COMMISSION
AGENDA MEMORANDUM
Item No.
6d
ACTION ITEM
Date of Meeting
June 27, 2017
DATE: June 5, 2017
TO: Dave Soike, Interim Executive Director
FROM: Ralph Graves, Senior Director Capital Development Division
George England, Program Leader, Aviation Project Management Group
SUBJECT: North Satellite Renovation & North Satellite Transit Station Lobbies Project (NSAT)
(CIP #C800556)
Amount of this request:
$200,000,000
Total estimated project cost:
$551,321,192 (update in August)
ACTION REQUESTED
Request Commission authorization for the Executive Director to: (1) increase project
authorization for the North Satellite Renovation & North Satellite Transit Station Lobbies
Project by $200,000,000; (2) execute Preliminary Work Amendment #3 (PWA #3) with Hensel
Phelps (HP) for up to $200,000,000; (3) authorize Port staff to execute all change orders to the
HP contract within authorized budget and project scope without returning for additional
Commission authorization; and (4) authorize Port Construction Services (PCS) to execute small
works contracts and use Port crews to support NSAT construction.
EXECUTIVE SUMMARY
Since September 13, 2016, when the Commission authorized an additional $7 million capital
budget increase for the third floor redesign for a total authorized budget of $551M, staff has
completed the scope and budget transfers associated with taxiway revisions, emergency
generator purchase and consolidation of Program Management CIP. Additionally, the final
NSAT design was completed on April 14, 2017. The project team consisting of the Port, Alaska
Airlines (AS), AECOM and HP has continued to collaborate and coordinate, as has been the
foundation of the Port/Alaska partnership throughout, to refine the development of the NSAT
project. Staff has determined the current $551M authorized budget must be increased, the
magnitude of which will be updated in August of 2017.
The result of the last nine months is an improved design that better addresses customer and
operational service, gate capacity and the passenger experience for the next 5 years. The intent
has been to ensure that during construction there is no significant degradation in level of
service and to assure the smooth activation of each new portion of the facility. Recent work
COMMISSION AGENDA Action Item No. __6d__ Page 2 of 9
Meeting Date: June 27, 2017
Template revised September 22, 2016; format updates October 19, 2016.
included validation of the design by conducting simulations, analysis, studies, detailed phasing,
micro phasing and construction sequencing.
The negotiations continue with HP on the final Maximum Allowable Construction Cost (MACC)
and the project team continues to refine the final estimated cost and budget required to
complete the project. The final cost impacts of all this will exceed the current $551M budget
and staff is working to finalize the necessary increase to move the project forward. In order to
continue construction and maintain the overall project completion schedule, staff recommends
amending the HP contract under PWA #3 to perform Preliminary Work Package #3 (PWP #3) for
up to an additional $200,000,000. PWA #3 allows HP to retain current staff, continue
construction and to execute contracts with all subcontractors whose bids have been accepted
for the base building construction.
In order to maintain project schedule and construction sequencing, staff is requesting
authorization to execute all pending and future change orders to the HP contract within
authorized budget and project scope. The allowances and contingencies identified in the
contract are required by RCW and are the contractual mechanisms for executing the future
change orders. Staff will provide summaries of these changes in quarterly briefings throughout
construction.
To better accommodate unforeseen/changed conditions and install port procured equipment,
staff is requesting approval for PCS to execute small works contracts with small contractors and
suppliers and use crews in support of the NSAT construction.
Port staff is working closely with AS to prepare a letter of concurrence to move forward with
this project in accordance with the Letter of Understanding between the Port and AS dated
April 5, 2012.
Key Points:
1. Authorization to execute a contract amendment with HP is requested to maintain the
project schedule completion dates. While staff continues finalizing the necessary
budget increase, negotiating the final MACC, the Port and HP have negotiated services
and secured subcontract bids for the project. Details of the contract amendment are as
follows:
a. HP will execute contracts with all subcontractors whose bid results have been
received and accepted in order to retain each sub and their bid pricing. This is
needed given the current hot construction market, and increases in commodity
and subcontractor pricing that we are experiencing.
b. Increase General Conditions and Negotiated Support Services for items that HP
would normally provide on a construction project including temporary phasing
COMMISSION AGENDA Action Item No. __6d__ Page 3 of 9
Meeting Date: June 27, 2017
Template revised September 22, 2016; format updates October 19, 2016.
support items such as lifting and transport equipment, work platforms, shoring,
scaffolding and barricades to separate and protect passengers from the
construction work.
