Template revised September 22, 2016.
COMMISSION
AGENDA MEMORANDUM
Item No.
9a
BRIEFING ITEM
Date of Meeting
January 30, 2018
DATE: January 22, 2017
TO: Dave Soike, Interim Executive Director
FROM: George England, Program Leader, Aviation Project Management Group
Michael Ehl, Director, Aviation Operations
Jeffrey Brown, Director, Aviation Facilities and Capital Programs
SUBJECT: 2017 Q4 NorthSTAR Program and North Satellite Project (CIP C800556) Briefing
EXECUTIVE SUMMARY
The North Sea-Tac Airport Renovation (NorthSTAR) Program is a collaborative effort of the Port
and Alaska Airlines (AS) to improve traveler experience and customer service. The North
Satellite (NSAT) Renovation and Expansion project is the largest segment of the NorthSTAR
Program. This component project addresses the expansion of the North Satellite from 12 to 20
contact gates, modernization of the existing North Satellite facility including North Satellite and
Concourse C Satellite Transit Stations, and expansion of the baggage system to accommodate
the satellite expansion. On August 15, 2017 the Commission approved the remaining
unauthorized funds for the entire NSAT project. Construction is well underway and currently
progressing on schedule.
This presentation details the progress made over the past quarter on these projects.
1. CIP C800556 NorthSTAR NSAT Renovation & North Satellite Transit System Lobbies
This project includes the modernization of NSAT and the satellite transit system (STS) lobbies at
Concourse C and North Satellite including infrastructure and seismic reinforcement, the
expansion of the NSAT to 20 contact gates and expansion of the baggage handling system to
improve customer service, provide a balance of holdrooms, concessions and circulation space
to meet the overall program vision.
Accomplishments
FAA approved Phase 1 crane operations
Temporary Chiller operational. Chilled water pipe demolition in utilidor is finished.
Opened bids, executed contract and ordered all steel Passenger Loading Bridges
Alaska level of service/passenger flow analysis coordination (Phase 2 & Concourse C)
completed
Final Conformed document set issued Nov 21
st
COMMISSION AGENDA Briefing Item No. _9a__ Page 2 of 7
Meeting Date: January 30, 2018
Template revised September 22, 2016.
Final revised restroom design delivered to Port Dec 31
st
Submitted design documents (Leadership in Energy & Environmental Design [LEED]
application) to U. S. Green Building Council
Final schedule and pathway to obtaining timely final building permit agreed to by all
parties
Resolved schedule conflicts between 2018 Taxiway project and NSAT Phase 1 opening
Completed 400Hz generator replacement scope
Rainwater harvest tanks are installed and buried
Phase 1 basement concrete is complete
Crane to erect steel (columns and beams) mobilized and assembled on Dec 18
th
Progress
Major structural steel erection ongoing through the end of January 2018
Replacement of chilled water piping in NSAT utilidor is underway (30% complete)
Central Core 1
st
escalator (NS-4) replacement underway
Hensel Phelps (HP) assembling PLB install bid package based on completed coordination
between contract drawings and PLB procurement
Starting Phase 1 tenant improvement and Airport Dining & Retail projects coordination
Art program elements building integration/coordination underway
Seating layout (all seats powered) being incorporated into project
Initiating Phase 2 Interim Ground Board design and scoping process
Mothers room final design underway
Elevator/Escalator design modifications underway
Metrics
Budget/Planned
Utilization
to Date
Cumulative Spent Against Budget
$658.3 M
$98.3 M
Overall Schedule Progress
15%
15%
Cash flow for Reporting Period (Q4 2017)
$19.3 M
$19.1 M
Contingency Remaining
$38.5 M
$26.3 M
Small Contractor Supplier (SCS) Design
6.4%
6.2%
SBE Participation (Construction)
16.0%
13.5%
SCS Participation (Construction)
5.5%
5.2%
WMBE Participation (Construction)
3.6%
3.5%
Apprenticeship Utilization
15.0%
13.4%
1
Minority Utilization (% of apprenticeship)
15.0%
24.0%
1
Women Utilization (% of apprenticeship)
10.0%
19.4.0%
1
Preferred Entry Apprentices
1 in 5
No Data
2
COMMISSION AGENDA Briefing Item No. _9a__ Page 3 of 7
Meeting Date: January 30, 2018
Template revised September 22, 2016.
