
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
October 14, 2011
Page 2 of 3
As part of the project, the Port furnished the contractor with conveyor equipment the contractor
could use at its discretion for the project along with new equipment required for the project. The
contract specification required the contractor to provide operations and maintenance manual
information on all components utilized on the project including information supporting the
existing owner-furnished conveyor materials which had been incorporated into the installation.
Through Change Order #2, the contract also came to include a substantially upgraded computer
monitoring system with revised manual information requirements.
Following the contract requirements, the contractor submitted the final operations and
maintenance manuals, which were rejected by key project stakeholders with comments to revise
and resubmit. The contractor requested clarifications on the submittal comments and asked that
the Port reconsider many of the contractually required portions of the manuals that he felt were
unnecessary and would add approximately 7,000 pages yielding an unwieldly and unusable
manual for staff. He believed the Port already had manuals for the owner-furnished equipment
and advised that other requriements were outdated and would only complicate the use of the new
manuals. The Port engaged in lengthy internal discussions between Construction Management,
Project Management, Engineer of Record, and the Conveyor and Electrical Departments.
In order to ensure that the new manuals would be current and could be efficiently used, it was
ultimately determined that the contract requirements should be changed, and the revised manuals
were submitted and approved August 15, 2011. This change order is being issued to address the
excusable 147 days of time it took for the Port and the contractor to resolve this issue and obtain
more streamlined manuals for our stakeholders, for a new completion date of August 15, 2011.
FINANCIAL ANALYSIS:
The change order is at no cost. No additional project funds are being requested as a result of this
change order.
CONTRACT INFORMATION:
The following information relates to the contract and competitive award:
Contract award date: July 12, 2010
Original period of performance: July 12, 2010, through January 8, 2011
Previous contract extensions: 72 Days
Contract extension this change order: 147 Days
Current Contract Completion Date: August 15, 2011