
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
October 21, 2011
Page 3 of 4
PROJECT SCOPE OF WORK AND SCHEDULE:
Scope of Work:
This request will support the future needs to modify or replace components of mechanical and
electrical systems that have reached the end of their useful life or need to be modified or
expanded to support added customer requirements. It will provide design documents and
construction support of identified mechanical and electrical projects in addition to unknown pop-
up projects that may occur. Mechanical projects may include, but not be limited to the
following: Central Plant facilities, people and baggage conveyance systems, fire protection
systems, heating ventilation and air conditioning (HVAC) systems, stormwater treatment and
handling systems, hydraulic systems, pipe distribution systems, sanitary sewer system, controls,
plumbing and water distribution systems, passenger loading bridges, gangways, industrial waste
system upgrades, studies and lifecycle cost analyses and infrastructure upgrades to support
Airline Realignment projects. Electrical projects may include, but not be limited to: permanent
emergency generator power systems, power system feeder tap replacements, upgrading or
modifying power distribution systems, including feeders to facilities, power distribution projects,
addition of 3
rd
and 4
th
point connectors, modifications to the airfield power system, and
infrastructure upgrades to support Airline Realignment projects. Each contract will allow scope
for architectural, structural, civil, fire protection, acoustical and other ancillary design services
related to the mechanical and electrical project.
The commissioning IDIQ contracts will provide commissioning services for various projects.
During pre-construction, the consultant will review and provide comment on 60%, 90%, and
100% design drawings and specifications; prepare commissioning, training, operations and
maintenance specifications in accordance with the Port’s master specifications; develop the
Commissioning Plan; and prepare documents in support of LEED© certification where
applicable. During construction, the commissioning consultant will coordinate with the
contractor to implement the Commissioning Plan including the review and approval of
equipment submittals, installation and operational checklists, functional performance testing
criteria, and acceptance testing procedures; provide the Draft Commissioning Report for building
temporary certificate of occupancy; and prepare documents in support of LEED© certification
where applicable. Post-construction services will include a review of the contractor-provided
operation and maintenance manuals for consistency with the commissioning process; coordinate
and oversee the contractor provided equipment and system training; and provide the Final
Commissioning Report.
Schedule:
It is estimated that the contract will be executed by April 2012 and have a three-year ordering
period. The contract duration may extend beyond that period to allow work to be completed.
FINANCIAL IMPLICATIONS:
The total estimated cost for mechanical and electrical services will have a total maximum value
of $8,000,000. The total estimated cost for commissioning services will have a total maximum
value of $2,000,000. No work is guaranteed to the consultant, and the Port is not obligated to