 7/31/2018
Demolition of existing timber piers
and 26 and Shipway
north of the Inner Harbor ®
Demolition of existing steel sheet
pile to the existing mud line
regrade site and install rip-rap.
<< ¬
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: 6/1<<¯°
(Commission Construction Auth.)
Budget/ ¡ In¢£¤¤¥¦
Significant Developments
Schedule
Project is on schedule. Contractors punch list completion is expected by
February 2018.
Budget
Dollars in Millions
Project is in final stages of construction.
Within budgeted authori
8
7
6
5
4
3
2
1
0
6.8
5.3
3.0
Authorized Forecasted
Costs
Incurred
Change Order
Project Total
5
Risks
No risks to report at this time.
Budget Transfers
Amount
0
§
¡¤£¢¡¨§ §¡¤©¢¡
6
Dollars in Millions
Number of COs
Amount of COs
Current Quarter
5
¡
5.4
5
4
3
2.0
2
1
0.1
0
From
Initial
To
Change
Orders
Spent
Pª¡
V
Port of Seattle 4Q 2017 Report - 95
FOURTH QUARTER REPORT, 2017
ID Badge System Replacement
Project: C800162
Budget: $2,500,000
Phase: Closeout
Start: 5/1/2012
Schedule Completion: 11/30/2017
Procurement and replacement of
the Portwide ID Badge system
including softwareà hardwareà and
eÊDzº>>´¶¼Ò
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
The final phase to deploy a portal for employer self-ser±²³´ was completed in
Qµ 2017.
Schedule
Prior Report: A critical project to replace the ±´¶·¸¹ º¹¸±²ding an interface with
TSA for the badging process security checks and focus on performance
impro±´>>´¶¼½ will redirect Port and ±´¶·¸¹ resources resulting in a delay of the
final components of the ID Badge System Replacement project by an additional
fi±´ months.
2.505
2.5
2.495
2.49
2.485
2.48
2.475
2.47
2.50
2.50
Dollars in Millions
Significant Developments
2.48
Authorized Forecasted
Construction Costs
Not Applicable
Budget
On budget
Change Order
Current Quarter
Number of COs
0
Amount of Cos
¿À
ÆÇ½¼²È²³É¼²¸¶ for COs: None this ÊÇÉrter
Project Total
¾
(¿ÁÂÃÄÂÁÅ
Risks
None at this time
Budget Transfers
Amount
¿À
ËÌÍÎÌÍÏÐÑ
96 - Port of Seattle 4Q 2017 Report
From
To
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Parking System Replacement
Project: C800728
Budget: $5,500,000
Phase: Implementation
Start: 1/6/2015
Scheduled Completion: 12/30/2018
Replacement of the Airport Main
Parking System
ðñòñóô
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
New system was deployed on original schedule in QÓ 2017. Additional features
such as reducing impacts of bank outages and expansion to North Employee lot
will be deliÔÕÖÕ× in 2018.
Schedule
Additional features will be deliÔÕÖÕ× throughout 2018.
6
Dollars in Millions
Significant Developments
5.50
5.50
5
4
2.45
3
2
1
0
Authorized Forecasted
Budget
Costs
Incurred
On budget
Construction Costs
Not Applicable
Change Order
Current Quarter
Number of COs
0
Amount of Cos
Ù0
ÝÞßàáâáãäàáåæ for COs: None this çÞärter
Project Total
Ø
ÙÚØÚÛÜØÚ
Risks
No significant risks at this time.
Budget Transfers
Amount
From
To
Ùè
éêëìêëíîï
Port of Seattle 4Q 2017 Report - 97
FOURTH QUARTER REPORT, 2017
Vessel Moorage System
Project: C800729
Budget: $550,000
Phase: Implementation
Start: 1/12/2016
Schedule Completion: 12/30/2018
Implementation of a õöÿÿöv
moorage system to support marina
and terminal operations.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Contract with selected õö÷øùú was completed in Qûü implementation is in
progress.
Schedule
Project implementation was delayed due to a lack of response to original
procurement. A new procurement was adõöúýþÿöø and a õö÷øùú selected.
0.6
Dollars in Millions
Significant Developments
0.55
0.55
0.5
0.4
0.3
0.2
0.1
0.05
0
Budget
Authorized Forecasted
On budget
Change Order
Number of COs
Amount of Cos
J ÿýþþýþù÷ for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Risks
No significant risks at this time.