1 Represents participation for PWP #1 effort only
2 No Information available yet Too early to report
* Does not reflect pending scope/budget transfers
M = million
Construction Contract Metrics
Budget/Planned
Percent
Original Contract Sum
$453.6 M
Executed Change Orders
$7.4 M
1.6 %
Current Contract Sum
$461.0 M
Original Construction Contingency
$23.2 M
Contingency Expended/Authorized
$6.3 M
27.2 %
Remaining Construction Contingency
$16.9 M
72.8 %
Negotiated Support Services (NSS)
NSS Original Budget Value
$40.0 M
NSS Authorized Amount
$5.6 M
13.9 %
NSS Remaining Amount
$34.4 M
86.1 %
Change Orders executed over $300,000:
None this period
Risks
Ability to maintain current construction schedule impacted by further scope changes,
operational changes, customer service, unforeseen or unanticipated situations
Central Core phasing challenges Complexity of central core escalator and elevator
phasing and impacts to passenger and operational levels of service
Adequately covering within budget non-discretionary/discretionary post final design
scope changes, change orders, errors and omissions and differing site conditions during
construction
Ability to provide adequate terminal/airside facilities (12 vs 14 gates) to minimize
passenger & operational levels of service impacts during Phase 2
Uncertainty regarding certification level, Leadership in Energy & Environmental Design
(LEED)
Ability to meet Century Agenda goals for energy use and greenhouse gas (GHG) emission
reduction
Timely completion of Taxi lane A/B improvements to meet the scheduled opening of
NSAT Phase 1 for operations
COMMISSION AGENDA Briefing Item No. _9a__ Page 4 of 7
Meeting Date: January 30, 2018
Template revised September 22, 2016.
2. CIP 800544 NorthSTAR Program Management & Controls - Consolidated
3. CIP 800547 NorthSTAR Concourse C Vertical Circulation Complete
4. CIP C800555 NorthSTAR Refurbish Baggage System Complete
5. CIP C800545 NorthSTAR Main Terminal Improvement Removed
6. CIP C800554 NorthSTAR Concourse C&D Exterior Stairs - Deleted
ATTACHMENTS TO THIS BRIEFING
(1) Attachment A: Quarterly Commission Update PowerPoint
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
North Sea-Tac Airport Renovations (NorthSTAR) (CIP #C800544)
Oct 24, 2017 NorthSTAR Program status update
July 25, 2017 NorthSTAR Program status update
April 25, 2017 NorthSTAR Program status update
January 24, 2017 NorthSTAR Program status update
September 13, 2016 Request Commission authorization for the Chief Executive Officer to
(1) increase the North Satellite Renovation & North Satellite Transit Station Lobbies
(NSAT) project scope and budget; (2) increase authorization for project design; (3)
amend design service agreement with URS that exceeds 50% of the value of the original
contract; and (4) increase authorization for Preliminary Work Package #2 (PWP #2)
construction.
August 9, 2016 NorthSTAR Program Status Update
May 24, 2016 Commission authorized Chief Executive Officer to 1) increase the North
Satellite project scope and budget; 2) increase authorization for NSAT design and overall
project support; 3) amend service agreements with Jacobs Project Management
Company and AECOM; and 4) authorize the use of port crews and small works
contactors to perform work for the project.
February 23, 2016 NorthSTAR Program status update
November 24, 2015 NorthSTAR Program status update
July 14, 2015 NorthSTAR Program status update
April 28, 2015 NorthSTAR Program status update
January 27, 2015 NorthSTAR Program status update
October 28, 2014 - NorthSTAR Program status update
August 19, 2014 - NorthSTAR Program status update
May 27, 2014 NorthSTAR Program status update
January 14, 2014 NorthSTAR Program status update
September 24, 2013 NorthSTAR Program status update
June 25, 2013 NorthSTAR Program status update
COMMISSION AGENDA Briefing Item No. _9a__ Page 5 of 7
Meeting Date: January 30, 2018
Template revised September 22, 2016.
April 9, 2013 The Commission authorized the Chief Executive Officer to enter into a
project labor agreement covering the NorthSTAR program’s five major construction
projects.
March 26, 2013 NorthSTAR Program status update
June 26, 2012 The Commission received a briefing on the status of the Airline
Realignment Program and budget restructuring in association with the NorthSTAR
Program.
April 10 2012 Authorizations for the North Sea-Tac Airport Renovations program for: 1)
preliminary project funding; 2) execution of consulting contracts for design/construction
support services and project management services; and 3) use of Port crews and
consultants to conduct regulated materials management surveys and field support
services for preliminary project planning tasks.
North Satellite Renovation & North Satellite Transit Station Lobbies (CIP #C800556)
August 15, 2017 The Commission authorized
Increase the authorized budget by $107,000,000 capital and $500,000 expense and
authorize the remaining $261,547,392 capital and $8,800,000 expense, amending the
Hensel Phelps (HP) contract by $161,563,526 for the final MACC to complete the
project in Q3 2021. Authorize execution of all pending and future change orders to
the HP contract within the authorized budget and project scope to avoid potential
delays. Authorize Port crews to support NSAT construction and authorize Port staff to
enter into a TRA with AS for the reimbursement of AS and Port responsible design
efforts and improvements.
