Page 4 of 6
Wayfinding Signage and Curbside Modifications - Construction Contract
Construction Status Summary
ï‚· Phase I contract completed November 18, 2011.
ï‚· Phase II (Signage) the Contractor remobilized on January 9, 2012, and contract completion date is
April 20, 2012. The Contractor was issued Beneficial Occupancy on March 9, 2012.
ï‚· Construction progress on Phase II is 100% complete.
Milestones Accomplished this Month
ï‚· All signage is complete as of March 9, 2012. Temporary signage will remain in place to maintain
existing directions until the date that new shuttle bus operations commence.
Cost Status Summary
ï‚· Summary: 19 change orders have been issued and 4 are pending.
Design
Design Work in Progress
 RCF: No additional Design Change Notices (DCN’s) have been issued. Approximately 2,782
Requests for Information (RFI) have been submitted by the contractor, of which 2,782 are closed.
ï‚· RCF Signage: Team continues developing various rental customer travel scenarios and timeline to
allow staff before facility opening to conduct mock trial runs to further ensure adequate wayfinding
and signage is in place. The Port will install additional signage if determined necessary after these
trial runs are conducted.
ï‚· AT&T under construction and nearing completion. Wi-Fi installation continues in CSB.
ï‚· All Port supplied systems, furniture and equipment has been approved, ordered and some have been
delivered.
ï‚· Port Construction Services is currently installing additional Bird Control, Pipe Protection, CSB Wi-Fi
conduit, Power to wayfinding signage, additional lighting required by code, modifying speed bump
heights and Stair L emergency egress code modifications.
ï‚· Final contract getting signatures for DWA to prepare the final record drawings.
ï‚· Commission approved the surplus and transfer of property to the City of SeaTac and WSDOT. A
number of smaller property surplus and property transfer agreements with various Utility companies,
WSDOT and City of SeaTac for RCF, BMF and ORI projects remain.
Industry
ï‚· Held Industry joint business and technical meeting on March 14, 2012. All tenants are under
construction and making good progress. Continued coordinating with Facility Management Company
on turnover tasks.
Rental Car Facility Program Activation
ï‚· A date for the RCF Grand Opening Celebration has been set and the Activation team is meeting with
Public Affairs to plan the details in coordination with the Facility Manager. Internal and external
communication materials, such as web content for the internet and Compass page for the RCF are
being developed. The Port will also provide a PDF brochure template to the RACS to print and
distribute to their customers.