COMMISSION
DATE: February 20, 2018
TO: Stephen P. Metruck, Executive Director
FROM: Jeffrey Brown, Director Aviation Facilities and Capital Programs
Wayne Grotheer, Director, Aviation Project Management Group
SUBJECT: Passenger Loading Bridges Phase 2 (CIP#C800793)
Total estimated project cost:
ACTION REQUESTED
Request Commission authorization for the Executive Director to (1) prepare design and
construction bid documents for the replacement of the passenger loading bridge (PLB) at Sea-
Tac Airport Gates C11, C15, and S6 and the PLB and fixed walkway at Gates C9, C18, D11, and
D4; (2) purchase seven new PLBs and four fixed walkways; (3) use Port crews and small works
contracts. The amount of this request is $7,700,000 for a total estimated project cost of
$10,000,000.
EXECUTIVE SUMMARY
Reliable, well operating passenger loading bridges are critical to airline and airport operations.
Port staff has created a prioritized list of PLBs, whose age and condition indicate a need for
replacement or refurbishment. Nine PLB’s (and associated fixed walkways) considered to be at
highest risk for failures are scheduled for replacement under this project: Gates B10, S11, C11,
C15, S6, C9, C18, D11, and D4. Funding for the replacement of Gates S11 and B10 were
approved under prior Commission action. This request will provide the necessary funding for
the seven remaining highest risk PLBs. The airlines approved this project in 2017 through a
Majority-in-Interest vote.
Staff will return to Commission as necessary to facilitate additions to the PLB renewal and
replacement program.
JUSTIFICATION
The PLBs at Sea-Tac have high utilization compared to airports with comparable annual
enplanements. In 2015, Sea-Tac processed approximately 217,000 passengers per gate, the
highest of all peer airports and well above the national average of approximately 153,000. Any
unplanned downtime due to PLB or fixed walkway failure impacts airlines and customer service.