June 27, 2017 The Commission authorized four NSAT related items:
increase project authorization for the North Satellite Renovation & North Satellite
Transit Station Lobbies Project by $200,000,000; execute Preliminary Work
Amendment #3 (PWA #3) with Hensel Phelps (HP) for up to $200,000,000; authorize
Port staff to execute all change orders to the HP contract within authorized budget
and project scope without returning for additional Commission authorization; and
authorize Port Construction Services (PCS) to execute small works contracts and use
Port crews to support NSAT construction
September 13, 2016 The Commission authorized four NSAT related items:
the increase of project scope and budget (capital) by $7,000,000 for the revised third
floor layout to better accommodate the signature restaurant, provide 3,000 additional
square feet of future airport related leasable space, and increase AS premium traveler
lounge as requested by 4,850 square feet.
Increase authorization by $1,000,000 for project design.
Amend design service agreements with AECOM that exceed 50% value of the original
contract.
Increase authorization by $30,000,000 to accommodate Preliminary Work Package #2
construction.
May 24, 2016 - The Commission authorized four NSAT related items:
Increase of project scope and budget (capital and expense) by $121,219,098 for 30% &
60% design scope additions and risk contingencies
COMMISSION AGENDA Briefing Item No. _9a__ Page 6 of 7
Meeting Date: January 30, 2018
Template revised September 22, 2016.
Increased authorization of $11,000,000 for continued NorthSTAR Program/Project
Management services and NSAT design and overall project support.
Amend service agreements with Jacobs Project Management Co. and AECOM.
Authorize the use of port crews and small works contractors.
December 8, 2015 The Commission authorized $98,100,000 for the following:
Additional Pre-Construction services ($1,200,000)
Construction auditing services
Preliminary Construction work
March 24, 2015 The Commission authorized three NSAT related items:
Expand the baggage handling system increasing the project scope for $14,400,000 and
$1,954,000 to complete the design.
Entering into a developer agreement with Puget Sound Energy and $200,000 in
reimbursement for the design and construction of underground gas infrastructure.
$5,300,000 to Prepare four locations to accommodate temporary passenger loading
bridges, to construct temporary construction offices; To complete construction of a
Satellite Transit System (STS) North loop Dynamic Display system; $600,000 in expense
funds for regulated materials management for AS’s tenant improvement project; and
Approval to use Port crew labor and small works contractors to complete early project
work.
August 5, 2014 The Commission authorized expansion of the NSAT, $191,323,143 budget
increase, $15,717,800 to complete the design, execute amendments to existing
consulting contracts; execute future consulting contracts and use of and to advertise for
General Contractor/Construction Manager (GC/CM) alternative public works contractor.
July 22, 2014 - NSAT Expansion Briefing
April 22, 2014 Seattle-Tacoma International Airport Capital Program - Briefing
January 14, 2014 NSAT expansion briefing.
May 28, 2013, Commission authorized the execution of separate service agreements for
Construction Management Services and Commissioning Services, of approximate values
of $10 million and $1.5 million.
December 11, 2012 The Commission was briefed on the Vertical Conveyance
Modernization Project Aero Phases 1 and 2 and the possibility of adding the specified
elevators and escalators to the NorthSTAR program.
July 24, 2012 - Commission authorized $32,000,000 for the design of the NorthSTAR NSAT
Renovation and NSTS Lobbies project.
April 10, 2012 - The Commission authorized the execution of consultant contracts for
design and construction support services; program management services; and the
completion of site surveys for regulated materials management, for $1,200,000.
NorthSTAR Concourse C Vertical Circulation Project (CIP #C800547)
October 22, 2013 Commission authorized $16,145,000 for advertising for bids, executing
a major construction contract, executing a tenant reimbursement agreement with AS,
using Port crews to provide construction services for the Concourse C Vertical
Circulation.
COMMISSION AGENDA Briefing Item No. _9a__ Page 7 of 7
Meeting Date: January 30, 2018
Template revised September 22, 2016.
November 6, 2012 Commission authorized the design for the 1:20 sloped walkways and
elevator(s) at Gates C2, C10-12, and C14 on Concourse C.
NorthSTAR North Main Terminal Improvements Project (CIP #C800545)
December 3, 2013 Commission authorized $1,500,000 for preliminary engineering up to
30% design.
North Satellite Refurbish Baggage System Project (CIP#C800555)
September 24, 2013 The Commission authorized staff to: (1) advertise, award, and
execute a major public works contract for the construction of the North Satellite
Refurbish Baggage System Project; and (2) authorize the use of Port crews.
July 12, 2013 The Commission was notified of 1 added scope item and 2 scope items
moved into the scope previously identified as suggested scope.
November 6, 2012 The Commission authorized staff to prepare design documents and
use Port crews to support site investigation needed to develop the contract documents,
for $3,760,000.