Budget Transfers
Amount
$
C
98 - Port of Seattle 4Q 2017 Report
From
To
Construction Costs
Not Applicable
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Project Delivery System
Project: C800747
Budget: $1,000,000
Phase: Design
Start: 12/14/2016
Schedule Completion: 12/31/2018
De#%&'(% of a project deli#%d)
system initially for construction
projects. System will replace two
legacy systems.
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
is currently in progress.
1.2
Dollars in Millions
DeD
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: N/A
Schedule
On schedule
Budget
On budget
1.00
1.00
1
0.8
0.6
0.4
0.22
0.2
0
Authorized Forecasted
Change Order
Number of COs
Amount of Cos
for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Costs
Incurred
Construction Costs
Not Applicable
Risks
No significant risks at this time
Budget Transfers
Amount
$0
From
To
!"
Port of Seattle 4Q 2017 Report - 99
FOURTH QUARTER REPORT, 2017
Data Center Operations/Business Continuity
Build out of the remote data center
to support automated backup and
recor*+,
Project: C800748
Budget: $1,200,000
Phase: Implementation
Start: 1/12/2016
Schedule Completion: 5/1/2018
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Infrastructure procurement and deployment has been completed to support
automated backup and recor*+,- The next phase to migrate applications to the
new infrastructure is in progress.
1.25
Dollars in Millions
Significant Developments
1.20
1.20
1.2
1.15
Schedule
During the design processe complexities were identified that delayed the final
deployment.
1.08
1.1
1.05
1
Authorized Forecasted
Budget
On budget
Construction Costs
Not Applicable
Change Order
Number of COs
Amount of Cos
./01232451267 for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Risks
Competing priorities from other projects may further delay project completion.
Budget Transfers
Amount
$0
89:;9:<=>
100 - Port of Seattle 4Q 2017 Report
From
To
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Port of Seattle W?@ABE? Redevelopment
Project: C800776
Budget: hijjkjjj
Phase: Implementation
Start: 8/9/2016
Schedule Completion: 3/30/2018
RedeLFZI[\FGR of the Port of
Seattle Website
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Testing is in progress for a planned Q1 2018 deployment.
0.80
0.80
Dollars in Millions
0.82
0.8
0.78
0.76
0.74
0.72
0.7
0.68
Schedule
VFGHIK deliLFKM has delayed deployment by N months.
Budget
On budget
0.72
Authorized Forecasted
Costs
Incurred
Change Order
Number of COs
Amount of Cos
OPQRSTSUXRSIG for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Construction Costs
Not Applicable
Risks
With this deployment we are moLSGm to a flexible content management system
that will facilitate decentraliYFH content deLFZI[\FGR] management] and
placement. While the benefits are significant] the learning curLF for the new
technology across the Port may re^PSKF additional time to ensure website
content is appropriately deliLFKFH at launch.
Budget Transfers
Amount
$0
From
To
_`ab`acfg
Port of Seattle 4Q 2017 Report - 101
FOURTH QUARTER REPORT, 2017
Airport Subway System Information Displays
Project: C800782
Budget: $2,920,000
Phase: Implementation
Start: 8/9/2017
Schedule Completion: 12/31/2018
Procurement and implementation of Project Status:
an upgraded informational display
Schedule: Within or Ahead
system for the Airport trains and
Budget: On or Under
Status Reset: N/A
stations.
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Dollars in Millions
Implementation is in progress.
Schedule
On schedule
Budget
On budget
3.5
3
2.5
2
1.5
1
0.5
0
2.97
2.97
2.00
Authorized Forecasted
Change Order
Number of COs
Amount of Cos
lnopqsqtupqwx for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Risks
No significant risks at this time.
Budget Transfers
Amount
yz{|{{{
}~~
102 - Port of Seattle 4Q 2017 Report
From
C800782
To
C80556
Construction Costs
Not Applicable
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Airport Data Network Switch Upgrade
Project: C800788
Budget: $2,982,000
Phase: Implementation
Start: 2/23/2016
Schedule Completion: 7/30/2018
E and software upgrade
for the network supporting Airport
Operations systems.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Failure of some of the new e re a product change that will delay
the final implementation until Q2 2018. There will be no significant budget
impact from this de
Schedule
Prior Report: System deployment was delayed due to an unexpected firewall
procurement re and opportunity. By completing a competiti
procurement during this project we are able to set a standard that will reduce
maintenance costs and maximi training benefits.
Dollars in Millions
Budget/ ¡¢¡ In£¤¥¥¦§
Significant Developments
3.5
3
2.5
2
1.5
1
0.5
0
2.98
2.98
2.02
Authorized Forecasted
Costs
Incurred
¨¡¢¥¤£¢© ¨ ¡¢¡
Not Applicable
Budget
On budget
Change Order
Number of COs
Amount of Cos
for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Risks
No significant risks at this time.
