Item No. Date of Meeting 9a_supp Jan 30, 2018 Sea-Tac International Airport NorthSTAR Program Fourth Quarter 2017 Program and North Satellite Project Update 1 NSAT Renovation & NSTS Lobbies Project Design Completed : 4/14/17 12 to 20 contact gate positions. 160,000 sf to 428,000 sf Key elements: Infrastructure Gate Additions Clerestory river Airline services Marketplace Station lobbies Technology Seismic reinforcement North Satellite - Objective and Purpose 2 Construction Video https://www.youtube.com/watch?v=C58twvN 0tm0&feature=youtu.be Steel Construction 3 NSAT Renovation & NSTS Lobbies Accomplishments • Completed 2017 Project goals • Project on schedule and within budget • Phase 1 basement concrete is complete • Final building permit received • Resolved schedule conflicts between 2018 Taxiway project and NSAT Phase 1 opening • Completed passenger flow analysis for Concourse C & D - passenger congestion concerns • Submitted design documents (LEED application) to United States Green Building Council • Rainwater harvest tanks are installed and buried Current Work • Structural steel erection ongoing through April 2018 • Starting Phase 1 tenant improvement and Airport Dining & Retail projects coordination • Art program elements building integration/coordination underway North Satellite - Accomplishments and Current Work - Q4 2017 4 NSAT Renovation & NSTS Lobbies Risks • Impacts from scope changes, operational changes, customer service, unforeseen or unanticipated situations • Maintaining critical path of central core escalator and elevator phasing complexity with potential impacts to passenger and operational levels of service • Ability to provide adequate terminal/airside facilities (12 vs 14 gates) to minimize passenger & operational levels of service impacts during Phase 2 • Uncertainty regarding certification level, Leadership in Energy & Environmental Design (LEED) • Ability to meet Century Agenda goals for energy use and Green House Gas (GHS) emission reduction North Satellite - Current Risks Q4 2017 5 NSAT Renovation & NSTS Lobbies Metrics • Tracking well to SBE, SCS and M/WBE project goals and requirements • No operational incidences recorded this quarter • 170 change orders executed for $7.4M increasing contract value by 1.6%; none over $300K • Apprentice goals are being exceeded • Spent $6.3M (27.2%) of construction contingency with $26.3M remaining project contingency • Total project spending $19.4M Quarterly Project Metrics Q4 2017 6 North Satellite 2015 North Satellite Today North Satellite Future North Satellite - Progress 7 Phase 1 from NSAT Roof 8 Phase 1 Basement View 1/3/18 9 Phase 1 from NSAT Roof 1/3/18 10 Phase 1 Basement Completion 12/2017 11 Rainwater Harvest Tanks 12 New Steel installation progress 12/4/17 Steel and Generators 13 Escalator NS-4 Removal 14 Escalator NS-4 Replacement 15 Chilled water piping replacement progress - 30% complete 16