Item No. _9a_supp___ Meeting Date January 9, 2018 Baggage Optimization 2017 Quarter 4 Briefing 1 Purpose • Replaces six individual baggage screening systems with a centralized system that optimizes the operation and functionality of the checked baggage system • Accommodate 60 Million Annual Passengers (MAP) • Passengers will benefit from increased capacity, reliability, redundancy, and security Meeting travelers' baggage needs will contribute to increased customer service 2 Schedule • Phase 1 - Notice to Proceed issued on May 26, 2017 and construction is underway • Phase 2 - Design underway to develop Bid Documents • Overall project construction expected to be complete in 2025 Quarter 1 Construction underway 3 Phase 1 Construction Q1 2017 - Q3 2019 4 Phase 2 Construction Q2 2019 - Q2 2022 5 Phase 3 Construction Q3 2022 - Q1 2025 6 Financials Total Project Budget $445,050,000 Total TSA Contribution $93,220,422 Total Commission Authorization to Date $136,312,200 Amount Spent to Date (as of 11/9/17) $27,996,064 TSA Reimbursement to Date (as of 11/9/17) $9,885,804 Project on budget as currently scoped 7 Phase 1 Progress • TSA delivered (8) baggage screening machines • Concrete demolition and excavation of CT ramp between basement and ramp levels • Utility relocations and lighting installation • BHS conveyor mock-up assembly and review • Drywall, electrical, and communication installation in new AVM foreman offices Upcoming work: structural support of CT ramp, review of BHS submittals, and conveyor delivery 8 TSA delivery of eight baggage screening machines 9 Demolition of concrete and excavation of CT ramp between basement & ramp levels 10 BHS conveyor mock-up under review 11 Rebar installation and concrete pour for CT building extension 12 Contract Requirements Program Requirement / Goal To Date Small Business Enterprise (SBE) 15% of contract value 11.26% total 5% of SBE 5.53% 15% of total hours 18.27% Small Contractors & Suppliers (SCS) Apprenticeship • Pending Commission resolution, MWBE goals will be included in future procurements Progress as of 11/9/17 13 Phase 2 Progress • Executed Service Directive • Held kick-off meeting • Continued bi-weekly coordination meetings • Reviewed lessons learned from Phase 1 • Risk & mitigation identification Upcoming work: Identify critical milestones and develop sequencing plan 14