COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
December 2, 2011
Page 3 of 3
CONTRACT INFORMATION:
The following information relates to the contract and competitive award:
Contract award date: May 17, 2010
Original period of performance: May 17, 2010, through January 12, 2011
Previous contract extensions: 147 Days
Contract extension in this Change Order #030: 163 Days
Contract Completion Date in Change Order #030: November 18, 2011
FINANCIAL INFORMATION:
Original contract amount: $3,892,800
Previous Change Orders Executed: $431,103
Current contract amount $4,323,903
This request, Change Order #030 $17,178
Subtotal Construction Costs $4,341,081
Anticipated WSST @ 9.5% $412,403
Revised Contract Amount $4,753,484
PREVIOUS COMMISSION ACTION:
On October 25, 2011, the Commission authorized the Chief Executive Officer to issue Change
Order #023 for a time extension of 75 days and increase the contract amount by $32,990 to
provide additional landscaping plants at the North Airport entry feature.
On January 26, 2010, the Commission authorized the Chief Executive Officer to advertise for
construction bids, award the contract and construct the NER Phase 1 project consisting of final
paving, landscaping and reclamation (CIP C800034). The estimated cost of this project,
$5,880,000, is within the previously authorized budget.
On April 11, 2006, the Commission passed Resolution No. 3559, which authorized the Chief
Executive Officer to execute an interlocal agreement with Sound Transit to establish the real
property, financial and construction arrangement for the construction of the Airport Link Project.
The Commission authorized an additional $61,411,000 for a total project-wide authorization of
$78,282,000 and authorization to enter into contracts estimated at $165,000,000.
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST:
None.