
COMMISSION AGENDA – Action Item No. _4h___ Page 2 of 4
Meeting Date: December 12, 2017
Template revised September 22, 2016; format updates October 19, 2016.
JUSTIFICATION
During a utility power outage, the Airport is unable to operate. An extended loss of utility
power at the Airport halts the Port’s, airlines’ and tenants’ ability to utilize the Airport. Loss of
electrical power shuts down airline and concession electronic communications, jet bridge
operations, flight information displays, ticket printers, security checkpoints, electric ground
support equipment (eGSE) chargers, baggage conveyors, lighting for legal occupancy within the
terminal, heating/cooling systems, and other functions. The continued reliable operation of
Sea-Tac Airport is vital to meeting the needs of the region and the airlines.
The Alternate Utility Facility (AUF) is providing a separate power source to the airport’s south
connection point to the utility transmission grid. The design and construction of the AUF has
required PSE to modify their interconnection equipment and to study the effects on their
transmission network. This work is cost reimbursable to PSE and is governed by a project
specific utility agreement. After initial work PSE has estimated that their efforts will cost more
than is allowed in the current Not-To-Exceed agreement.
DETAILS
Scope of Work for the Amendment
(1) Relocate PSE Point of Service #1 and #2 and associated ancillary equipment.
(2) Study impact of AUF on PSE transmission system.
Schedule
Activity
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1 – Do not increase the Not-To-Exceed amount of the ESCA
Cost Implications: $30,000,000 Expensed (Asset will be delivered, but will be unusable)
Pros:
(1) None.
Cons:
(1) PSE crews will be unable to complete their work installing, testing, and commissioning
necessary PSE facilities and assets.
(2) AUF project will not be able to interface with PSE facilities rendering the AUF facility
unusable.
This is not the recommended alternative.