
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
October 21, 2011
Page 2 of 4
BACKGROUND:
This IDIQ is not associated with the first two phases of current PLB Replacement – Airline
Realignment CIP (C800467), the design services for which are being addressed under a separate
IDIQ contract already in place.
Through the end of 2015, Airport staff estimates that up to 15 PLBs will potentially require the
design services expected to be delivered under this contract. Historical data indicates that the
design for a PLB replacement project typically costs $35,000 to $50,000.
There are currently two capital projects that will require the type of design services expected to
be delivered under this contract. The first is C800267 – Airport Owned Gate Infrastructure II,
which continues through the end of 2014 and proposes to refurbish or replace existing Port-
owned PLBs which have reached the end of their service lives. CIP C800267 will have
sufficient funding ($2.4 million) to replace one and refurbish three PLBs. The second is a yet-to-
be-named CIP that is expected to continue through the end of 2015 and proposes to purchase
PLBs that are currently airline-owned and to refurbish or replace them as preferential and
common use gates.
Over the past several months, Port staff held long-range PLB strategy and acquisition planning
meetings in order to identify how best to procure the required PLB design services.
The scheduling of PLB replacement and refurbishment projects is relatively unpredictable and
highly dependent upon operational and capacity concerns. In the past, the utilization of this type
of IDIQ contract has proven to be an efficient, cost effective and flexible method of responding
to uncertain design requirements over a multiple-year time span. While Port staff have the skills
required to produce these designs, they do not always have the available capacity to take on
additional work. Past experience shows the Port typically has contracted with consultants for
these particular design services due to the lack of availability of Port staff, the short duration of
the assignments and the fact that the need for these services is normally intermittent in nature.
PROJECT JUSTIFICATION:
Project Objectives:
There is an ongoing requirement for design services for PLBs beyond the current renewal and
replacement and airline realignment efforts. The capacity of the current PLB Design Services
IDIQ has been depleted by the first two phases of the Airline Realignment project at Concourses
D and B as well as by the remaining work in the current PLB renewal and replacement CIP.
Additional design capacity is required to complete designs for the five PLBs that are expected to
be replaced at the North Satellite. Further, up to four Port-owned PLBs are programmed for
refurbishment or replacement through the end of 2014. Finally, there are six airline-owned PLBs
(three at the South Satellite and three at Concourse B) that are not included in the scope of the
current airline realignment CIP and will likely be acquired by the Port as they become available
for purchase.