JUSTIFICATION
Amending the contract by up to $200,000,000 is necessary to support the critical path of
construction, to retain current HP staff managing the construction, to retain subcontractor bids
by executing contracts and to maintain the overall project schedule completion dates. This
provides staff the additional time required to finalize the specific budget increase and complete
negotiations of the final MACC. Staff will return to the Commission with the full project
authorization request in August 2017. To date $196,773,800 has been previously authorized for
design and preliminary work. Staff recommends proceeding with construction by increasing
the current project authorization and executing a contract amendment with HP.
Staff has been advancing construction activities through two preliminary work packages that
have used previously authorized funds. The preliminary work has benefitted the project and
will seamlessly transition into the major construction of the project. Preliminary construction
work includes excavation, footings and foundations, preliminary mechanical, electrical and
plumbing utilities below grade, metal decking, and the structural steel for the expansion
portion of the North Satellite building. Structural piles have been installed in the new
expansion area as construction progresses.
The formal majority-in-interest (MII) project approval for $531 million occurred on March 31,
2016. The Commission previously authorized additional scope items added to the project on
September 13, 2016. Staff recently briefed the Airlines on May 18, 2017 on the current status of
the project. Staff has determined another MII approval from the Airlines is not required as
described in the section titled budget and source of funds below.
Staff has been reporting that market conditions have contributed to overall budget increases.
These factors are now included as realized market driven cost increases, due to documented
increases in regional construction activity, increases in subcontractor and commodity pricing,
resulting in a low interest bidding climate. While staff has worked closely with the contractor
to maximize bidder interest to obtain competitive pricing, a large number of sub-bid packages
had only one or two bidders. As we completed the design the building systems designs were
fully developed resulting in the engineer’s estimate for the project increasing. As a result staff
has determined the budget must increase, the magnitude of which is not fully finalized at this
time.
Staff has and will continue to work closely with AS and HP to mitigate construction impacts in
order to maintain the highest level of customer and operational experience during the project.
A more complex and detailed construction work-sequencing plan to transition from Phase I to
Phase II has been completed. The sequencing plan harnesses new port strategies for growth via
COMMISSION AGENDA Action Item No. __6d__ Page 4 of 9
Meeting Date: June 27, 2017
Template revised September 22, 2016; format updates October 19, 2016.
the new Hardstand Terminal at Concourse D to minimize impacts to airport operations while
providing as many operational gates as possible during the construction.
This project has been coordinated with the Sustainable Airport Master Plan (SAMP), continues
to coordinate closely with the near term planning of the Airport through 2021, and will not be
adversely affected by future development recommendations of SAMP.
Project Objectives
1. Extend the length of NSAT by approximately two hundred forty feet to improve
customer service and accommodate additional aircraft and passengers.
2. Seismically strengthen NSAT and expand the existing infrastructure.
3. Balance and integrate NSAT functional areas and requirements (concessions,
holdrooms, amenities, airline operations and airline services) through a renovation and
expansion of the NSAT’s terminal area to achieve acceptable levels of service.
4. Align near term and forecasted airport-wide gate use and capacity by providing 20
contact gates at NSAT.
5. Optimize gate door contact points, loading bridges and aircraft parking positions,
including fuel hydrants and other support utilities.
6. Meet or exceed current sustainability goals of the Century Agenda. This project is
pursuing Leadership in Energy and Environmental Design (LEED) certification.
7. Create a “frictionless” and stress-free passenger experience within NSAT.
8. Create an exciting and attractive facility integrating hold-rooms, diverse amenities and
numerous concessions.
9. Maintain and promote a Northwest sense of place through the design of architecture
and connected technologies.
DETAILS
The project design has been completed and delivered to HP. The passengers will travel
smoothly through the construction areas and be drawn to positive digital messaging illustrating
the final facility configuration. The Port has collaborated with the contractors, designers and
Alaska to maintain operational requirements through the planned construction.
Numerous passenger flow simulations, level of service analyses, and circulation/use studies
have been conducted. These efforts have led to a path of success during the construction
phases and assuring the smooth activation of each consecutive sequence of construction. The
collaboration results in a better overall NSAT terminal design.
COMMISSION AGENDA Action Item No. __6d__ Page 5 of 9
Meeting Date: June 27, 2017
Template revised September 22, 2016; format updates October 19, 2016.
Scope of Work
This request includes the following elements associated with the requested authorizations:
1. Amend the HP contract by up to $200,000,000 to maintain project schedule completion
dates. While finalizing negotiations on the MACC for a revised total authorization of
$299,895,187 capital.
