Item No.: Meeting Date: 6e_s upp June 27, 2017 C800612 Baggage Optimization Capacity Acceleration June 27, 2017 1 Capacity Increase Scope Request • • • • The Baggage Optimization project was initially scoped in 2012 to accommodate a projected volume of 45 million annual passengers (MAP), with an expandable design to accommodate future growth. 45 MAP was expected to be adequate capacity through 2027; however, due to unprecedented growth, the Airport exceeded 45 MAP in 2016. To avoid significant negative impacts to airlines and travelers, acceleration of this future work is necessary now in order to increase the baggage system capacity to accommodate a projected 60 MAP. Requesting to incorporate expansion into existing Baggage Optimization Phases 2 and 3. The Airport is growing faster than was anticipated. 2 Revised Baggage Optimization Phases (including future capacity of 60 MAP) Budget Construction Start Construction End Phase 1 $135 M Q2 2017 Q3 2019 Phase 2 $83 M + 60 MAP Q3 2019 Q2 2022 Phase 3 $100 M + 60 MAP Q2 2022 Q4 2024 Project Phase Original Total $319 M Q4 2023 (Original) 60 MAP Capacity + $150 M 14 months Favorable Phase 1 Bid - $24 M Revised Total $445 M Q 2024 This capacity increase will add $150M and 14 months to the project. 3 Budget Details • • Budget Increase: + $150,000,000 Capacity Increase scope - $24,000,000 Return from favorable Phase 1 bid = $126,000,000 Net Increase for Increased Capacity New Total Project Budget $319,050,000 Original Budget + $126,000,000 Net Increase for Increased Capacity = $445,050,000 Revised Total Estimate Project Cost Revised project budget will be $445,050,000. 4 Budget Details • This Request: + $19,937,000 + $5,000,000 - $24,300,000 = $637,000 Project Management funds to expand capacity Port crews and small works to perform additional construction work Return from favorable Phase 1 bid (previously authorized for construction) Net Increase for Increased Capacity This request is for Commission to authorize $637,000. 5 Additional Capacity Scope Details • • • • • Five CTX machines (TSA provided) and spur lines Two additional mainlines Two additional recirculation lines Building infrastructure to accommodate additional BHS capacity With coordination of the IAF project- - - - • Two additional makeup units One manual encode station Partial demolition of IAF baggage system Additional feedlines With coordination of the South Satellite renovation project- - - Additional outbound line in the baggage tunnel Two additional makeup units Availability to add manual encode and additional makeups in the future Required Baggage Optimization Scope to achieve 60 MAP 6 Port Construction Services Pre-Work Scope • • • • • • • • • • H-line wall code compliance for Phase 2 permit Claim 13 conveyor input installation Right of way clearances Right of way conveyor, MCP and conduit demolition Change order alternative Portering Shutdown support Equipment movement and TSA/contractor support Tenant, TSA, Airline and Port move support Testing Support This PCS work will help to streamline the transition between phasing and capacity expansion. 7 Baggage Optimization Project Update 8 Q1 Financials Total Project Budget $ 319,050,000 Total TSA Contribution $ 93,220,422 Total Commission Authorization to Date $ 135,375,000 Amount Spent to Date (as of 3-31-17) $ 20,454,390 TSA Design Reimbursement to Date (as of 3-31-17) $ 5,834,580 The project is within budget as originally scoped. 9 Phase 1 Bid Results • Contract Awarded to lowest bidder: - PCL Construction Services Inc. (General Contractor) - Jervis Webb (Baggage Sub-Contractor) • Bid Amount: - $52,000,000.00 (Below Engineer's Estimate) The project returned $24M due to a low bid below the Engineer's Estimate. 10 Phase 1 Small Business Requirements • Small Business Requirement: 15% - Certified Small Business: 5% included within 15% total • Specialized Baggage, Controls, and Electrical equipment installation is not heavily represented in the Small Business Community. Total Requirement: 15% Small Business 11 Phase 1 Pre-work • New makeup device and a new odd-size device in the North end of the bagwell have been installed. • Work completed by PCS, Port Maintenance, and Small Works. Completion of pre-work allowed Horizon operations to be moved prior to major contract work 12