Budget Transfers
Amount
$0
From
To
Port of Seattle 4Q 2017 Report - 103
FOURTH QUARTER REPORT, 2017
Checkpoint ª<<¬t Time
Project: C800790
Budget: ÆÇÈÉÇÊÈËËË
Phase: Implementation
Start: 7/12/2016
Schedule Completion: 6/30/2018
Procure and implement an
automated system to track
moÌÍÎ͸² and estimate wait times
for checkpoints 2 through 5.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Schedule
Schedule is delayed by ® months due to competing priorities for construction
resources.
Dollars in Millions
Checkpoint 2 construction was completed in Q 2017. Construction begins for
Checkpoint and 5 in Q1 2018 and Checkpoint ® is estimated for Q2.
Budget
1.4
1.2
1
0.8
0.6
0.4
0.2
0
Change Order
Budget Transfers
104 - Port of Seattle 4Q 2017 Report
From
To
Dollars in Millions
Project Total
0
$0
Re¹º>>¼½¾ construction costs are significantly higher than originally estimated prior to
procurement of the selected system. This may re¹º>>¼½ additional funding to complete
all planned checkpoints.
¿ÀÁÂÀÁÃÄÅ
0.30
Costs
Incurred
Construction Costs
Current Quarter
0
$0
Risks
Amount
$0
1.22
Authorized Forecasted
On budget
Number of COs
Amount of Cos
¯°±²³´³µ¶²³·¸ for COs: N/A
1.22
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
0.63
0.63
0.08
Authorized Forecasted
Costs
Incurred
FOURTH QUARTER REPORT, 2017
SeaTac Smartphone App
Project: C800800
Budget: $500,000
Phase: Implementation
Start: 2/23/2016
Schedule Completion: 5/30/2018
DeÏÐÕÖ×ÑÐÒÓ of a Mobile app with
SeaTac Mapsá Retailá Diningá and
SerÏÞàÐ Optionsá and other
important customer serÏÞàÐ
features.
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Features for a first deployment of an iOS mobile app haÏÐ been completed but
improÏÐÑÐÒÓÔ on indoor turn-by-turn way-finding are in progress. Andriod
deÏÐÕÖ×ÑÐÒÓ is in progress.
Schedule
Prior Report: The team has re-eÏØÕÙØÓÐÚ solution and the Port deÏÐÕÖ×ÑÐÒÓ
team will partner with a design firm to deliÏÐÛ mobile application. . The first
phase deployment was delayed by four months and completed in QÜ 2017.
Budget
0.6
Dollars in Millions
Significant Developments
0.50
0.50
0.5
0.4
0.31
0.3
0.2
0.1
0
Authorized Forecasted
Costs
Incurred
Construction Costs
Not Applicable
On budget
Change Order
Number of COs
Amount of Cos
ÝÙÔÓÞßÞàØÓÞÖÒ for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Risks
No significant risks at this time.
Budget Transfers
Amount
$0
From
To
CORPORATE
Port of Seattle 4Q 2017 Report - 105
FOURTH QUARTER REPORT, 2017
Airport Telecommunications Capacity Increase
Project: C800827
Budget: $565,000
Phase: Closeout
Start: 2/23/2016
Schedule Completion: 11/30/2017
Increase of copper and fiber
telecommunications capacity to
meet Port and Tenant reçèéùäúäåíì
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Additional capacity completed in Qâ 2017.
Schedule
Prior Report: Procurement took longer than expected delaying the project by
seãäå (7) months.
Budget
Change Order
Current Quarter
0
$0
Project Total
0
$0
Risks
No significant risks at this time
Budget Transfers
Amount
$0
òóôõóôö÷ø
106 - Port of Seattle 4Q 2017 Report
0.57
0.57
0.5
0.4
0.28
0.3
0.2
0.1
0
Prior Report: Contractors estimate is significantly higher than the Port
budgetary estimate due to increasing local cost trends. Because capacity
constraints for copper will soon impact tenant operations and larger project
schedulesæ fiberæ for which there is no immediate needæ will be eliminated from
the scope to complete as çèéckly as possible. The project will complete fiber
conduit to minimiêä future costs for fiber expansion.
