Item No. 7c_Supp Date: December 13, 2011 Capital Improvement Projects Third Quarter Report 2011 Commission Briefing Capital Improvement Projects Overall Status of Projects • 90 Total Projects in report • 53 Projects are within or ahead of target schedule and budget • 36 Projects have either target schedule or budget off • 1 Project has both schedule and budget off Project Status Total CIPs Managed by CDD 100% 90% Project Distribution per Quarter 80% 70% 60% 50% 40% 30% 20% 10% 0% 3Q10 Report 4Q10 Report 1Q11 Report 2Q11 Report 3Q11 Report Both Schedule and Budget off 1 1 3 2 1 Either Budget or Schedule off 28 30 28 28 29 On Schedule/On Budget 45 42 43 49 45 AVIATION PROJECT SUMMARY • Six projects are behind schedule: - Water System Isolation Valve Upgrade (3 months) - The schedule was extended to avoid operational impacts during the busy holiday season. - Parking System Replacement (2 months) - Decision to utilize "best bid" procurement delayed advertisement and completion of the bid documents. Negotiations and final contract specifications are taking longer than anticipated. - Common Use Equipment Expansion (6 months) - Investigation of existing infrastructure took longer than anticipated. Removal of ticket counter scope at a late stage of design required changes to the design documents. AVIATION PROJECT SUMMARY, Cont. • Six projects are behind schedule (cont.): - Concourse D Common Use (6 months) - Construction of the mock-up casework took longer than anticipated. Gate shutdowns associated with this project are currently being coordinated with other Concourse D shutdown work. - South Satellite Concessions Project (12 months) - Design concept alternatives required more extensive review than anticipated. The new concept allows the existing duty free to remain operational during construction, but requires a longer construction period. - South Satellite Additional Gate Lobby (12 months) - Project delay was caused by delayed design negotiations and contracting. Additionally, a longer design period is required due to dependency on the South Satellite Concessions Project. AVIATION PROJECT SUMMARY, Cont. • One project is under budget: - Roof Replacement Program (~$1,000,000) - Project is scheduled to reach beneficial occupancy in October 2011 and anticipates a significant savings. SEAPORT PROJECT SUMMARY Two projects delayed/over budget:  Security Round 7 schedule - Construction bids came in over estimate, slightly delaying schedule. Commission authorized additional funding and project is within revised budget amount.  T-86 Grain Facility Modernization - Critical Work Authorization issued for additional funding to accommodate tenant's shutdown schedule. Project is in close-out phase. REAL ESTATE PROJECT SUMMARY One project is behind schedule:  FT C15 HVAC Improvements - Preliminary schematic design expected in Q3 slightly delayed to Q4. CORPORATE PROJECT SUMMARY One project with a new reportable schedule variance this quarter: - Enterprise Project Cost System (9/2012) - Configuration of the software took longer than anticipated due to resource availability and complexity of the software. One project is under budget: - Ground Transportation Management System ($150,000) - Project is in close out and will be returning savings.