Page 4 of 7
Work In Progress
BMF Building: Tilt-up panel sack & patch is nearly complete. Standing seam and membrane roofing
systems on all structures are effectively complete, pending installation of related flashings, gutters &
downspouts. The buildings are considered “weathered-in”, excluding skylight & window
installations. Exterior siding installation at the Office areas has begun. Interior wall framing is well
under way at the office areas. Pits for bus lift equipment are complete, and radiant heat flooring
piping has been installed in preparation for final slab placements in the bus bays. All mechanical,
special system and electrical system rough-ins have begun. Masonry work was completed by the end
of September. Contractor’s progress to deliver the telephone/comm room is on track for October 20
th
.
BWF Building: Tilt-up panel sack & patch is nearly complete. Rough-in work for all electrical &
mechanical systems is under way, and some light fixtures have been installed. Interior masonry and
wall framing is complete, awaiting completion of rough-ins & inspections before drywall cover.
CNG Facility: Metal clad siding on the control structure is complete & interior has been roughed-in,
framed and drywall installed. Control panelboard installations have begun. CNG storage tanks were
installed this past month, and other equipment has begun to arrive following factory testing.
Contractor targets all shipments complete by October 31
st
. Site: Lower site concrete paving is
complete, except for curbs at landscape islands and sidewalk installation. First layer of asphalt
paving is done, and surfacing course is on temporary hold to mitigate damage from construction
traffic. Upper lot concrete paving overlay work has begun. All utilities virtually complete, pending
acceptance by sewer & water district authorities.
Offsite: Asphalt paving repairs at 194
th
Street will be performed soon following completion of the
gas piping installed by Puget Sound Energy. Prime Contractor has re-sequenced paving at the South
194
th
St./28
th
St. South intersection to follow the PSE work.
Operation and maintenance costs of TESC and Chitosan Enhanced Filtration System (CEFS)
installations remain within budget, but the system removal has been delayed. Onset of winter weather
will increase burn rate on remaining allocated funds, and the RE is working with the Contractor on
alternate TESC solutions.
Cost Status Summary
Summary: Change Orders: 12 executed and 27 change proposals in review.
Wayfinding Signage and Curbside Modifications - Construction Contract
Construction Status Summary
Phase I contract completion date is November 18, 2011.
Phase II (Signage) can begin January 9, 2012, and contract completion date is March 1, 2012.
Milestones Accomplished this Month
Notice To Proceed for Phase I, curbing south and north portions issued.
Traffic control devices and pedestrian fencing installed at both Phase I south and north.
Phase I south demolition completed.
Work In Progress
Phase I north existing striping is being removed.
Preparing for formwork and curbing at Phase I south.
Preparing for demolition at Phase I north.