
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
March 16, 2012
Page 2 of 4
CNG station, and the Port’s error in specifying the requirements for the DDC system. To keep
the project moving, avoid impacting the opening of the RCF, and avoid additional contractor
claims for constructive acceleration, staff requests authorization to issue a change order
extending the required contract completion date by up to 94 calendar days.
BACKGROUND:
When the BMF project was advertised for construction bids, the Port and the Rental Car Industry
had established a tentative opening date for the RCF of March 2012. The BMF project includes
a new CNG station and, per the construction contract, the Port is responsible to provide the buses
for the contractor to complete the testing and commissioning of the new CNG station. In order to
complete the testing and commissioning for the new CNG station, the station needs to be fully
loaded, which requires the use of any combination of both existing employee parking and new
rental car buses. At that time the BMF project was advertised for construction bids, it was
anticipated that the new rental car busing operation would potentially have started and support
the completion and activation of the new CNG station by January 2012. Since that time, the Port
has made a number of decisions that have delayed the startup of the rental car busing operation
until April 20, 2012, and the opening date of the RCF to May 17, 2012. Given these delays, Port
staff has pursued an option to utilize Pierce Transit buses to support the completion of the CNG
station testing and commissioning effort. That work is currently scheduled for the week of
March 11, 2012, and supports a beneficial occupancy date for the new CNG station of March 30,
2012.
When the BMF project was advertised for construction bids, the Port included in the contract
documents the requirements for the DDC system. The DDC system is intended to provide a
direct communication link between the BMF systems and the Airport’s central operating systems
so that the systems in the BMF can be remotely monitored and managed. Typical systems that
are included with the DDC system include the heating and ventilation systems, fire suppression,
and water and natural gas utilities. Unfortunately at the time the project was bid the
requirements for the DDC system were incorrect and this error was not caught until work began
on the interface of the DDC system with the other systems. Port staff anticipates that the DDC
system can be corrected in March 2012, which would support a beneficial occupancy date for the
BMF building of April 12, 2012.
This time extension will allow work to proceed without forcing the contractor to either accelerate
to meet the current contractual completion date, or risk a potential claim for liquidated damages.
The 94 calendar days is based on an estimate that we will be substantially complete with the
BMF project on May 17, 2012. The Port is requesting authorization on a “Not to Exceed” basis
as the parties continue to work towards being able to complete the work as early as possible.
The 94-day extension will not affect the currently scheduled opening of the RCF.