COMMISSION AGENDA – Action Item No. __6d__ Page 8 of 9
Meeting Date: June 27, 2017
Template revised September 22, 2016; format updates October 19, 2016.
• April 26, 2016 – NorthSTAR Program status update
• February 9, 2016 – NorthSTAR Program status update
• December 8, 2015 - Project authorization, and execute contract amendments and
change orders to HP for $98.1 million and execute a contract for project specific
construction audit services.
• November 24, 2015 – NorthSTAR Program status update and NSAT budget briefing
• July 14, 2015 – NorthSTAR Program status update
• April 28, 2015 – NorthSTAR Program status update
• March 28, 2015 – The Commission authorized three NSAT related items:
o Expand the baggage handling system increasing the project scope for
$14,400,000 and authorizing $1,954,000 to complete the design.
o Entering into a developer agreement with Puget Sound Energy and authorizing
$200,000 in reimbursement for the design and construction of underground gas
infrastructure.
o Authorized $5,300,000 to
Prepare four locations to accommodate temporary passenger loading
bridges, to construct temporary construction offices.
To complete construction of a Satellite Transit System (STS) North loop
Dynamic Display system.
$600,000 in expense funds for regulated materials management for AS’s
tenant improvement project.
Approval to use Port crew labor and small works contractors to complete
early project work.
• January 27, 2015 – NorthSTAR Program Status Update
• January 6, 2015 – The Commission authorized (1) $5,000,000 preconstruction services;
(2) execution of a General Contractor/Construction Manager contract for
preconstruction services; and (3) transfer of scope, $1,750,000 budget and authorization
for STS station roof replacement to the North Satellite Renovation and Expansion
project.
• October 28, 2014 – NorthSTAR Program Status Update
• August 5, 2014 – Commission authorized an estimated $191,323,143 to expand the
NSAT by 8 additional gates, an additional $15,717,800 for design completion, and use of
the General Contractor/Construction Manager alternative public works contracting
procedure for NSAT expansion construction procurement.
• July 22, 2014 - NSAT Expansion Briefing.
• April 16, 2014 – Seattle-Tacoma International Airport Capital Program – Briefing.
• January 14, 2014 – NorthSTAR Program status update and initial NSAT Expansion
briefing.