AVIATION PROJECT SUMMARY, Cont.
• Six projects are behind schedule (cont.):
– Concourse D Common Use (6 months) – Construction of the mock-up
casework took longer than anticipated. Gate shutdowns associated with
this project are currently being coordinated with other Concourse D
shutdown work.
– South Satellite Concessions Project (12 months) – Design concept
alternatives required more extensive review than anticipated. The new
concept allows the existing duty free to remain operational during
construction, but requires a longer construction period.
– South Satellite Additional Gate Lobby (12 months) - Project delay was
caused by delayed design negotiations and contracting. Additionally, a
longer design period is required due to dependency on the South
Satellite Concessions Project.