COMMISSION
AGENDA MEMORANDUM
Item No.
6e
ACTION ITEM
Date of Meeting
January 30, 2018
DATE: January 22, 2017
TO: Dave Soike, Interim Executive Director
FROM: Wendy Reiter, Director Aviation Security
Wayne Grotheer, Director Aviation Project Management
SUBJECT: Airport Terminal Safety and Security Enhancements (CIP #C800862)
Amount of this request:
$1,481,000
Total estimated project cost:
$12,941,000
ACTION REQUESTED
Request Commission authorizations for the Executive Director to (1) proceed with the design
and preparation of contract bid documents for Phase II of the Airport Terminal Safety and
Security Enhancements (TSE) project for $1,481,000 for a revised total project authorization of
$7,789,000 for both phases.
EXECUTIVE SUMMARY
Phase II will install: 1) additional security and safety features in the Main Terminal and Parking
Garage; and 2) access ramps along both curbsides to meet current Americans with Disabilities
Act (ADA) standards. An existing Architect Services Indefinite Delivery/ Indefinite Quantity
(IDIQ) service agreement will be utilized to direct the design services. Staff will return later in
2018 for authorization to advertise, award and execute the construction contract for Phase II.
Phase I of the TSE project was previously authorized by the Commission on October 24, 2017.
JUSTIFICATION
Proceeding with Phase II of the TSE program will continue to keep the occupants of the Main
Terminal safe. Installing ADA compliant access improvements for disabled travelers on both the
Arrivals and Departures curbsides as part of the security work ensures that the design is
compatible. These improvements support the Ports goal of making SeaTac the most accessible
airport in the nation for people with disabilities.
DETAILS
Current ADA standards require the provision of one accessible loading zone for every
continuous 100 linear feet, or fraction thereof, of curbside. Each accessible loading zone shall
be designated with signage along both curbsides. Accessible loading areas on the drives are
COMMISSION AGENDA Action Item No. _6e___ Page 2 of 4
Meeting Date: January 30, 2018
Template revised September 22, 2016; format updates October 19, 2016.
critical, as confirmed by staff, who recommend that ADA accessible ramps be added and
incorporated into the security project, especially since the installation of both are so closely
tied together.
Scope of Work
The project will install security and ADA access improvements at the entrances to the Main
Terminal from the Arrivals and Departures curbsides. The number of accessible loading zones
will increase from two to twelve on the Arrivals curbside, and from three to twelve on the
Departures curbside. Security improvements will also be installed in the Main Garage at the
entrance to each of the six sky bridges.
This scope of work entails opportunities for small and disadvantaged businesses. Project staff is
working with the Economic Development Division Small Business Group, to help identify and
promote those opportunities within the scope of work.
Preliminary Schedule (TSE Phase II only)
Commission design authorization
2018 Quarter 1
Design start
2018 Quarter 1
This Request
Total Project
Design
$1,481,000
$2,087,000
Construction
$0
$10,854,000
Total
$1,481,000
$12,941,000
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Three options were considered as follows:
Alternative 1Status Quo Do not proceed with security or ADA access improvements
Cost Implications: $ 0
Pros:
(1) No capital investment
Cons:
(1) Does not increase the safety and security of the Main Terminal.
(2) Does not enhance ADA accessibility.
This is not the recommended alternative.
COMMISSION AGENDA Action Item No. _6e___ Page 3 of 4
Meeting Date: January 30, 2018
Template revised September 22, 2016; format updates October 19, 2016.
Alternative 2Proceed with the security improvements only
Cost Implications: $5,559,000
Pros:
(1) Proceeding with the security improvements will increase the safety and security of the
Main Terminal.
Cons:
(1) Requires a capital Investment of $5,559,000.
(2) Does not take advantage of an opportunity to install ADA access ramps with the
installation of security improvements in order to reduce the total costs of both
projects, avoid removing and reinstalling recently complete work if work is done
separately, and minimize construction impacts on the traveling public
This is not the recommended alternative.
Alternative 3 Proceed with security and ADA access improvements
Cost Implications: $6,653,000
Pros:
(1) Proceeding with security and ADA access improvements under one project saves
approximately $260,000 and reduces the overall construction impacts to the traveling
public.
(2) Proceeding with security improvements will increase the safety and security of the
Main Terminal.
(3) The Arrivals and Departures curbsides will become compliant with current ADA
standards sooner than currently planned and helps expedite achieving the Port goal of
making the Airport the most accessible airport for people with disabilities in the
nation.
Cons:
(1) Requires a greater capital investment of $6,653,000
This is the recommended alternative.
FINANCIAL IMPLICATIONS
Cost Estimate/Authorization Summary
Capital
Expense
Total
COST ESTIMATE
Original estimate
$9,854,000
$0
$9,854,000
Previous change (Phase I)
$714,000
$0
$714,000
Current change (Phase II)
$2,373,000
$0
$2,373,000
Revised estimate
$12,941,000
$0
$12,941,000
COMMISSION AGENDA Action Item No. _6e___ Page 4 of 4
Meeting Date: January 30, 2018
Template revised September 22, 2016; format updates October 19, 2016.
Cost Estimate/Authorization Summary
Capital
Expense
Total
AUTHORIZATION
Previous authorizations
$6,298,000
$0
$6,298,000
Current request for authorization
$1,481,000
$0
$1,481,000
Total authorizations, including this request
$7,779,000
$0
$7,779,000
Remaining amount to be authorized
$5,162,000
$0
$5,162,000
Annual Budget Status and Source of Funds
This project was included in the 2018 2022 capital budget and plan of finance with a budget
of $9,854,000 million. The cost increase is due to adding scope for the sky bridges (Phase I),
and adding the ADA access improvements (Phase II). The budget increase will be transferred
from the Aeronautical Allowance CIP (C800753) resulting in no net change to the Aviation
capital budget. The funding source will be the Airport Development Fund and future short-
term revenue bonds. This project was approved by the airlines via the November 2017
Majority-in-Interest vote.
Financial Analysis and Summary
Project cost for analysis
$12,941,000
Business Unit (BU)
Terminal Building
Effect on business performance
(NOI after depreciation)
NOI after depreciation will increase
IRR/NPV (if relevant)
N/A
CPE Impact
$0.07 in 2019
Future Revenues and Expenses (Total cost of ownership)
Port staff does not anticipate a significant change in the on-going operation and maintenance
costs associated with these improvements since preventative maintenance is not performed on
the security and ADA access improvements. Additional costs will be incurred if the
improvements are damaged and need to be replaced.
ATTACHMENTS TO THIS REQUEST
None
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
October 24, 2017 The Commission authorized Design and Construction of Phase I of
Airport Terminal Safety Enhancements and Security Improvements