COMMISSION AGENDA – Action Item No. __4g__ Page 5 of 10
Meeting Date: November 14, 2017
Template revised September 22, 2016; format updates October 19, 2016.
with the use of a PLA, offsite labor, such as for the delivery of materials, is not a part of
the PLA.
4) Completion of the initial phase of work by 5/31/18 so the IAF bridge construction can
proceed. The projects are linked as the detour route for Taxiway A during April to May
construction encumbers Hardstand 6 and the IAF work will need to shift aircraft from
Hardstand 2 to Hardstand 6 for the bridge assembly to occur.
5) Beginning work after Labor Day that is anticipated to extend into December will be
highly dependent upon favorable weather, a scarce commodity at that time of year, and
the ability for the Contractor to access the airfield, which may be prevented during fog
or other such conditions. The late start of work could cause the work the re-opening of
RW 16L/34R to be delayed. Since this runway is the longest and closest to the terminal,
an extended closure has an extremely high impact on airport operations. During poor
visibility conditions the airport may go into Surface Movement Guidance and Control
Systems (SMGCS) and the airport will then be limited to a single runway. Once the 2
nd
phase of airfield construction begins, the work then must be completed and deleting
scope is not a mitigation option. The nature of the work; excavation, lighting, and
utilities, within the runway and taxiway safety areas cannot be left unfinished or open.
6) Should the 2
nd
phase of airfield construction, which closes the runway, extend to late
January 2019, the NSAT Phase 1 opening of gates that allows work to continue on NSAT
Phase 2 and to maintain airline operations would be impacted.
Mitigation measures continue to be developed and will need to be reexamined as the project is
delivered. Current mitigation measures include:
1) Request for approval to notify rather than return to the Commission should an irregular
bid occur and for the contract to be awarded as long as there are sufficient authorized
funds will help to avoid delays in the project proceeding.
2) Appropriate measures to ensure the initial phase of work is complete before the current
union contracts expire on 5/31/18 will be used.
3) Staff is working with FAA and the airlines to examine the potential earlier start of the 2
nd
phase of work to reduce risk that occurs with construction in the fall and winter. This
would also help to avoid or mitigate the domino of impacts that could occur to airport
operations and the NSAT project should completion of this work be delayed by weather.
4) As mentioned above, weather, bid protests, and other such external factors are difficult
to mitigate in advance but will be monitored, communicated and addressed at the time,
should they occur.
Scope of Work
1) Relocate Taxiway L
2) Adjust Taxiways B/Q centerline radii to include adjustment of in-pavement taxiway
centerline lights and pavement marking
3) Modify and realign Surface Movement Ground Control (SMGC’s) lights and connection
centerlines between Taxiway A, Taxiway B and entrance to North Satellite taxilane
4) Replace damaged asphalt with concrete at South Satellite