
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
December 2, 2011
Page 2 of 4
better defined, improving the functionality of the enclosures regarding secured storage and
telephone niches as well as providing significant aesthetic improvements to the public
passageways under the sky bridge escalators.
The D-B contractor was also requested to rephase the installation of escalators at the north and
south Main Terminal (MT) STS stations from a single phase to two phases to provide improved
passenger flow during construction.
The Port received a cost proposal from the contractor to rephase the North and South MT STS
Station escalators from a single phase to two phases of construction in the amount of $316,000
for each location. At both locations, the rerouting of passengers to alternative exits during the
approximately four month construction durations as originally scoped by the Port was
determined upon further review by the Port and airline stakeholders to present unacceptable
inconveniences including increased risk of security breaches. The additional cost for each
location represents multiple mobilizations, modified hoisting of trusses, and restricted work
space.
BACKGROUND:
The Port directed the contractor to proceed with design and construction of four stainless steel
enclosures below the escalators at four MT skybridges to upgrade the area’s aesthetics for
consistency with the more modern and contemporary appearance of the South Main Terminal
and the Central Terminal. A $186,000 not-to-exceed Change Order 3 was issued with $26,000
estimated for design and $160,000 for construction. The Port is now in receipt of the final
design and cost proposal from the contractor for $425,000. An independent estimate is
underway. A final reconciliation change order will be issued after the final costs have been
established. Staff does not expect the final amount to exceed the contractor estimate of
$425,000.
Escalators 221, 222 & 224 serve the south MT STS and escalators 521, 522 and 524 serve the
north MT STS. The basis of design and schedule for each of these two locations was predicated
on the initial request for proposal that identified two phasing options for this work to allow the
contractor to complete the construction in one phase or two in an effort to shorten the overall
project duration with manageable level of disruption. The D-B contract was executed with the
north and south MT STS stations constructed in one phase at each location consistent with the
D-B contractor’s scope.
During the design of the Main Terminal escalator replacements, a more thorough review by the
Port and airline stakeholders concluded the single phase routing would result in an undesired
level of inconvenience to and potential confusion for passengers. Further, the alternate routing
was determined to increase the potential for security issues while passengers transitioned from
sterile to non-sterile areas in the terminal. By changing the phasing from one to two phases, the
existing egress routings can be maintained with only minor congestion due to the reduction in
available escalators during each construction phase. The Port is now in receipt of the final cost