Bus Maintenance Facility - Construction Contract
2011 Accomplishments
Bioswale improvements at Port property (occupied by Tyee Golf Course) adjacent to project site.
High pressure natural gas line installation at South 194
th
Street for service to CNG Fueling Station.
City of SeaTac roadway improvements at South 194
th
Street/28
th
Street South intersection.
New utilities, paving, and began landscaping at upper and lower sites.
Building weathered-in for completing interior finishes.
BMF telecommunications room ready for work by POS final build-out.
Construction has progressed to 88%.
Construction Status Summary
Overall project completion date remains at February 13, 2012.
Construction progress is approximately 88%.
Construction costs are trending to be within authorized budget.
An average of 42 construction workers on site daily.
Milestones Accomplished this Month
Bus Maintenance Building weathered in, including skylights.
Occupancy of telecom room for POS final installations.
Compressed Natural Gas (CNG) equipment delivered/installed & on-site testing commenced. Bus lift
equipment installation complete at main service bay.
Work In Progress
Bus Maintenance Facility Building: Tilt-up panel sack & patch complete, to be followed by
application of anti-graffiti coating (weather dependent). Roofing systems on all structures are
complete. Some flashing being installed at BMF clerestory skylight to complete weather protection.
Exterior siding installation at the Office areas is 80% complete. Interior wall framing is done &
drywall installation approximately 50% complete. Taping & bedding has begun. Finish painting
ongoing in service areas: approx. 50% complete. Bus lift equipment installed & operational in main
service bay. Lift for chassis wash area pending delivery. Slab placements complete, with only
grinding (performance finish) required at maintenance bay. Mechanical, special system and
electrical system rough-ins between 80 & 100%. Fixture & trim installations underway. Roof
mounted mechanical units are set & system connections ongoing.
Bus Wash Facility Building: Tilt-up panel sack & patch is complete, to be followed by application of
anti-graffiti coating (weather dependent). Electrical & mechanical rough-ins complete. Fixture &
trim installations ongoing. Bus wash equipment 90% complete. Canopy above cleaning station is
complete.
CNG Fueling Facility: Control structure & interior is complete. Panels and control equipment
installed & in process of being wired.
Site: Upper and lower site paving is 95% . Finishing sidewalks & driveways. Fencing &
landscaping between 75% - 85%. All utilities virtually complete, pending acceptance by sewer &
water district authorities.