
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
October 14, 2011
Page 6 of 6
TRIPLE BOTTOM LINE SUMMARY:
This project will provide tangible improvements to the Airport’s vertical circulation capability.
Passengers will be able to depend on reliable vertical circulation means to safely and quickly
move between floors in the South Satellite, Concourse C and Main Terminal. In addition, the
modernized freight elevators will allow goods to be reliably delivered to the concession storage
areas, and safely and efficiently retrieved by concession tenants when needed. Reduced freight
and service use of passenger elevators in the North and South Satellite will also enhance
passenger travel experiences.
PROJECT SCHEDULE:
(For the Capital Funded Major Construction Contract)
Commission Authorization to Start Design October 2011
Start Design November 2011
Design Complete June 2012
Commission Authorization to Bid and Increase Budget June 2012
Bid Advertisement July 2012
Commission Authorization to Award August 2012
Construction Start October 2012
Construction Complete December 2013
(For the Expense funded RMM Major Construction Contract)
Commission Authorization to Bid and Increase Budget October 2011
Design Start October 2011
Design Complete November 2011
Bid Advertisement November 2011
Commission Authorization to Award (if necessary) December 2011
Construction Start January 2012
Construction Complete August 2013
ALTERNATIVES CONSIDERED/RECOMMENDED ACTION:
Alternative 1: The age and their obsolete technology require these elevators to be modernized to
current standards. This is the recommended alternative.
Alternative 2: The “Do Nothing” alternative results in continued customer service disruptions
and increased maintenance costs. Many parts are no longer available and have to be custom
manufactured, where possible. At some point in time, even custom fabricated replacement parts
will not be available, and the elevators will be modernized using maintenance funds, all at a
greater cost than proceeding with a designed and competitively bid modernization project.
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS:
None.
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST:
Map – Key Plan, Vertical Conveyance Modernization, Aero Phase 1