COMMISSION AGENDA – Action Item No. _6a_ Page 4 of 5
Meeting Date: June 27, 2017
Template revised September 22, 2016; format updates October 19, 2016.
Current request for authorization
Total authorizations, including this request
Remaining amount to be authorized
Annual Budget Status and Source of Funds
This project, CIP C800722, was included in the 2017-2021 capital budget and plan of finance
with a budget of $6,589,000. The revised estimate includes a scope transfer for the ADR
Infrastructure Modifications project from CIP C800638 Concession Infrastructure with a budget
amount of $6,190,000 and a budget increase of $4,032,000 transferred from the Aeronautical
and Non-aeronautical Allowance CIPs. The funding source will be 2018 revenue bonds.
Financial Analysis and Summary
Project cost for analysis
Terminal Building (HVAC) and Terminal Non-Aeronautical
(vertical circulation)
Effect on business performance
(NOI after depreciation)
NOI after depreciation will increase
Future Revenues and Expenses (Total cost of ownership)
Aviation Maintenance anticipates only a minimal increase in Operations & Maintenance costs
with respect to the additional 13 Variable Frequency Drives and the Light Emitting Diode
lighting for the sides of the two staircases which will be absorbed with current resources. No
impact is anticipated as a result of the renewal and replacement of existing equipment. There
will be an increase in O&M costs related to the two additional elevators of approximately
$35,000/year on the current elevator service contract, and a total annual increase of $8,000 for
the two additional HVAC units as a result of this project.
ATTACHMENTS TO THIS REQUEST
(1) Presentation slides
(2) Video presentation
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
August 9, 2016 – Central Terminal Expansion Heating Ventilating and Air-conditioning
Upgrade Construction Authorization (CIP C800722)