2. Authorize PCS to execute small works contracts and use crews to support NSAT
construction.
Small Business
Under the current scope of work the Contractor and their sub-contractors will be executing
small works contracts. In addition any work required to support the project contracted through
Port PCS will further continue to support small business attainment for this project.
Schedule
The schedule to complete the project as noted below. The team has accommodated many
changes including the redesign of the third floor. HP’s bidding schedules are completed. The
team has agreed to the project schedule and it is specifically noted in the HP contract
amendment.
Activity
Design completion
2
nd
Quarter 2017
Commission construction authorization
2
nd
Quarter 2017
Construction start
2
nd
Quarter 2016
In-use date Phase 1
2
nd
Quarter 2019
In-use date Phase 2
3
rd
Quarter 2021
Substantial Completion
1
st
Quarter 2022
Cost Breakdown
This Request
Project Total
Design
$0
$80,844,013
RMM/ERL
$0
$11,800,000
Construction
$200,000,000
$432,245,676
State & Local Taxes
$0
$38,231,503
Total
$200,000,000
$563,121,192
COMMISSION AGENDA Action Item No. __6d__ Page 6 of 9
Meeting Date: June 27, 2017
Template revised September 22, 2016; format updates October 19, 2016.
FINANCIAL IMPLICATIONS
Authorization Summary
Capital
Expense
Total
Previous Budget
$538,102,042
$11,800,000
$549,902,042
Budget Transfers
$13,219,150
$0
$13,219,150
Current Budget
$551,321,192
$11,800,000
$563,121,192
Previous authorizations
$194,718,800
$3,500,000
$198,218,800
Authorization Transfers associated with
above Budget Transfers
$2,055,000
$0
$2,055,000
Current request for authorization
$ 200,000,000
$0
$200,000,000
Total authorizations, including
this request
$396,773,800
$3,500,000
$400,273,800
Remaining amount to be authorized
$154,547,392
$8,300,000
$162,847,392
Annual Budget Status and Source of Funds
This project is included in the 2016 2020 capital budget and plan of finance with a budget of
$415.8 million. The project will be funded with a combination of Airport Development Fund,
revenue bonds and Passenger Facility Charge revenues (PFCs).
The terms under which AS will participate in the Port’s NorthSTAR Program costs have been
established via an April 5, 2012, Letter of Understanding between the Port and AS. The airlines
approved this project for $531 million on March 31, 2016 via the majority-in-interest (MII)
process as outlined in the Signatory Lease and Operating Agreement (SLOA). Since the project
is under construction, per SLOA any additional budget increase does not require further MII
approval. The airlines were recently briefed on the potential for a budget increase on May 18,
2017.
Financial Analysis and Summary
Project cost for analysis
$551M
Business Unit (BU)
Terminal
Effect on business performance
(NOI after depreciation)
NOI after depreciation will increase
IRR/NPV (if relevant)
N/A
CPE Impact
$1.20 in 2021 per March 2016 MII. To be updated upon
agreement of MACC.
Future Revenues and Expenses (Total cost of ownership)
An adequate estimate of staff hours and materials expense to operate the expanded and
renovated NSAT building is still in development. Thorough design reviews of 30, 60, and 90
percent design stages have evaluated infrastructure systems to minimize the total cost of
ownership. It is already understood that the additional expansion area will incur additional
COMMISSION AGENDA Action Item No. __6d__ Page 7 of 9
Meeting Date: June 27, 2017
Template revised September 22, 2016; format updates October 19, 2016.
maintenance expense. A key objective of the project is installing sustainable materials and to
maximize the maintainability of the new equipment. The complete renovation/replacement of
the mechanical, electrical, lighting, communications, pre-conditioned air, 400 Hz, baggage and
other major systems provides an opportunity to achieve life cycle cost efficiencies and savings.
The project is pursuing LEED certification, and is submitting the design for evaluation in June of
2017. Rigorous in depth studies and evaluation of options for 30 year life cycle cost have
resulted in a more holistic decision making throughout the design process, balancing first cost,
energy consumption, replacement cost of infrastructure, and maintenance over the life of the
facility. The resulting design champions total cost of ownership for the Port.
ATTACHMENTS TO THIS REQUEST
None
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
April 25, 2017 –NorthSTAR Program status update
January 24, 2017 –NorthSTAR Program status update
September 13, 2016 Commission authorized four NSAT related items:
o Increase the North Satellite Renovation & North Satellite Transit Station Lobbies
(NSAT) project scope and budget (capital) by $7,000,000 for a revised total
budget of $549,902,042.
o Increase authorization by $1,000,000 for project design.
o Amend design service agreement with URS that exceeds 50% of the value of the
original contract.
o Increase authorization by $30,000,000 for Preliminary Work Package #2 (PWP
#2) construction for a revised authorization total of $194,718,800.
