
COMMISSION AGENDA – Action Item No. 6a Page 2 of 7
Meeting Date: January 24, 2017
Template revised September 22, 2016; format updates October 19, 2016.
overlay instead of a complete roof system replacement. Proceeding with an overlay allows the
Port to retain the existing roofing, insulation and substrate, saving schedule, duration and cost.
While the existing condition issues on the Concourse C roof were being worked through,
Concourse B roof was under design and also designated via the design process as a good
candidate for a roof overlay. Since Concourse C roof replacement was deferred until 2017 and
Concourse B was slated for 2017, staff decided, after review with Engineering, CPO,
Maintenance, and the Aviation Project Management Group, that these projects could be
procured as one construction project. This will allow the Port to potentially save costs by
initiating a single procurement and managing a single construction contract.
JUSTIFICATION
Replacing airport roofs extends the life of the building, an important Port asset. The Concourse
B and C roofs, similar to other critical systems, must be replaced as they age and deteriorate.
The current roofing systems on Concourse B and C are 25 years old and have reached the end
of their dependable leak-free lifespan. Because the roofs are exposed to the elements and
experience wear and tear, when they fail the risk to the traveling public increases, and the safe
availability of the facility becomes impaired. In order to provide a leak-free terminal
environment and safe experience for those who travel through and work in the facility, the
Concourse B and C roofs have been identified as the next roofs to be replaced.
The recommended replacement age for this type of roof is between 15-20 years. The
warranties have expired as the roofs are beyond the industry standard life expectancy. While
the existing roofs are leaking, those leaks are considered relatively minor at this time. However,
as leaks occur there is the potential for leaking water to enter the public spaces and place both
tenants and passengers at risk of slips and falls. When leaks occur, the Airport may be required
to secure the portion of the concourse where the leaks are occurring during wet weather
events as a preventive measure. This is contrary to the Port’s strategy of anticipating and
meeting the needs of our customers, as this action would take portions of the concourse out of
service during a time of increased usage and gate shortages.
For Concourse B and Concourse C we are replacing the roof using a roof overlay. A roof overlay
replaces the topmost roofing membrane only. It allows the Port to retain and reuse the roofing
materials underneath the roofing membrane. While the existing roof membrane is breaking
down, it has protected the existing materials beneath it allowing for them to be reused. The
overlay will prevent the demolition and haul away of materials that are in good serviceable
condition. In addition, roofing membrane manufacturers will provide the same warranty the
Port receives on standard roof replacement projects that replace everything. As the alternatives
analysis highlights below, an overlay reduces the cost of replacing both roofs by $1.3 million to