Number of COs
Amount of Cos
ëèìíéîéïðíéñå for COs: N/A
Dollars in Millions
0.6
From
To
Authorized Forecasted
Construction Costs
Not Applicable
Costs
Incurred
FOURTH QUARTER REPORT, 2017
South Loop Airport Train ûüýt Time Displaþ
Project: C800835
Budget: $
Phase: Implementation
Start: 6/19/2016
Schedule Completion: 11/30/2017
Expand the North L Subway
Wait Time Display to the South
L and Shuttle Stations
Project Status:
Schedule: Delayed
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Schedule
Competing projects affecting construction resources continue to delay completion.
Budget
On budget
Dollars in Millions
Construction is in progress for Q1 2018 completion.
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
0.58
0.58
0.40
Authorized Forecasted
Change Order
Project Total
0
$0
Construction Costs
0.32
Dollars in Millions
Number of COs
Amount of Cos
ÿJ for COs: N/A
Current Quarter
0
$0
0.31
0.31
0.3
0.28
Risks
Resource aa
completion.
from competing project may continue to delay construction
Costs
Incurred
0.26
0.26
0.24
0.22
Budget Transfers
Amount
$0
Authorized Forecasted
From
Costs
Incurred
To
C
Port of Seattle 4Q 2017 Report - 107
FOURTH QUARTER REPORT, 2017
Supplier Outreach and Procurement System
Project: C800907
Budget: $800,000
Phase: Implementation
Start: 7/11/2017
Schedule Completion: 3/31/2019
This project will p2)3%de an
integrated supplier outreach and
procurement solution that utiliu4"
34*v)2 p2)3%ded systems for
outreach with a Port-de34P)p4v
solution for procurement
management.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
DeD is currently in progress.
Dollars in Millions
1
Schedule
On schedule
Budget
0.80
0.80
0.8
0.6
0.4
0.2
0.04
0
On budget
Authorized Forecasted
Change Order
Number of COs
Amount of Cos
!"#%&%'(#%)* for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Risks
No significant risks at this time
Budget Transfers
Amount
$0
+,-.,-/01
108 - Port of Seattle 4Q 2017 Report
From
To
Construction Costs
Not Applicable
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Enterprise Network Firewall Upgrade
Project: C800908
Budget: $1,500,000
Phase: Planning
Start: 6/27/2017
Schedule Completion: 12/31/2018
Upgrade of the Enterprise Network
Firewall Software and EH69IKM>8N
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Planning and design are in progress.
Dollars in Millions
2
Schedule
On Schedule
Budget
On budget
1.50
1
0.58
0.5
0
Authorized
Forecasted Costs
Incurred
Change Order
Number of COs
Amount of Cos
56789:9;<89=> for COs: N/A
1.50
1.5
Current Quarter
0
$0
Project Total
0
$0
Construction Costs
Not Applicable
Risks
No significant risks at this time
Budget Transfers
Amount
$0
From
To
?@AB@AEFG
Port of Seattle 4Q 2017 Report - 109
FOURTH QUARTER REPORT, 2017
PeopleSoft Financials Upgrade
Project: C800909
Budget: $3,600,000
Phase: Planning
Start: 12/12/2017
Schedule Completion: 3/31/2019
Upgrade of the PortcS PeopleSoft
Financials System.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Dollars in Millions
Planning is in progress for a QQ Deployment.
Schedule
On Schedule
Budget
On budget
4
3.5
3
2.5
2
1.5
1
0.5
0
3.60
3.60
0.01
Authorized Forecasted
Change Order
Number of COs
Amount of Cos
ORSTUVUWXTUYZ for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Risks
No significant risks at this time
Budget Transfers
Amount
$0
[\]^\]_`b
110 - Port of Seattle 4Q 2017 Report
From
To
Construction Costs
Not Applicable
Costs
Incurred
FOURTH QUARTER REPORT, 2017
Rental Car Facility Fleet Tracking System
Project: C800929
Budget: $1,055,000
Phase: Design
Start: 6/27/2017
Schedule Completion: 3/31/2019
Procure a fleet tracking system and
|ih}nde next bus displays for
passengers~ }hnce paging~ wireless
access~ and music at all pick up
locations.
Project Status:
Schedule: Within or Ahead
Budget: On or Under
Status Reset: N/A
(Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
defghi has been selected and contract negotiations are in progress.
Dollars in Millions
1.2
Schedule
On Schedule
Budget
1.06
1.06
1
0.8
0.6
0.4
0.2
0.02
0
On budget
Authorized Forecasted
Costs
Incurred
Change Order
Number of COs
Amount of Cos
jklmnonqrmnhf for COs: N/A
Current Quarter
0
$0
Project Total
0
$0
Construction Costs
Not Applicable
Risks
No significant risks at this time
Budget Transfers
Amount
$0
From
To
stwxtwyz{