August 9, 2016 NorthSTAR Program status update
May 24, 2016 Commission authorized four NSAT related items:
o Increase NSAT project scope and budget (capital and expense) by $121,219,098
for a revised total budget of $542,902,042.
o Increase authorization by $11,000,000, $5,000,000 for continued NorthSTAR
Program/Project Management services (CIP# C800544) for a new total of
$9,350,000 and $6,000,000 and overall project support (CIP# C800556) for a new
total of $163,718,000.
o Amend service agreements with Jacobs Project Management Company and URS.
o Authorize the use of port crews and small works contractors to perform work for
the project.
COMMISSION AGENDA Action Item No. __6d__ Page 8 of 9
Meeting Date: June 27, 2017
Template revised September 22, 2016; format updates October 19, 2016.
April 26, 2016 NorthSTAR Program status update
February 9, 2016 NorthSTAR Program status update
December 8, 2015 - Project authorization, and execute contract amendments and
change orders to HP for $98.1 million and execute a contract for project specific
construction audit services.
November 24, 2015 NorthSTAR Program status update and NSAT budget briefing
July 14, 2015 NorthSTAR Program status update
April 28, 2015 NorthSTAR Program status update
March 28, 2015 The Commission authorized three NSAT related items:
o Expand the baggage handling system increasing the project scope for
$14,400,000 and authorizing $1,954,000 to complete the design.
o Entering into a developer agreement with Puget Sound Energy and authorizing
$200,000 in reimbursement for the design and construction of underground gas
infrastructure.
o Authorized $5,300,000 to
Prepare four locations to accommodate temporary passenger loading
bridges, to construct temporary construction offices.
To complete construction of a Satellite Transit System (STS) North loop
Dynamic Display system.
$600,000 in expense funds for regulated materials management for AS’s
tenant improvement project.
Approval to use Port crew labor and small works contractors to complete
early project work.
January 27, 2015 NorthSTAR Program Status Update
January 6, 2015 The Commission authorized (1) $5,000,000 preconstruction services;
(2) execution of a General Contractor/Construction Manager contract for
preconstruction services; and (3) transfer of scope, $1,750,000 budget and authorization
for STS station roof replacement to the North Satellite Renovation and Expansion
project.
October 28, 2014 NorthSTAR Program Status Update
August 5, 2014 Commission authorized an estimated $191,323,143 to expand the
NSAT by 8 additional gates, an additional $15,717,800 for design completion, and use of
the General Contractor/Construction Manager alternative public works contracting
procedure for NSAT expansion construction procurement.
July 22, 2014 - NSAT Expansion Briefing.
April 16, 2014 Seattle-Tacoma International Airport Capital Program Briefing.
January 14, 2014 NorthSTAR Program status update and initial NSAT Expansion
briefing.
COMMISSION AGENDA Action Item No. __6d__ Page 9 of 9
Meeting Date: June 27, 2017
Template revised September 22, 2016; format updates October 19, 2016.
September 24, 2013 NorthSTAR Program status update.
September 24, 2013 The Commission authorized staff to: (1) advertise, award, and
execute a major public works contract for the construction of the NSAT Refurbish
Baggage System Project; and (2) authorize the use of Port crews.
June 25, 2013 NorthSTAR Program status update.
May 28, 2013, Commission authorized the execution of separate service agreements for
Construction Management Services and Commissioning Services, of approximate values
of $10 million and $1.5 million.
April 9, 2013 The Commission authorized the Chief Executive Officer to enter into a
project labor agreement covering the NorthSTAR program’s five major construction
projects.
March 26, 2013 NorthSTAR Program status update.
December 11, 2012 The Commission was briefed on the Vertical Conveyance
Modernization Project Aero Phases 1 and 2 and the possibility of adding the specified
elevators and escalators to the NorthSTAR program.
July 24, 2012 - Commission authorized $32,000,000 for the design of the NorthSTAR
NSAT Renovation and NSTS Lobbies project.
June 26, 2012 - The Port Commission was briefed on the NorthSTAR program by Wayne
Grotheer, Director Aviation Project Management Group.
April 10, 2012 - The Commission authorized the execution of consultant contracts for
design and construction support services; program management services; and the
completion of site surveys for regulated materials management, for $1,200,000.