
COMMISSION AGENDA – Action Item No. 4b Page 2 of 4
Meeting Date: 12/5/2017
Template revised September 22, 2016; format updates October 19, 2016.
South Satellite – Freight
Main Terminal – South/Center
MT-3
Public elevator to Police Department; stops
at ramp, ticketing and floors 2, 3, and 4.
Modernize
MT-4
Police service elevator; stops at ramp,
ticketing and floors 2, 3, and 4.
Modernize
MT-5
Police service elevator; stops at ramp,
ticketing and floors 2, 3, and 4.
Modernize
MT-6 Main Terminal – North/Central Modernize
Twelve hydraulic
elevators
B, J, K, L, Q, D1, MT-8, MT-9, MT-20, MT-30,
MT-40, MT-50
Add hydraulic oil cooling
packages
601, 602, 611, 612
North end of Main Terminal, serving Sky
Bridge #6
Replace
DETAILS
On April 21, 2014, the Port executed a construction contract with Absher Construction for the
amount of $4,603,000 with a contract completion date of April 20, 2016 (duration of 730
calendar days). Through the Change Order process, 76 days of time were added to the contract
for a Substantial Completion date of July 5, 2016 (41 plus 35 days on 2 Change Orders).
The Contractor experienced labor and production issues which delayed the project completion
by 168 days until 12/21/2016, when Substantial Completion was accomplished. Post Substantial
Completion, design errors were identified during a Labor & Industries permit inspection on
elevator MT-3, which was required to be corrected. This Change Order settles the final cost
and time due to delays caused by both the Port and the Contractor.
Scope of Work
Work included development of infrastructure to modernize seven existing elevators and four
escalators, and retrofit twelve hydraulic elevators with hydraulic oil cooling systems.
Infrastructure development included: